This is a Statement of Work (SOW) for the repair and maintenance of the Marshland District Maintenance Shop Complex at St. Croix National Scenic Riverway in Pine City, Minnesota (15975 State Highway 70). The project encompasses comprehensive repairs and upgrades to five buildings and associated infrastructure within a fenced maintenance complex. Work must be completed within 90 calendar days of the Notice to Proceed and includes all supply lead times, material deliveries, installation, and final commissioning.

The scope includes exterior and interior repairs across all five structures: the Main Shop (40' x 60' Star Manufacturing building), Wood Shop (30' x 50' pole building), Small Storage Building (32' x 12'), Large Pole Building (56' x 30'), and Gas Shed (16' x 12'). Specific work items include replacing a 200-amp and 100-amp electrical panels in the Main Shop; replacing six and eight high bay LED lights in the Main Shop and Wood Shop respectively; replacing two 75,000 BTU radiant tube heaters (Reznor brand or equivalent); painting all exterior surfaces with light grey finish (approximately 5,950 total square feet across all buildings); replacing multiple metal insulated service doors with specified hardware; replacing nine total sectional overhead garage doors (10' x 10'); replacing roof ridge cap on the Gas Shed; replacing a powered gate opener with electrical service running approximately 90 feet from a new panel; repairing and replacing approximately 150 feet of 7-foot-tall chain link fence with 3-strand barbed wire top; and related site work. All work must comply with the 2026 National Electric Code and 2024 International Building, Fire, Plumbing, Mechanical, Energy Conservation, Wildland Urban Interface, and Fuel Gas Codes. Contractors must submit accident prevention plans, construction schedules with critical path analysis, quality control plans, and comply with National Park Service regulations including weekly toolbox safety meetings, photo documentation, environmental protection measures, and noise limitations.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Div. 1 V. 2023-11-11 Page | 1

St. Croix National Scenic Riverway

401 N Hamilton St., St. Croix Falls, WI 54024

Repair and Maintain Marshland District Maintenance Shop

Complex Facilities

PMIS 317736

PROJECT SPECIFICATIONS

NATIONAL PARK SERVICE

2026-03-01

Page | 2

TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

Section 01 10 00 - Division 01 Short Form General Requirements

DIVISION 07 – THERMAL and MOISTURE PROTECTION Section 07 72 00 Roof Accessories

DIVISION 08 – OPENINGS

Section 08 11 00 Hollow Metal Doors and Frames Section 08 36 10 Overhead Garage Doors Section 08 70 00 Finish Hardware Section 08 71 23 Commercial Door Operators

DIVISION 09 – FINISHES

Section 09 91 13 Exterior Painting

DIVISION 23 HVAC

Section 23 54 16 Gas Radiant Tube Heater

DIVISION 26 ELECTRICAL

Section 26 05 50 Wiring Methods Section 26 56 60 Lighting Systems

DIVISION 32 Exterior Improvements Section 32 31 11 Gate Operators

SITE PLAN – APPENDIX A

PHOTOGRAPHS -- APPENDIX B

Page | 3

SECTION 01 10 00

DIVISION 1 SHORT FORM GENERAL REQUIREMENTS

PART 1 – GENERAL

ITEM 1 - DESCRIPTION OF WORK

1.1 Background: The Marshland Maintenance complex includes 5 buildings; A Main shop, Wood shop, small storage building, large pole building, and a small equipment/gas shed. The maintenance complex is entirely secured by a fence and does not include any public access.

There is a public parking area and trail head along the road leading to the secured maintenance complex.

1.1.1 The Main shop is a Star Manufacturing “Red Iron” Structure built in the early 1980s.The overall building is 40-feet x 60-feet with a 20-feet x 40-feet area utilized as heated administrative space and the remainder as heated storage and work space.

1.1.2 The Wood shop is a 30-feet x 50-feet insulated pole building that is used for carpentry work and storage.

1.1.3 The small storage building is 32-feet x 12-feet with steel exterior and is used as cold storage of smaller equipment.

1.1.4 The large pole building is 56-feet x 30-feet wood framed with steel exterior. It is used for cold storage of larger equipment.

1.1.5 The gas shed is 16-feet x 12-feet and block with a steel frame. The gas storage building is cold storage of the district’s fuel cans and small engine equipment.

1.2 Work Covered by the Contract Documents:

A. Project Location: 15975 State Highway 70, Pine City MN 55063

B. This project will address exterior and interior repairs to five buildings and the surrounding chain link fence. All five buildings’ exteriors will be cleaned, prepped, and painted for the first time since 2009. The main shop requires the current electrical panel to be replaced and updated, The replacement of the 1996 Reznor radiant shop heater, and the replacement of overhead high bay LED shop lights. The Wood shop requires the replacement of two 3’ steel service doors, replacement of the 10’ x 10’ insulated overhead garage door, and replacement of the 1996 Reznor radiant shop heater. The small storage building only requires painting.

The large pole building requires the replacement of two 2’-8” steel service doors, and replacement of three 10’ x 10’ overhead garage doors. The Gas shed requires the replacement of 16’ of clear ridge cap on the roof, and replacement of the 6’-0” steel double door. Another item requiring work will be the 400’ chain link fence and gate opener. About

150’ of fence requires minor repairs to fix connections and straighten, and replacement of a nonoperational powered gate opener.

