This is an attachment containing site pictures and requirements for Well 3 at Shaw AFB, showing the current equipment and locations that need upgrading. The images show the existing stripper level sensor system that needs to be replaced with a single ultrasonic or radar level sensor mounted on a new 4" PVC pipe, which must be marked with High High Level, High Level, Low Level, and Low Low Level indicators and include heat tracing. The attachment also shows a NEMA Premium main well motor, electrical cabinets and VFD that need to be returned to 20th CES, analyzers and plumbing to be demolished, and a potential EMCS Allen Bradley PC workstation location.
The document includes example graphics of desired HMI displays showing tower levels and motor status indicators, with specifications for a gray background interface that needs to be replicated for each well and tower. Additional requirements include installing a small drop-down wall-mounted table for water sampling, verifying supply voltage for the new main motor VFD, and maintaining existing fiber connections while removing associated conduit and cabinets. The images provide visual context for contractors to understand the scope of demolition, replacement, and new installation work required.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Atch 3-HMI Screen Reference.pdf | ||
| Atch 1-Statement of Work- VLSB 18-0010 Repair Well 3 with SCADA Upgrade.pdf | ||
| Atch 2- Shaw AFB Well Utility Controls Schematic.pdf | ||
| Atch 6-Air Force Form 66-Blank.xlsx | XLSX spreadsheet | |
| Atch 5-Pricing Sheet-Well Automation BLANK-NO FORMULA.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment 01 - Site pictures
AT 01 -1
Well 3 – Current stripper level sensor system.
Stripper Tower tank level sensor. Contractor to delete the three sensor and provide a single ultra sonic or radar level sensor. The contractor remove and install a new clear 4’’ PVC pipe.
The sensor shall be mounted to the top of the pipe. The pipe shall be marked with the High High Level, High level, Low Level, Low Low Level. The contractor shall provide the ability on the HMI to reset the rescale the sensor by running the water level up to the high level and hitting high high level set button and running the water level down to the low low level and hitting the low low level set button. The system will need to be heat traced. The system will also need to reuse or install a new pressure gauge at the bottom.
AT 01 -2
Well 3 - Main Well motor
AT 01 -3
Well 3 -
Electrical cabinet and VFD to be returned to 20th CES.
AT 01 -4
Well 3 – Cabinet to be demoed along with attached conduit. Fiber to remain.
AT 01 -5
Well 3 – Cabinet to be demoed along with attached conduit.
AT 01 -6
Potential EMCS Allen Bradley PC work station location
AT 01 -7
Well 3 -
Old Analyzers and all plumbing to be demolished
AT 01 -8
B251 Water Shop Potential display location.
AT 01 -9
Well 3 – Current transformer in the electrical room. Contractor needs to verify the supply voltage to the new main motor VFD.
AT 01 -10
AT 01 -11
Well -3 Contractor to install small drop-down wall mounted table. For the water shop to take samples.
AT 01 -12
Example of the graphics where the display shows the tower level, and which motors are running in green. Would prefer a gray background.
Example of the gray background. The contractor shall provide a display like this for each well and tower.
AT 01 -13