Atch_4_Kirwin_Office_Bldg_Bid_Schedule_Rev_1.xlsx

XLSX spreadsheet 14 KB Posted

Attached to
KS-KIRWIN NWR-REHAB HQ OFFICE & STORAGE
Solicitation number
140F0121R0090
Issued by

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

PROJECT DESCRIPTION:
Repair/replace damaged siding, eaves, soffits, roof, gutters, and downspouts. Replace the existing metal roof with an asphalt shingle roof, note there are (2) layers of Asphalt Shingles under the metal roof. Verify OSB Roof Sheathing is in good condition and replace as necessary. Replace all exterior doors and windows. Paint entire exterior to include; stucco, siding, soffits, eaves, trim, and doors. Replace existing exterior soffit lights and add additional exterior lights to be located on the drawings. Examine air flow into the Conference Room and balance system as needed, this room does not get adequate heat flow currently. Replace existing carpet and vinyl flooring with like product.
A. GENERAL CONDITIONS:
Division 1: General Requirements
Mobilization and demobilization$
Bond$
General Requirements (testing)$
General Requirements (other)$

Division 1 Total $

B. SUMMARY OF COST BREAKDOWN FOR MATERIALS, LABOR AND EQUIPMENT

Div. 2 Existing Conditions $

Div. 7 Thermal & Moisture $

Div. 8 Openings $

Div. 9 Finishes $

Div. 23 HVAC $

Div. 26 Electrical $

BASE TOTAL $ $0

OVERHEAD AND PROFIT (percentage) % $ 0

TOTAL PLUS OVERHEAD AND PROFIT $ $0

*Install Roof Sheathing (includes O, H & P) Unit Price SF $

*Roof Sheathing may or may not need to be replaced. See Specification 061600. The line item above is for a Unit Price per square foot, based on need, as identified by the contractor during demolition. The contractor will have the Government, FWS inspectors verify the proposed quantity of sheathing to be replaced. The quantity may be none, or some of the roof sheathing. Once the quantity and total price are agreed to by the contractor and the Government, a contract modification will be issued to add the work to the contract.

&"Times New Roman,Regular"&12BIDDING SCHEDULE

Kirwin Office Renovation - 21-027 (Office Building) Kirwin NWR

Kirwin, KS

File details come from the government source that posted it. Updated .