1. Work on the main shop consists of;

A. Replace the main 200amp Cutler Hammer electrical panel and the 100amp sub panel, also Cutler Hammer, with new panels.

Page | 4

a. Provide 200 amp NQ Circuit Breaker Panelboard as manufactured by

Schneider Electric, or equal from approved manufacturers.

i. Approved Manufacturers

1. Eaton

2. Siemens

3. Schneider

ii. Size: 200 amp, 40 space

iii. Provide panelboard with Bolt-on breakers

iv. Provide new breakers to match existing branch circuits amperage

v. Ensure that grounding electrode system and grounding electrode conductor are reinstalled to meet 2026 National Electric Code requirements. Existing system meets requirements.

vi. Contractor to verify available fault current from utility in sizing

AIC rating of main breaker in 200-amp panelboard.

b. Provide 100 amp NQ Circuit Breaker Panelboard as manufactured by

Schneider Electric, or equal from approved manufacturers.

i. Approved Manufacturers

1. Eaton

2. Siemens

3. Schneider

ii. Size: 100 amp, 20 space

iii. Provide panelboard with Bolt-on breakers

iv. Provide new breakers to match existing branch circuits amperage

v. Provide new branch circuit for gate opener, coordinate size with gate opener requirements

c. Modify existing conduits to accommodate new panel board enclosures.

Coordinate with COR.

B. Replace 6 high bay overhead LED lights (see attached cut sheet).

a. The current lights have exposed wires and splices from the conduit to the fixture. Replacements will be installed with appropriate conduit and wiring boxes to conceal wiring per code requirements.

b. Color temperature: 4000 Kelvin

C. Replacement of one 75,000BTU radiant tube shop heater, Reznor brand or equivalent (see cut sheet provided). Heater will be vented through the wall according to manufactured specifications.

D. Paint the entire exterior surface of the exterior walls and trim approximately

2900sqft.

a. The color will be light grey in color. Contractor to provide samples for approval by COR.

b. Contractor must confirm quantity.

c. The condition and preparation requirements for all surfaces shall be in accordance with the most recent edition of the MPI Repainting Manual requirements.

2. Work on the Wood shop consists of;

A. Replace 2 metal insulated exterior service doors, frames and hardware. 36”x84”.

i. Doors to match existing unless otherwise noted.

ii. Contractor to verify all dimensions.

Page | 5

iii. Doors to swing in direction of egress from the building.

iv. Provide door hardware (for each door)

1. 3 Hinges – FBB199 NRP 4-1/2” x 4-1/2”, US32D

2. 1 Storeroom lockset – 45H 7D 15J, 626

3. Closer – LCN 4111 with Hold Open, AL

4. Threshold – 171A, AL

5. Perimeter Gasketing – 290AS, AL

6. Pest Control Sweeps – 162622, AL

7. Rain Drip – 346C, AL

8. Kick Plate – 8” x 12” LDW, US32D

v. See specifications.

B. Replace 8 high bay overhead LED lights (see attached cut sheet).

i. The current lights have exposed wires and splices from the conduit to the fixture. Replacements will be installed with appropriate conduit and wiring boxes to conceal wiring per code requirements.

ii. Color temperature: 4000 Kelvin

C. Replace 1 overhead insulated garage door, rails, and motor. Garage door is

10’x10’.

i. Match existing unless noted otherwise.

ii. Provide insulated garage door with steel back panels to protect insulation.

iii. Contractor must confirm size, thickness, profile, and color and submit for

COR approval prior to ordering.

D. Paint the entire exterior surface of the exterior walls and trim approximately

1650sqft.

i. The color will be light grey in color. Contractor to provide samples for approval by COR.

ii. Contractor must confirm quantity.

iii. The condition and preparation requirements for all surfaces shall be in accordance with the most recent edition of the MPI Repainting Manual requirements.

E. Replacement of one 75,00BTU radiant tube shop heater, Reznor brand or equivalent (see cut sheet provided).Heater will be vented through the wall according to manufactured specifications.

3. Work on the Small Storage building consists of;

A. Paint the entire exterior surface of the exterior walls and trim approximately

400sqft.

i. The color will be light grey in color. Contractor to provide samples for approval by COR.

ii. Contractor must confirm quantity.

iii. The condition and preparation requirements for all surfaces shall be in accordance with the most recent edition of the MPI Repainting Manual requirements.

4. Work on the Large Pole building consists of;

A. Replace 2 metal insulated exterior service doors, frames and hardware. 32”x84”.

i. Doors to match existing unless otherwise noted.

ii. Contractor to verify all dimensions.

iii. Doors to swing in direction of egress from the building.

iv. Provide door hardware (for each door)

Page | 6

1. 3 Hinges – FBB199 NRP 4-1/2” x 4-1/2”, US32D

2. 1 Storeroom lockset – 45H 7D 15J, 626

3. Closer – LCN 4111 with Hold Open, AL

4. Threshold – 171A, AL

5. Perimeter Gasketing – 290AS, AL

6. Pest Control Sweeps – 162622, AL

7. Rain Drip – 346C, AL

8. Kick Plate – 8” x 12” LDW, US32D

v. See specifications.

B. Replace 3 overhead uninsulated garage doors, rails, and motors. Garage doors are 10’x10’.

i. Match existing unless noted otherwise.

ii. Contractor must confirm size, thickness, profile, and color and submit for

COR approval prior to ordering.

C. Paint the entire exterior surface of the exterior walls and trim approximately

1800sqft.

i. The color will be light grey in color. Contractor to provide samples for approval by COR.

ii. Contractor must confirm quantity.

5. Work on the Gas Shed building consists of;

A. Replacement of 16’ of clear ridge cap on existing roof surface.

B. Replace 1 metal insulated exterior pair of service doors, frames and hardware.

72”x84”.

i. Doors to match existing unless otherwise noted.

ii. Contractor to verify all dimensions.

iii. Doors to swing in direction of egress from the building.

iv. Provide door hardware.

