Atch 3_Drawings_Bldgs C3 C4 C8.pdf

PDF 3 MB Posted

Attached to
Natural Gas Fuel Lines, Ames
Solicitation number
12639523Q0201
Issued by

View the file

Other files

File Type Posted
12639523Q0201-0002.pdf PDF
Atch 2_SOW Bldg C3 C4 C8 Nat Gas Supply.docx DOCX document
12639523Q0201-0001.pdf PDF
Site visit attendance.pdf PDF
Contractor questions.docx DOCX document
Atch 1_Federal Construction Wage Rates_Story County.pdf PDF
Atch 2_SOW Bldg C3 C4 C8 Nat Gas Supply.docx DOCX document
12639523Q0201.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Location Coordinator:Contracting Officer Rep.:Contracting Officer:Engineering Project Manager:

Task

Order #:

Drawing Title:PROJECT TITLE:

FEU Project #:

Drawing Number:

Agricultural Research Service U.S. Department of Agriculture

NCAH

1920 Dayton Avenue Ames, Iowa 50010

Revision:

Client:

Sheet: Of

Designer:

Date:

Date:

UNITED STATES DEPARTMENT OF AGRICULTURE

AGRICULTURE RESEARCH SERVICE

NATIONAL CENTERS FOR ANIMAL HEALTH

WORK

AREASITE

ENTRANCE

Note: Temporary Site Entrance during Summer/Fall 2023 will be at this location.

12639523Q0201, Attachment 3

Order #:

Drawing Title:PROJECT TITLE:

FEU Project #:

Drawing Number:

Agricultural Research Service U.S. Department of Agriculture

NCAH

1920 Dayton Avenue Ames, Iowa 50010

Revision:

Client:

Sheet: Of

Designer:

Date:

Date:

1) Install approximately 80' of 1" HDPE Fuel Line from existing 2" HDPE, 30 psig Fuel Line to Building C3. Connect new 1" Fuel Line to 2" Fuel line using 2x1 Electrofusion Tap Tee. Install 1" Anodeless Riser with 1" Riser cock, regulator and Meter Set.

2) Install approximately 100' of 1" HDPE Fuel Line from existing 2" HDPE, 30 psig Fuel Line to Building C4. Connect 1" Fuel Line to 2" Fuel line using 2x1 Electrofusion Tap Tee. Install 1" Anodeless Riser with 1" Riser cock, regulator and Meter Set.

3) Extend approximately 350' of 2" HDPE Fuel Line from existing 2" HDPE, 30 psig Fuel Line to Building C8. Line is to be bored under existing road. Extend Fuel line 15' beyond east building line and install 2" HDPE Electrofusion Cap.

MB-401 C3

C4

C5

C7

Existing 2" HDPE, 30 psig Fuel Line

Fuel Line Isolation Valve at MB-401 Meter Set

Install 1" HDPE Fuel Lines to C3 and C4

Extend 2" HDPE, 30 psig Fuel Line to C8

Order #:

Drawing Title:PROJECT TITLE:

FEU Project #:

Drawing Number:

Agricultural Research Service U.S. Department of Agriculture

NCAH

1920 Dayton Avenue Ames, Iowa 50010

Revision:

Client:

Sheet: Of

Designer:

Date:

Date:

N

Install 1" HDPE Fuel lines to C3 and C4. Install Anodeless Risers with 1" Riser cocks, regulators and Meter Sets. Connect Meter set to existing fuel line into buildings and Convert C3 and C4 from Propane to Natural Gas.

Project to Extend Natural Gas Fuel Line to Buildings

C3, C4, and C8

New 1" HDPE Fuel Lines to C3 and C4

New 1" Riser, Regulator, and

Meter Set

Existing 2" HDPE, 30# Fuel Line

Order #:

Drawing Title:PROJECT TITLE:

FEU Project #:

Drawing Number:

Agricultural Research Service U.S. Department of Agriculture

NCAH

1920 Dayton Avenue Ames, Iowa 50010

Revision:

Client:

Sheet: Of

Designer:

Date:

Date:N

Project to Extend Natural Gas Fuel Line to Buildings

C3, C4, and C8

Existing 2" HDPE, 30# Fuel Line

Extend 2 HDPE Fuel line to C8. Cap new 2" Fuel Line to C8 approximately 10' east of east building line.

Extend 2" HDPE Fuel Line to C8 for Future

Order #:

Drawing Title:PROJECT TITLE:

FEU Project #:

Drawing Number:

Agricultural Research Service U.S. Department of Agriculture

NCAH

1920 Dayton Avenue Ames, Iowa 50010

Revision:

Client:

Sheet: Of

Designer:

Date:

Date:

Project to Extend Natural

Gas Fuel Line to Buildings C3, C4, and C8

Typical Diaphragm Meter Set

Arrangement

Disconnect Propane supply and install C4 Meter Set at this location

Disconnect Propane supply and install C3 Meter Set at this location. Connect to existing underground fuel line.

Remove existing regulator at C4 and replace with new pipe.