About this file

The document is a Statement of Work (SOW) for a USDA APHIS construction project at the Insect Management and Molecular Diagnostics Laboratory (IMMDL) located on Moore Air Base in Edinburg, Texas. The project involves replacing three Kysor/Rheem SEER environmental growth chambers (EGCs), eight chilled water units, and two standard walk-in coolers, which are over thirty years old and experiencing significant equipment obsolescence. The replacement scope includes comprehensive demolition of existing systems, installation of new evaporators, condensers, control panels, piping, electrical connections, humidification/dehumidification systems, and digital control interfaces.

The solicitation (12639525R0019) is set aside exclusively for small businesses, with a project estimated between $1M and $5M under NAICS code 238220 for Plumbing, Heating, and Air Conditioning Contractors. The project will be conducted at a restricted facility with work hours from 7 a.m. to 3:30 p.m. Monday through Friday, requiring EPA-certified technicians and compliance with Texas state and local codes. All equipment must be new and unused, and installation must be performed professionally. Key project contacts include Gabriel Lopez (Facilities Manager) and Javier Caltzontzint (Supervisory Maintenance Mechanic), both from the USDA APHIS facility in Edinburg, Texas.

View the file

Other files for this federal contract opportunity

Other files attached to Environmental Growth Chambers, HVAC, and Controls Replacement, Moore Air Base, TX, newest first.
File Type Posted
Qs_and_As Excel Sheet Growth Chambers R02.xlsx XLSX spreadsheet
12639525R0019-0003.pdf PDF
12639525R0019-0002.pdf PDF
RFIs and responses.docx DOCX document
Building 6414 EGCs Attendance Site Visit.pdf PDF
IMG_0110.jpeg JPEG file
IMG_0112.jpeg JPEG file
IMG_0117.jpeg JPEG file
IMG_0115.jpeg JPEG file
IMG_0107.jpeg JPEG file
IMG_0113.jpeg JPEG file
IMG_0111.jpeg JPEG file
IMG_0109.jpeg JPEG file
12639525R0019-0001.pdf PDF
Atch 2_Federal Construction Wage Rates_Hidalgo County.pdf PDF
12639525R0019.pdf PDF
Show all 16

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation 12639525R0019, Attachment 1 Statement of Work For 6414 Growth Chamber HVAC Units And Controls Replacements June 2025

1.0 CONTRACT PROJECT: Growth Chamber HVAC Unit & Controls Replacements

2.0 LOCATION: USDA APHIS PPQ IMMDL

(Insect Management and Molecular Diagnostics Laboratory)
Bldg. 6414
22675 N. Moorefield RD
Moore Air Base
Edinburg, TX 78541

3.0 PROJECT BACKGROUND: The IMMDL (Insect Management and Molecular Diagnostics Laboratory), building number 6414, is located on Moore Air Base (MAB). Square footage is 19,431 sf with one floor. The original construction was in 1981, with partial exterior/interior renovations over the years and most recently in 2024.

The laboratory identifies, develops, and provides technology transfer of a wide range of scientific methods to PPQ and State departments of agriculture. In addition to these core functions, the laboratory cooperates with stakeholders and researchers to provide expertise to PPQ regarding geographic information systems, biological control, area-wide pest management, and sterile insect technology (SIT) support for the Mexican fruit fly eradication program. In addition, the laboratory leads the agency’s Unmanned Aircraft Systems (UAS) initiative to develop methods for the successful incorporation of new UAS technologies into PPQ programs.

The laboratory is responsible for developing and validating technologies used to detect and diagnose plant pests, as well as developing methods to support APHIS-PPQ programs (i.e., Fruit Fly). The focus of the laboratory’s diagnostic work is on insects that cause damage directly to plants or that serve as vectors of plant disease, but molecular biological methods are also used to support production of beneficial insects through detection of insect pathogens in rearing populations. Methods developed at the laboratory include cutting-edge molecular approaches to study nucleic acids such as High-Throughput Sequencing, real-time PCR, isothermal amplification, and microfluidic genotyping. These have been used to complete confirmatory identifications, to track high-risk pathways of invasive species, and to screen insect genomes for new molecular tools. In addition, the laboratory is examining how recent advances in methods such as CRISPR and nanotechnology can be used in the treatment of plant pathogens. The laboratory conducts the selection of fruit fly strains, and all quality control tests related to fruit fly.

The building houses environmentally controlled laboratories, offices, and scientists. IMMDL performs research and conducts experiments using Environmental Growth Chambers (EGCs). The EGCs in building 6414 are over thirty years old, malfunctioning, and dilapidated. All the EGCs need to be upgraded due to obsolete controls and HVAC unit parts no longer sold in the open market.