1. 6 Hinges - FBB199 NRP 4-1/2” x 4-1/2”, US32D

2. 2 Flush Bolts – 555, US26D

3. 1 Storeroom lockset – 45H 7D 15J, 626

4. 1 Astragal – 355CS, AL

5. 2 Overhead Stops - #9 with Hold Open, 630

6. 1 Threshold – 171A, AL

7. 1 Perimeter Gasket – 290AS, AL

8. 2 Pest Control Sweeps – 162622, AL

9. 1 Rain Drip – 346C, AL

10. 2 Armor Plates – 30”x2” LDW, US32D

v. See specifications.

C. Paint the entire exterior surface of the exterior walls and trim approximately

100sqft.

i. The color will be light grey in color. Contractor to provide samples for approval by COR.

ii. Contractor must confirm quantity.

iii. The condition and preparation requirements for all surfaces shall be in accordance with the most recent edition of the MPI Repainting Manual requirements.

6. Work on the Complex Fence Consists of;

A. Replace approximately 90ft of 7’ tall chain link fence with 3 strand barbwire top to match existing fence. New fence will match existing fence construction.

Page | 7

i. Existing section of fence will be completely removed. Posts and footings will be pulled and all holes will be filled and compacted with suitable soil.

All removed material will be lawfully disposed of off NPS property.

ii. New fence will be 7 foot-high K-Klass (KK) chain-link fence, constructed of 2-inch mesh, galvanized before weaving (GBW), 9-gauge fabric, matching the surrounding existing fence construction. Fence construction includes 3” terminal posts, 2 ½” line posts, 1 5/8 continuous top rail and 3 strands of barbwire on top.

B. Replace one section of existing chain link fence, approximately 10’. Currently the fence connecting to the wood shop has shifted away from the building and has created a gap that is a security concern. Replace the approximate 10’ section so that there is less than a 6” space between the fence and building. Refer to Wood

Shop Fence Image.

C. Removal of old gate opener, and installation of new opener.

i. Remove all components of the existing gate opener. Motor, chain, sensors, and key pad. .

ii. New opener will match specifications found in section 32 31 11.

iii. Installation of new electrical service required for the opener is required.

Nearest electrical supply is approximately 90’ from opener location.

iv. Provide power from new 100-amp panel board installed in main shop as part of this scope of work.

v. Circuit must be in approved raceway. Provide duct seal on each end.

Coordinate conduit path with COR.

1. Must meet minimum cover requirements of 300.5.

2. Any above grade conduit shall be Schedule 80.

C. Contractor to provide third-party inspection of electrical work through commercial inspection agency prior to final inspection by COR.

a. Third party inspection agency to be licensed by the state. Provide verification to COR prior to inspections.

b. Since this is on Federal land, no local permits are required.

c. Inspector to confirm that all work complies with requirements of 2026 National Electric

Code.

D. Contractor to follow all applicable codes.

E. Applicable Codes:

a. 2026 National Electric Code

b. 2024 International Building Code

c. 2024 International Existing Building Code

d. 2024 International Fire Code

e. 2024 International Plumbing Code

f. 2024 International Mechanical Code

g. 2024 International Wildland Urban Interface Code

h. 2024 International Fuel Gas Code

i. 2024 International Energy Conservation Code

Page | 8

F. All work will be performed under a single contract.

G. Period of performance: Work shall be completed within 90 calendar days of the start date provided on the Notice to Proceed.

a. Clarification: The Notice to Proceed will be issued with a period of performance that is all inclusive of supply lead times, material deliveries, decommissioning, installation, anticipated average weather days for location, final commissioning, and acceptance of completed work. The contractor will be expected to provide a project schedule with adequate critical path details to ensure all work is completed within the stated calendar days from issuance of the Notice to Proceed. If weather impacts project beyond typical average weather patterns, contractor shall provide documentation in request for additional days.

1.3 Existing Condition Protections:

A. Preservation of Historical and Archeological Fabric:

i. The Historic and Archeological Data Preservation Act of 1974 provides for the preservation of historical and archeological data that might otherwise be lost as the result of alterations to the terrain caused by a federal or federally licensed activity or program.

ii. IF, in connection with operations under this contract, the Contractor, subcontractors, or employees of any of them, discovers, encounters or becomes aware of any possible historical or archeological data, objects or sites of cultural value on the project area, such as historical ruins, graves or grave markers, fossils, or artifacts, the Contractor shall immediately suspend all operations in the vicinity of the discovery and notify the

Contracting Officer immediately, when safe to do so, and follow up in writing within 2 days, giving the location and nature of the findings. No objects of cultural resource value may be removed. Contracting Officer will contact other entities as required.

iii. Where appropriate by reason of discovery, the Contracting Officer may order delays in the time of performance and/or changes in the work. If such delays and/or changes are ordered, the time of performance and contract price shall be adjusted in accordance with Changes clause.

iv. The Contractor will be responsible for protecting the cultural resources within and adjacent to the project area from damage. In addition, the Contractor will be liable for all damage to the cultural resources caused by their actions or the actions of their agents or representatives. The Contractor shall immediately notify the Contracting

Officer or their representative if any damage occurs to any cultural resource and immediately suspend work in the area in which damage has occurred until authorized to proceed.

v. The Contractor agrees to include this language within all subcontracts.

ITEM 2 – PROTECTING EXISTING UTILITIES

2.1 Protecting Existing Utilities: Notify Contracting Officer (CO), Contracting Officer’s Representative

(COR) and utility companies as required to request location services prior to and to coordinate any excavation/digging operations, and/or for demolition if within Scope of Work.

Page | 9

2.2 Contractor shall be responsible for locating and preventing damage to known utilities on site or indoors. If contractor damage occurs, alert CO and COR as soon as safely possible, and repair utility at no additional expense to the Government. If damage occurs to an unknown utility, contact CO and COR as soon as safely possible.

