Atch 3_Floor Plan.xlsx
XLSX spreadsheet 23 KB Posted
- Solicitation number
- 12639523Q0265
About this file
This document contains a floor plan for the demolition and renovation of a laboratory space. The floor plan details the existing layout of the laboratory including HVAC systems, lighting fixtures, doors, benches, cabinets, and other fixtures. The renovation work includes removing interior walls and ceilings, relocating doors and fixtures, extending an interior wall, and installing a new drop ceiling, HVAC ducts, sprinklers, and lighting. A walk-in cooler measuring approximately 14' x 18' x 9'6" will also be installed. The related federal contract opportunity is solicitation number 12639523Q0265 from the Department of Agriculture Animal and Plant Health Inspection Service Marketing and Regulatory Programs Business Services for demolition and renovation work of the laboratory space located in Gastonia, North Carolina.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFIs and responses.docx | DOCX document | |
| Atch 2_Federal construction wage rates_Gaston County.pdf | ||
| Atch 1_Statement of Work.docx | DOCX document | |
| 12639523Q0265.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Current
| 15' 10" | HVAC Return* | |||||
| Light Fixture* | ||||||
| O | O | |||||
| HVAC Supply | Light Fixture | HVAC Supply | Light Fixture | |||
| O |
PCR LAB 17' 6" Light Fixture*
| 9' ceiling, solid | ||
| 9' 6" wall to open plenum | ||
| NUCLEIC ACID LAB | HVAC Supply* |
HVAC Supply Light Fixture HVAC Supply Light Fixture
Light Fixture*
| O | O | |
| 36" door |
| O | ||||||||
| 15' 10" | ||||||||
| HVAC Supply | Light Fixture | Light Fixture | Light Fixture* | |||||
| 5' 1" | 36" door | |||||||
| 22' 11" | ||||||||
| O | O | |||||||
| Sprinkler Head | Sprinkler Head | 8' 10" |
| 41" door | |
| FRONT OF BUILDING |
BENCH
BENCH
INSTRUMENT
SINK
SINK
CABINETS
CABINETS
CABINETS
CABINETS
CABINETS
CABINETS
Actions
| Remove inside walls all the way to the roof | |
| Remove solid ceiling over entire space | |
| Disconnect and cap eletrical outlets above ceiling for each removed wall | |
| Disconnect and cap plumbing drain at floor level | Inside wall contains sink and drain; drain may be reused for walking freezer |
| Remove desingated casework and benches without damaging them. Place in designated storage area. | |
| Disconnect and cap eletrical outlets above ceiling originally found in casework. | |
| Temporarily remove lighting (re-install with drop ceiling) | |
| Temporarily remove HVAC dusts (re-install with drop ceiling) | |
| Temporarily cap sprinklers ( re-install with drop ceiling) | |
| Remove and relocate 41" door on front hallway. | |
| Relocate electrical outlet displaced by relocation of door on front hallway. | |
| Extend inside wall approx 5' (height to the roof) to join perpendicular with front hallway wall. |
Remodeled
| 1 | ||||||||||||||||||||||||
| HVAC Return* | 2 | |||||||||||||||||||||||
| Light Fixture* | 3 | |||||||||||||||||||||||
| O | O | 4 | ||||||||||||||||||||||
| Sprinkler Head | Sprinkler Head | 5 | ||||||||||||||||||||||
| HVAC Supply | Light Fixture | HVAC Supply | Light Fixture | O | 6 | |||||||||||||||||||
| approx 4' clearance | 7 | |||||||||||||||||||||||
| 8 | 9' 6" wall to open plenum | |||||||||||||||||||||||
| 9 | replace solid ceiling with accoustic drop ceiling | |||||||||||||||||||||||
| 10 | ||||||||||||||||||||||||
| PCR LAB | Light Fixture* | 11 | ||||||||||||||||||||||
| 12 | ||||||||||||||||||||||||
| 13 | ||||||||||||||||||||||||
| 14 | ||||||||||||||||||||||||
| NUCLEIC ACID LAB | HVAC Supply* | 15 | ||||||||||||||||||||||
| Sink Drain? | 16 | |||||||||||||||||||||||
| X | 17 | |||||||||||||||||||||||
| 18 | DIME CALC | |||||||||||||||||||||||
| 19 | 0.6363636364 | = 14 / 22 | ft | |||||||||||||||||||||
| 20 | 0.6363636364 | = 21 / 33 | cells | |||||||||||||||||||||
| 21 | ||||||||||||||||||||||||
| 22 | ||||||||||||||||||||||||
| 7' | 23 | |||||||||||||||||||||||
| 24 | ||||||||||||||||||||||||
| 25 | ||||||||||||||||||||||||
| 26 | ||||||||||||||||||||||||
| 22' 11" | 27 | |||||||||||||||||||||||
| 28 | ||||||||||||||||||||||||
| 29 | ||||||||||||||||||||||||
| 36" door | 30 | |||||||||||||||||||||||
| 31 | ||||||||||||||||||||||||
| 25' | 32 | |||||||||||||||||||||||
| 33 | ||||||||||||||||||||||||
| 41" door | ||||||||||||||||||||||||
| FRONT OF BUILDING | ||||||||||||||||||||||||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | ||||||||
| DIME CALC | ||||||||||||||||||||||||
| 0.72 | = 18 / 22 | ft | ||||||||||||||||||||||
| 0.7647058824 | = 13 / 17 | cells |
SINK
WALK IN COOLER
approx 14' w x 18' L x 9'6" H inside 240 sq ft
CABINETS
CABINETS
CABINETS
CABINETS
CABINETS
BENCH
File details come from the government source that posted it. Updated .