4.0 SCOPE OF SERVICES:

4.1 General: The purpose of this SOW is to outline the upgrade and replacement of the current EGCs and Kysor/Rheem SEER HVAC units and controls replacement. Tasks under this SOW are as follows:

4.1.1 KYSOR/ RHEEM SEER EGC – (Qty: 3)

· Lock-Out Existing Units & Make Safe for Demo

· Demo Existing Evaporators & Water-Cooled Condensers

· Disconnect Electrical

· Demo Existing Control Panels

· Demo Selective Condenser Water Piping

· Demo Refrigerant Piping

· Set New Evaporator & Water-Cooled Condensing Unit

· Reconnect Condenser Water Piping

· Reconnect Drain Lines

· Reconnect Refrigerant Piping

· Reconnect Electrical Wiring for Chamber Equipment

· Insulate Refrigerant Suction Line Piping

· Insulate Condenser Water Piping

· Install Lighting Package

· Install Humidification & Dehumidification Systems

· Install New Digital Control Panel (7” Touch Screen) & Sensors

· Perform Start-Up

4.1.2 Environmental Growth Chambers (Qty: 8 Chilled Water Units)

· Lock-Out Existing Units & Make Safe for Demo

· Demo Existing Evaporators

· Demo Existing Chilled Water Pumps

· Demo Existing Humidification & Dehumidification Systems

· Disconnect Electrical

· Demo Existing Control Panels

· Demo Selective Chilled Water Piping

· Set New Chilled Water Evaporators

· Set New Inline Chilled Water Pumps

· Reconnect Chilled Water Piping

· Reconnect Drain Lines

· Install New 3-Way Chilled Water Control Valve

· Reconnect Electrical Wiring for Chamber Equipment

· Insulate Chilled Water Piping

· Install Lighting Package

· Install Humidification & Dehumidification Systems

· Install New Digital Control

4.1.3 Standard Walk-In Coolers (Qty: 2)

· Lock-Out Existing Units & Make Safe for Demo

· Demo Existing Evaporators & Air-Cooled Condensers (on roof)

· Disconnect Electrical

· Demo Existing Stand-Alone Controls

· Demo Refrigerant Piping

· Set New Evaporators & Air-Cooled Condensers (on roof)

· Reconnect Drain Lines

· Install New Refrigerant Piping

· Reconnect Electrical Wiring for Each Unit

· Insulate Refrigerant Suction Line Piping

· Install New Stand-Alone Thermostat Controller

· Perform Start-Up

Contractor must comply with applicable codes, environmental regulations in the State of Texas and local ordinances.

· All work shall be performed in accordance with all applicable State and Local codes and standards.

· All work to be performed by EPA certified technicians and executed in a professional, workman-like manner.

· All equipment and material installed on this project shall be new and unused unless otherwise noted.

· All work to be performed during normal business hours, Monday through Friday, unless otherwise noted.

5.0 PROJECT CONTACTS:

5.1 APHIS PPQ Facilities Manager

Gabriel Lopez

USDA, APHIS, PPQ FO

Moore Air Base 22675 North Moore Field Building 6407 Edinburg, TX 78541 Tel. No.: (956) 205-7608 Cell No.: (956) 207-9594 Email: Gabriel.Lopez@usda.gov

5.2 APHIS PPQ Supervisory Maintenance Mechanic

Javier Caltzontzint

USDA, APHIS, PPQ FO

22675 North Moore Field Building 6415 Edinburg, TX 78541 Tel. No.: (956) 205-7734 Cell No.: (956) 330-1145 Email: Javier.caltzontzint@usda.gov

6.0 SECURITY AND SAFETY REQUIREMENTS:

Moore Air Base is a restricted facility.

· Work Hours are Monday through Friday from 7 a.m. to 3:30 p.m. All work outside of the mentioned days and hours must be approved by the Facilities Maintenance manager in writing, prior to entering the facility. This includes work on Federal holidays.

· Some of this work will be required after 3:30. The contractor is to provide a schedule for those days to coordinate with the Maintenance Mechanic Supervisor.

· All employees must have a valid picture identification such as a driver’s license or a state identification card.

· All vehicles must have proper insurance and registration for entering the facility.

· All employees working at the facility must remain in the project site under the supervision of a qualified job site superintendent. Anyone found outside of the determined construction area will be removed from the facility and not allowed to return.

· Contractor must provide temporary and portable restroom facilities for their employees if the project has a duration of over three working days.