2.3 Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated below:

A. Notify CO and COR not less than two business days in advance of proposed utility interruptions.

B. Hours for Utility Shutdowns: Shutdowns shall not exceed 2 to 3 hours. Temporary provisions will be needed by the Contractor for periods longer than stated allowance or if required for critical systems as determined by COR.

ITEM 3 - CONTRACTOR’S USE OF PREMISES

3.1 Conduct of Operations: At all times the contractor shall conduct his operations in conformance with the rules and regulations promulgated by the Secretary of the Interior for the National Park

Service, and applicable park rules and regulations prescribed by the Park Superintendent.

Superintendent's Compendium - Saint Croix National Scenic Riverway (U.S. National

Park Service)

A. Communications: Contractor shall provide the Contracting Officer and COR with methods of communications including land and/or cell phone numbers (note some areas of work have limited service coverage), email and in case of emergency 24-hour contact options for duration of time operations.

B. No signs or advertisements (except those specified herein and as required for safety) shall be displayed on the construction site or within the park unless approved by the Contracting

Officer.

C. Smoking is not permitted within any Federal building or within 25 feet of entrances, operable windows, or outdoor air intakes.

D. Public Use of Site: Contractor shall at all times conduct operations to ensure the least inconvenience to the public. The Marshland Maintenance complex is not open to the public, but does serve as a duty station and hub of operations for a number of staff.

3.2 On-site work hours: Work shall be generally performed during normal business working hours of

7 a.m. to 4 p.m., Monday through Friday, except when otherwise indicated.

A. Work on Saturdays, Sundays, Federal holidays, early morning, or at night may not be performed without prior consent from the CO and COR. Submit requests for work outside of the stated normal business hours to the CO and COR for approval at least 48 hours in advance of the work.

Page | 10

The following Federal holidays are observed by the National Park Service:

New Year Day

Martin Luther King, Jr’s Birthday

Washington’s Birthday

Memorial Day

Juneteenth National Independence Day

Independence Day

Labor Day

Columbus Day

Veterans Day

Thanksgiving Day

Christmas Day

B. Note: Any of the above holidays falling on a Saturday will be observed on the preceding

Friday; holidays falling on Sunday will be observed on the following Monday. The specific day that each holiday is recognized for each year can be found at the following site: Federal

Holidays (opm.gov).

3.3 Contractor Use of Site:

A. General: Contractor shall have limited use of the site for construction operations. Limit use of premises to construction areas 12’ around each building. Please refer to the “Marshland

Maintenance Complex Arial” for staging areas. Do not disturb portions of Project site beyond areas in which the Work is indicated.

B. Driveways and Entrances: Keep driveways, access roads, and entrances serving premises clear and available to Government, Government's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials. Schedule deliveries to minimize use of driveways and entrances.

C. Do Not disturb site outside of noted disturbance area, including earthwork and clearing of vegetation, to:

1. 10 feet beyond building perimeters

2. 8 feet beyond surface walkways, patios, surface parking, fencing and utilities.

Contractor shall provide appropriate matts for equipment on vulnerable areas to reduce soil compaction. Contractor shall remediate soil compaction as directed to do so by the CO/COR.

D. Utilities

1. General: Cost or use charges for temporary facilities shall be included in the Contract Sum as required.

2. Water Service: Water from existing water system is available for use without metering and without payment of use charges. Provide connections and extensions of services as required for construction operations without any additional permit costs. Use resources wisely and minimize waste of water.

Page | 11

3. Electric Power Service: Electric power from existing system is available for use without metering and without payment of use charges. Provide connections and extensions of services as required for construction operations without any additional permit costs. Power may or may not meet your construction power tool requirements, provide generators if questionable. Use power in a resourceful manner and avoid excess power waste.

4. Waste Operation:

a. Toilets: Contractor must provide toilets for contractor personnel, sufficiently lighted and ventilated toilet facilities in weatherproof, sight proof, handicap accessible (if required), sturdy enclosures with privacy locks. Coordinate with COR for approved location if not shown on attached site plan. Waste Removal / Recycling: Contractor is responsible for removing all waste created by the project. Contractor shall recycle to the highest degree possible and empty dumpsters as necessary to avoid debris on site. Locate as shown on site plan or coordinated with COR.

E. Security and Protection facilities:

1. Environmental Protection: Provide protection, operate temporary facilities, and conduct construction in ways and by methods that comply with state and federal environmental regulations and that minimize possible air, waterway, and subsoil contamination or pollution or other undesirable effects.

2. Cleaning of Equipment: The Contractor shall ensure that prior to moving on to the Project Area, all equipment, is free of soil, seeds, vegetative matter, or other debris that could contain or hold seeds. Ensure that all equipment has been pressure washed and is free of exotic species prior to start-up of operations and moving of equipment to Project Area.

Equipment shall be considered free of soil, seeds, and other debris when a visual inspection does not disclose such material. Disassembly of equipment components or specialized inspection tools are not required.

3. Tree and Plant Protection: Not Applicable

4. Pest Control: Follow best practices to minimize attraction and harboring of rodents, roaches, and other pests and to perform extermination and control procedures at regular intervals so Project will be free of pests and their residues at project completion. Perform control operations lawfully, using environmentally safe materials.

5. Temporary Enclosures: Provide temporary enclosures such as snow fence as required for protection of construction in progress and completed, from access by visitors or staff, other construction operations, and similar activities.

6. Site Enclosure Fence: Site includes a locked gate. Complex is required to be locked at the end of every day.

7. Hot Work Permit: Submit HW-1 Hot work permit form and receive approval from COR prior to Hot work activities commencing on site.

