This document includes a federal contract solicitation and related schedule of material submittals. The solicitation seeks fixed-price quotes to remove, dispose of, and replace six live front transformers and ten unfused transformers at Cannon Air Force Base in New Mexico. The work must be completed within 180 days of award. Quotes are due by June 12, 2020. The requirement is set aside exclusively for Historically Underutilized Business Zone (HUBZone) small businesses. The North American Industry Classification System code for this effort is 335311 for power and specialty transformer manufacturing. A site visit is scheduled for potential offerors on May 21, 2020, with limited attendance due to COVID-19 restrictions. The solicitation and any amendments will be posted electronically to the Federal Business Opportunities website. Offerors must register in the System for Award Management to be eligible for award. The related schedule of material submittals lists submission requirements and deadlines for project documents throughout the design and construction phases.
View the file
Other files for this federal contract opportunity
Show all 33
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AF66
| SCHEDULE OF MATERIAL SUBMITTALS | PROJECT NUMBER | PROJECT TITLE | SOLICITATION / CONTRACT NO. | |||||||||||||||||||||
| 1067228 | Replace Live Front and Unfused Transformers | |||||||||||||||||||||||
| TO BE COMPLETED BY THE PROJECT ENGINEER | TO BE COMPLETED BY CONTRACT ADMINISTRATOR | |||||||||||||||||||||||
| LINE NUMBER | ITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTAL | NUMBER OF COPIES REQUIRED | REQUIRED SUBMISSION DATE | DATE RECEIVED IN CONTRACTING | DATE TO CIVIL ENGINEERING | RETURN SUSPENSE DATE | SUBMITTAL NUMBERS | DATE CONTRACTOR NOTIFIED | CONTRACTOR RESUBMITTAL | FINAL APPROVAL | REMARKS | |||||||||||||
| CERTIFICATION OF COMPLIANCE | SHOP DRAWINGS | SAMPLES | COLOR SELECTION | MFG'S RECOMMENDATION | MANUFACTURER'S WARRANTY | CATALOG DATA | OPERATING INSTRUCTIONS | SCHEDULES, LISTINGS, REPORTS, PLANS | TECHNICAL DATA | TEST REPORTS | FIELD REPORTS | OTHER | ||||||||||||
| APPROVED | DIS- APPROVED | |||||||||||||||||||||||
| 1 | Project Schedule | 1 | ||||||||||||||||||||||
| 2 | Project Progress Report/Meeting Minutes | 1 | ||||||||||||||||||||||
| 3 | 65% Design Analysis | 1 | ||||||||||||||||||||||
| 4 | 65% Design Drawings | 1 | ||||||||||||||||||||||
| 5 | 65% Specifications | 1 | ||||||||||||||||||||||
| 6 | 65% Civil Works IDIQ Cost Estimate | 1 | ||||||||||||||||||||||
| 7 | 65% RS Means Cost Estimate | 1 | ||||||||||||||||||||||
| 8 | 65% Scope of Work | 1 | ||||||||||||||||||||||
| 9 | 65% Schedule of Material Submittals Registry | 1 | ||||||||||||||||||||||
| 10 | 65% Equipment Cutsheets | 1 | ||||||||||||||||||||||
| 11 | 95% Design Analysis | 1 | ||||||||||||||||||||||
| 12 | 95% Design Drawings | 1 | ||||||||||||||||||||||
| 13 | 95% Specifications | 1 | ||||||||||||||||||||||
| 14 | 95% Civil Works IDIQ Cost Estimate | 1 | ||||||||||||||||||||||
| 15 | 95% RS Means Cost Estimate | 1 | ||||||||||||||||||||||
| 16 | 95% Scope of Work | 1 | ||||||||||||||||||||||
| 17 | 95% Schedule of Material Submittals Registry | 1 | ||||||||||||||||||||||
| 18 | 95% Equipment Cutsheets | 1 | ||||||||||||||||||||||
| 19 | 100% (Issue for Construction) Design Analysis | 3 | ||||||||||||||||||||||
| 20 | 100% (Issue for Construction) Design Drawings | 3 | ||||||||||||||||||||||
| 21 | 100% (Issue for Construction) Specifications | 3 | ||||||||||||||||||||||
| 22 | 35% Civil Works IDIQ Cost Estimate | 1 | ||||||||||||||||||||||
| 23 | 65% RS Means Cost Estimate | 1 | ||||||||||||||||||||||
| 24 | 95% (Issue for Construction) Scope of Work | 1 | ||||||||||||||||||||||
| 25 | 100% (Issue for Construction) Schedule of Material Submittals Registry | 3 | ||||||||||||||||||||||
| 26 | 100% (Issue for Construction) Equipment Cutsheets | 3 | ||||||||||||||||||||||
| 27 | NPI Description, Cost, Specification | 3 | 3 | 3 |