3.4 Storage - Staging Areas:

A. Confine Storage of materials and equipment to the project staging area noted on the plans/aerial. Specific storage units shall be provided by the contractor and exact location within staging area may be discussed at the preconstruction briefing. All storage units

Page | 12 provided by the contractor shall be in a clean and acceptable condition to the COR. Security of the materials and equipment on site is the Contractor’s responsibility.

3.5 Preservation of Natural Features:

3.6 Hauling Restrictions: Contractor shall verify and be responsible for the path accessing the site and obtaining / maintaining all local, state and federal permits/licenses associated with hauling/road requirements and dumping of materials associated with the project.

3.7 Housekeeping:

A. Keep project neat, orderly, and in a safe condition at all times.

1. Dispose of waste materials and recycling legally outside the park. The contractor shall not use park dumpsters

2. Address Recycling: Government goal is to salvage and recycle as much nonhazardous construction waste as possible. Use sustainable methods to extent possible during this project, recycling material as is probable with local means. Maintain accurate documentary records for submittal of all recycled materials used including fly ash and slag cement.

3.8 Occupancy Requirements for Buildings:

A. Existing Buildings:

1. Full Government Occupancy: Government will occupy buildings that will be under construction during the entire contract period. Cooperate with Government during construction operations to minimize conflicts and facilitate Government usage. Perform the Work so as not to interfere with Government's day-to-day operations. Maintain existing exits, unless otherwise indicated.

a. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from the CO or COR.

b. Maintain existing building in a weather tight condition throughout construction period. Repair damage caused by construction operations. Protect building and its occupants during construction period.

B. New /Existing Buildings Unoccupied:

1. Contractor shall be responsible for and protect the entire facility and construction site from notice to proceed through final acceptance.

2. Government Occupancy of Completed Areas of Construction: Government reserves the right to occupy and to place and install equipment in completed areas of building, provided such occupancy does not interfere with completion of the Work. Such placement of equipment and partial occupancy shall not constitute acceptance of the

Page | 13 entire project.

a. Contracting Officer will prepare a Beneficial Occupancy letter for each specific portion of the Work to be occupied before Government acceptance.

b. Obtain a Certificate of Occupancy from the NPS before Government occupancy.

c. Before partial Government occupancy, mechanical and electrical systems shall be fully operational, and required tests and inspections shall be successfully completed.

On occupancy, Government will operate and maintain mechanical and electrical systems serving occupied portions of building.

d. On occupancy, Government will assume responsibility for maintenance and custodial service for occupied portions of building.

3.9 Photo Documentation:

A. Contractor must provide existing condition, progress, and completion photos. All photos shall be in focus, show maximum range of depth of field general photo and then close up detail photo as needed. Shall be in JPEG digital form and submitted preferably electronically by email or optional via CD-R Archival Gold or DVD-R Archival Gold media with printed labels and 8 mega pixels minimum within 7 days from time of taken or as approved by COR.

B. Existing Condition Images:

1. Before starting construction, take color, dated, digital images of project site and adjacent property/roads/etc. that may be impacted by construction activity/traffic. Include existing items to remain or be salvaged from different vantage points and with context for location identification.

C. Construction Progress Images:

1. Document all sub-surface work/ trenches etc. prior to backfill with photos covering enough overall field view to show location and then zoom in for details. (Locations and dimensions shall also be noted on as built drawing set.)

2. Maintain organized index for photos with date, description, etc.

3. Additional images as needed when questions or emergency situations occur. Submit within 24 hours.

D. Completion Images:

1. Document all completed work within scope of work.

2. Maintain organized index for photos with date, description, etc..

3. Additional images as needed when questions or emergency situations occur. Submit within 24 hours.

3.10 Fire and Life Safety:

B. As a minimum, conduct one weekly 15 minute "toolbox" safety meetings. These meetings shall be conducted by a foreman or supervisor and attended by all construction personnel at the worksite. Topics need to coincide with work scheduled for the following week. Document and

Page | 14 submit meeting minutes to the CO and COR within one day after the meeting and document the meetings on the daily reports.

C. Comply with the requirements of NFPA 241 (Standard for Safeguarding Construction, Alteration, and Demolition Operations). Take all necessary precautions to prevent fire during construction. Provide adequate ventilation during use of volatile or noxious substances.

D. Store and handle hazardous materials in accordance with manufacturers and OSHA 29CFR1926 Subpart D requirements 1926 | Occupational Safety and Health Administration (osha.gov). Maintain readily available, on site, MSDS/Safety Data Sheets (SDS) for each chemical.

1. Immediately report all spills of hazardous materials to the CO, COR, and park.

2. Maintain a spill emergency response kit.

3. Train employees how to respond to a spill and use the emergency response kit.

3.11 Noise and Acoustics Management

A. Contractor shall not have personal radios or other media sources and they shall not be broadcast within NPS property.

B. Noise Control: Perform construction operations to minimize noise. Perform noise-producing work in less sensitive hours of the day or week as directed by the Contracting Officer or COR.

C. Repetitive and/or intermittent, high-level noise: N/A Permitted only during Daytime.

1. Do not exceed the following dB(A) limitations at 50 feet:

Sound Level in dB(A) Time Duration of Impact Noise

70 More than 12 minutes in any hour

80 More than 3 minutes in any hour

2. Maximum permissible construction equipment noise levels at 50 feet:

EARTHMOVING dB(A) MATERIALS HANDLING dB(A)

Compressors 75 Pneumatic Tools 80

Pumps 75 Saws 75

Generators 75 Vibrators 75

D. Ambient Noise:

1. Maximum noise levels (dB) for receiving noise area at property line shall be as follows:

a. Residential receiving area :

Daytime: 65 dB Nighttime: 45 dB

b. Commercial/Industrial receiving area:

Daytime: 67 dB Nighttime: 65 dB

ITEM 4 - COMMENCEMENT, PROSECUTION, AND COMPLETION

4.1 The Contractor shall commence work in accordance with the terms and conditions of the contract.

Contractor shall coordinate and incorporate long lead and delivery time items within the schedule.

ITEM 5 - EXAMINATION OF THE SITE

Page | 15

5.1 All bidders are urged to visit the job site and examine existing conditions before submitting bids.

Contractors will be accountable for understanding existing conditions. No cost changes for items visible during site visit will be allowed.

ITEM 6 - ABBREVIATIONS

6.1 The list of abbreviations, standards and organizations which may be used in/referred within the

Construction Specifications or Special Provisions, may be found linked from the listed page below. On the home page, follow the link under “Contracting and Procurement” labeled “NPS

Reference Standards.” https://www.nps.gov/orgs/1671/do-business-with-us.htm

ITEM 7 - ACCIDENT PREVENTION

7.1 Description: The work of this section consists of establishing and implementing an effective accident prevention program (APP) and providing a safe environment for all personnel and visitors.

7.2 Submittals:

A. Accident Prevention (Safety) Plan (APP): Submit a site-specific accident prevention (safety) plan. The Plan shall be written to comply with OSHA and project requirements (a generic plan is not acceptable) including but not limited to the following:

1. Name and qualifications of responsible supervisor to carry out the program.

2. First aid and rescue procedures.

3. Training, both initial and continuing.

4. Outline of each phase of the work, the hazards associated with each major phase, and the methods proposed to provide for property protection and safety of the public, National

Park Service personnel, and Contractor's employees. Identify the work included under each phase, with a Job Hazard Analysis (JHA)/Job Safety Analysis (JSA), etc. A sample

JHA template may be provided upon request.

5. Planning for possible emergency situations, such as cave-ins, earthquake, explosions, fires, floods, power outages, slides, and windstorms. Such planning shall take into consideration the nature of construction, site conditions, and degree of exposure of persons and property.

6. Contractor to identify nearest location of medical facility for emergencies

7. Recognition that works will be performed in remote areas with limited communication or cell phone coverage if applicable.

8. Supplemental hazard specific plans may be required IAW 29 CFR 1926 or 1910.

B. Meeting and Inspection Reports: Safety Meetings: As a minimum, conduct 15 minute

"toolbox" safety meetings. These meetings shall be conducted by a foreman and attended by all construction personnel at the worksite. Submit a report of safety meetings and inspections to CO and COR within one day after the meeting and document the meetings on the daily reports.

7.3 Qualification of Employees:

Page | 16

A. Ensure that employees are physically qualified to perform their assigned duties in a safe manner to include operators of vehicles and equipment. Provide operating instructions for all equipment.

B. Do not allow employees to work whose ability or alertness is impaired because of drugs, fatigue, illness, intoxication, or other conditions that may expose themselves or others to injury.

7.4 Accident Reporting: The Contractor shall report all accidents to the CO and COR as soon as safely possible and assist the CO and COR and other officials as required in the investigation of the accident.

7.5 First Aid Facilities: Provide access to facilities for the number of employees and appropriate to the hazards associated with the types of ongoing construction work at the site.

7.6 Emergency Instructions: Post telephone numbers and reporting instructions for ambulance, physician, hospital, fire department, and police in conspicuous locations at the work site.

7.7 Personal Protective Equipment (PPE): It is the Contractor's responsibility to require all those working on or visiting the site to wear necessary protective equipment at all times.

A. PPE must meet requirements of applicable ANSI standards. Selection shall conform to OSHA

29CFR 1926 Subpart E.

B. A hard hat use area shall be designated by the Contractor. The hard hat area shall be posted by the Contractor in a manner satisfactory to the Contracting Officer.

C. All PPE will be serviceable at all times. At a minimum, maintain 2 sets of PPE including hard hats and all other Accident Prevention Plan required equipment.

7.8 Hazardous Materials: It shall be the responsibility of all operators and contractors, functioning within the park to properly cleanup, mitigate and remediate if necessary, all unauthorized discharges of hazardous materials or non-hazardous chemical and biological products released from fleet and/or other support vehicles or stationary sources. Response shall be consistent with guidelines established by federal, state, and local regulations, and as outlined within the operator's Safety or Hazardous Materials Business Plan.

A. If a spill, leak, or other release occurs, the operator shall as soon as possible, without impeding cleanup, notify the local 911 Emergency Response, COR and or the National Park

Service Emergency Dispatch.

ITEM 8 - PRECONSTRUCTION CONFERENCE

8.1 If the Contracting Officer decides to conduct a preconstruction conference, the successful offeror will be notified and will be required to attend. The Contracting Officer’s notification will include specific details regarding the date, time, and location of the conference, any need for attendance by subcontractors, and information regarding the items to be discussed. See Item 9.1C below.

ITEM 9 - SUBMITTALS

Page | 17

9.1 General Contracting Submittal Procedures:

A. General: Prepare and submit submittals required by individual Technical Specification

Sections. Types of submittals are indicated in individual specific sections.

1. CM-16 Transmittal Form: All submittals shall be transmitted via electronic email using

National Park Service form CM-16 form. The form will be provided by the Contracting

Officer. No action will be taken on a submittal item unless accompanied by the CM-16 transmittal form. Submit completed CM-16 forms to the CO and the COR

B. Submittal List: administrative required submittals are listed below in 9.1.C and does not include technical section submittal requirements included in each technical section.

C. Preconstruction Conference Submittal: Satisfactory evidence of liability insurance coverage and workman’s compensation, and any applicable bonds, must be submitted within 10 calendar days of Notice of Award. The following items are to be submitted prior to the

Preconstruction Conference or as specified at the CO’s discretion. The timeline for the documents to be submitted will be addressed at the pre-construction conference for those items that were not received and approved prior. Notice to Proceed may not be issued, and the Contracting Officer will consider other contractual remedies if not resolved as directed.

Work shall not commence until written Notice to Proceed has been issued. Contracting

Officer will notify Contractor of tentative date for the Pre-Construction Conference:

1. Letter designating Project Superintendent.

2. Construction Schedule. (Must include shop drawings, procurement time including long lead time items, mobilization, trade work progression and completion at minimum.)

3. A comprehensive breakdown of the Schedule of Values.

4. Accident Prevention (Safety) Plan (see section 7 of this document).

5. A list of Subcontractors for this project.

6. Written statements from subcontractors certifying compliance with applicable labor standard clauses (SF1413).

7. Quality Control Plan.

9.2 Project Submittal Process (Shop Drawings, Product Data, and Samples): Contracting Officer will provide sample cover sheet and a list of required submittals is included in each technical specification or attached at the end of this document.

A. Shop Drawings: Indicate all coordinating materials and work impacting the installation coordination, connection details, anchorage requirements, hardware locations, and installation details and locations.

1. Submit Shop Drawings according to Part 9.1 of this section to include one digital file (.PDF or .TIF) and two full size hardcopy documents to COR.

B. Product Data: Provide component construction and specification data sheets, anchorage requirements and any other product specific data.

Page | 18

1. Submit Product Data according to Part 9.1 of this section to include one digital file (.PDF or .TIF) to COR.

C. Samples: Submit 2 color samples 4” x 6” minimum in size for all product color selections.

Paint samples shall be actual paint finish drawdown for all project colors.

1. Submit Samples CM-16 Transmittal Form according to Part 9.1 of this section to include one digital file (.PDF or .TIF) and physical samples of actual material to COR.

D. For submittals specified above, forward submittals to Contracting Officer and COR at least 15 days before need for approval (depends on length of project).

E. After approving submittals, Contracting Officer and/or COR will return one copy to the

Contractor. If submittals are not approved, Contracting Officer will return all copies to

Contractor with reasons for rejection. Resubmit, identifying changes. Any work done before approval shall be at Contractor's own risk.

9.3 Approved Equals: All brand names noted are subject to ‘or equal’ products. If an item in this solicitation is identified as “brand name or equal” or lists more than 1 manufacturer, the description of the proposed item must reflect the characteristics and level of quality that will satisfy the Government’s needs as demonstrated by the salient physical, functional, or performance characteristics that “equal” products must meet and/or exceed that as specified in the solicitation or relevant specification. Contractor shall incorporate and be responsible for all collateral costs due to the or equal proposed as required to provide a complete project.

A. For each item proposed as an “approved equal,” submit supporting data, including:

1. Drawings and samples as appropriate.

2. Comparison of the characteristics of the proposed item with that specified and with the salient characteristics provided.

3. Changes required in other elements of the work because of the substitution.

4. Name, address, and telephone number of vendor.

5. Manufacturer’s literature regarding installation, operation, and maintenance, including schematics for electrical and hydraulic systems, lubrication requirements, and parts lists.

Describe availability of maintenance service, and state source of replacement materials.

B. A request for approval constitutes a representation that General Contractor:

1. Has investigated and shall provide documentation in request showing that the proposed item is equal or superior in all respects to the salient characteristics specified.

2. Will meet or exceed warranties for the proposed item specified.

3. Has determined that the proposed item is compatible with interfacing items.

4. Will coordinate the installation of an approved item and make all changes required in other elements of the work because of the substitution.

5. Waives all claims for additional expenses that may be incurred as a result of the substitution.

C. Approved Equals will be evaluated and approved/disapproved during the submittal process.

Page | 19

9.4 Schedule of Values: Submit the Schedule of Values a minimum of one week prior to the

Preconstruction Conference for COR review. Schedule of Values shall include defined work line items with cost break downs including labor, material, and equipment for COR approval.

9.5 Progress Reporting: The initial Construction Schedule and Schedule of Values are required a minimum of one week prior to the Preconstruction Conference. After the Notice to Proceed is issued and after on-site work begins, progress will be documented via daily logs and by providing an updated Construction Schedule and Schedule of Values when requested, but minimally with each pay application. Submit digital copy electronically (PDF preferred) of all required documents.

Construction Schedules are normally in bar chart form and indicate estimated starting and completion dates for each part of the work. For a pay application to be reviewed and processed in a timely manner, the following information must either be submitted prior to or accompany submission of the pay application:

A. Daily/weekly progress reports during construction as part of the administration process.

B. Updated Schedule of Values: Breakdown each lump-sum item into component work activities used in the schedule, for which progress payments may be requested. The Schedule of

Values will form the basis for payment. The work activities broken out within the schedule of values shall be integrated into and made a logical part of the construction baseline schedule submitted under this specification. The total costs for the component work activities shall equal the contract price for that lump-sum item. The Contracting Officer may request data to verify accuracy of dollar values. A sample Schedule of Values format may be provided upon request.

ITEM 10 – TEMPORARY SERVICES

10.1 It is the Contractor’s responsibility to provide temporary services, equipment, tools, and skilled labor as required for the chosen means and methods to perform the work in accomplishing this

Contract.

ITEM 11 - PROJECT CLOSEOUT

11.1 Description: The work of this section consists of final cleanup, closeout submittals, final inspection procedures working toward Final Acceptance.

11.2 Cleaning: Remove all tools, equipment, surplus materials, and rubbish. Move attic stock to location coordinated with COR. At time of final inspection, project shall be thoroughly clean and ready for intended use. Inspector holds the right to reschedule if project is not ready for inspection.

11.3 Completion and Final Inspection: Contractor shall submit written certification of project completion and request a final inspection to the Contracting Officer and COR. The Contracting

Officer or designee will make an inspection within 10 days of receipt of request or at a mutually agreeable time.

A. If the work is determined to be complete following the final inspection with minor comments, the COR will prepare and provide the Contractor a Punch List noting outstanding items to be addressed.

Page | 20

B. If the work is not determined to be complete following the final inspection, the Contracting

Officer will notify Contractor in writing, stating reasons. Contractor, after completing the work according to the Contract Documents, shall resubmit completion and request a new final inspection. Re-inspection costs may be charged against the Contractor in accordance with the Inspection of Construction contract clause.

C. Contractor shall complete the Punch List within 30 calendar days, or a time directed by the

CO.

D. Once Contractor completes all items of work on the Punch List and all contractually required items are accepted, Contracting Officer will issue Letter of Final Acceptance of Work and request the final pay application.

E. If the Contractor fails to complete the work within the time frame, the Contracting Officer may correct the work with an appropriate reduction in contract price or charge for re-inspection costs in accordance with the Inspection of Construction contract clause.

F. Disposition of any permits and warranties required by the specifications in this section.

11.4 Final Acceptance of the Work: After all punch list deficiencies have been corrected, a Letter of

Final Acceptance will be issued. A Release of Claims document must be executed and submitted to the Contracting Officer before final payment can occur.

11.5 Warranties

A. Construction Warranty shall be based on date of final acceptance of the work and remain in effect for one year.

B. Provide all manufacturer warranty information of products installed organized by Division. All contact information, extent of coverage and conditions shall be clearly noted as well as date of overall final acceptance.

C. Information shall include operation and maintenance manuals for each warranted product.

ITEM 12 - DEFINITION OF CONTRACT LINE ITEMS

12.1 Summary

A. The intent of this section is to explain, in general, what is and what is not included in a contract line item, and the limits or cut off points where one item ends, and another begins.

B. If no contract line item exists for a portion of the work, include the costs in a related item.

12.2 List of Contract Line Items

A. Contract Line-Item No. CLIN 010 All Items, Paining, Garage doors, Service doors, Heaters, lighting, Electrical panel replacements, and fence/gate work.

1. This item consists of Paining, Garage doors, Service doors, Heaters, lighting, Electrical panel replacements, and fence/gate work.

2. Payment will be made per the contract and percentage of completion level.

Page | 21

END OF SECTION

HOLLOW METAL DOORS AND FRAMES 08 11 00 | 1

SECTION 08 11 00

HOLLOW METAL DOORS AND FRAMES

GENERAL

SUMMARY

Section Includes:

Metal doors and frames.

Related Specification Sections include but are not necessarily limited to:

Section 08 70 00 - Finish Hardware.

QUALITY ASSURANCE

Referenced Standards:

ASTM International (ASTM):

A653, Standard Specification for Steel Sheet, Zinc-Coated (Galvanized) or Zinc-Iron

Alloy-Coated (Galvannealed) by the Hot-Dip Process.

National Association of Architectural Metal Manufacturers (NAAMM):

Hollow Metal Manufacturers Association (HMMA).

Steel Door Institute (SDI):

117, Manufacturing Tolerances for Standard Steel Doors and Frames.

All SDI publications.

Steel Door Institute/American National Standards Institute (SDI/ANSI):

A250.6, Recommended Practice for Hardware Reinforcing on Standard Steel Doors and

Frames.

A250.7, Nomenclature for Standard Steel Doors and Steel Frames.

A250.8, Specifications for Standard Steel Doors and Frames.

A250.10, Test Procedure and Acceptance Criteria for Prime Painted Steel Surfaces for

Steel Doors and Frames.

A250.11, Recommended Erection Instructions for Steel Frames.

Qualifications: Manufacturer must be current member of SDI, and NAAMM (HMMA).

Wipe coat galvanized steel is not acceptable as substitute for galvanizing finish specified.

DEFINITIONS

As identified in SDI/ANSI A250.7.

SUBMITTALS

Shop Drawings:

Product technical data including:

HOLLOW METAL DOORS AND FRAMES 08 11 00 | 2

Acknowledgement that products submitted meet requirements of standards referenced.

Manufacturer's installation instructions.

Schedule of doors and frames using same reference numbers as used on Drawings.

SDI certification.

Contract Closeout Information:

Operation and Maintenance Data:

See Specification Section 01 10 00 for requirements for the mechanics, administration, and the content of Operation and Maintenance Manual submittals.

DELIVERY, STORAGE, AND HANDLING

Store doors and frames in accordance with SDI/ANSI A250.11.

PRODUCTS

MANUFACTURERS

Subject to compliance with the Contract Documents, the following manufacturers are acceptable:

Metal doors and frames:

Ceco Door by ASSA ABLOY.

Steelcraft by Allegion PLC.

Curries by ASSA ABLOY.

Or equal

MATERIALS

Steel Sheet: Hot-dipped galvannealed steel, ASTM A653, A60 coating.

Frames: Hot-dipped galvannealed steel, ASTM A653, A60 coating.

Supports and Reinforcing: Hot-dipped galvannealed steel, ASTM A653, A60 coating.

Inserts, Bolts and Fasteners: Manufacturer's standard.

Primer: Manufacturer's standard coating meeting SDI/ANSI A250.10.

Paint: doors & frames factory finished; color shall be approved by NPS.

Galvannealed Coating Repair: Per Manufacturer's recommendation.

Thermal Insulation: Polyurethane, CFC free.

ACCESSORIES

Frame Anchors:

Jamb anchors:

HOLLOW METAL DOORS AND FRAMES 08 11 00 | 3

Existing wall anchor: Minimum 18 GA, galvanized.

Stud partition and base anchors: Minimum 18…