This Performance Work Statement (PWS) details dryer vent cleaning services for Joint Base Elmendorf-Richardson (JBER) in Alaska. The contract requires a contractor to provide personnel, equipment, tools, and labor to clean 731 total dryer vents across multiple buildings including barracks, dormitories, lodging facilities, child development centers, fitness centers, and fire stations. Cleaning services will be performed semi-annually (twice per year) for most locations, with annual cleaning for specific facilities like fire station truck bays and some specialized rooms.
The contractor must follow manufacturer recommendations, National Fire Protection Agency (NFPA), Occupational Safety and Health Act (OSHA) codes, and local/state/federal regulations. Key requirements include completely removing lint and debris from entire vent systems, labeling serviced equipment, submitting detailed inspection reports within 5 business days after each service, and maintaining a quality control program. The contractor must also comply with base security requirements, provide professionally attired personnel, handle hazardous materials appropriately, and be flexible to accommodate potential mission changes at the base.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Questions and Answers_FA500025Q0015_27 Mar 2025.pdf | ||
| Questions and Answers_FA500025Q0015_25 Mar 2025.pdf | ||
| Site Visit Meeting Minutes.pdf | ||
| Amend 0002_COMBO_FA500025Q0015_Dryer Vent.pdf | ||
| Amend 0002 Atch 5 - Additional Provisions and Clauses.pdf | ||
| Questions and Answers_FA500025Q0015.pdf | ||
| Atch 3 - Price Schedule.xlsx | XLSX spreadsheet | |
| Atch 5 - Additional Provisions and Clauses.pdf | ||
| Atch 4 - Past Performance Questionnaire.docx | DOCX document | |
| Atch 2 - WD 2015-5681 Rev 22_dtd 12.23.24.pdf | ||
| COMBO_FA500025Q0015_Dryer Vent.pdf |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PERFORMANCE WORK STATEMENT
for
Dryer Vent Cleaning Services at
Joint Base Elmendorf-Richardson (JBER), Alaska
4 March 2025
Dryer Vent Cleaning Services Attachment 1 - PWS
FA500025Q0015
Table of Contents
1.0 GENERAL
1.1 Background
1.2 DRYER VENT CLEANING SERVICE DESCRIPTION
1.3 Dryer Vent Maintenance
1.4 Label/Equipment Tag
1.5 Preventive Maintenance Schedule
1.6 Inspection Reports/Documentation
2.0 SERVICE SUMMARY (SS)
2.1 Quality Control Program (QCP)
2.2 Quality Assurance (QA)
2.3 Surveillance Methods
2.3.1 Periodic Surveillance
2.3.2 Customer Complaints
2.3.3 100% Inspection
2.3.4 Safety and Fire Protection Requirements
2.5 Progress Meetings
3.0 GOVERNMENT FURNISHED PROPERTY AND SERVICES
3.1 Furnished Facilities
3.2 Furnished Supplies and Equipment
3.3 Furnished Services
3.4 Medical Emergency Services
3.5 Security Police and Fire Protection
3.6 Utilities
3.7 Preservation of Government Property
4.0 GENERAL INFORMATION
4.1 Hours of Operation
4.2 Performance of Services During Crisis Declared by the National Command Authority or Overseas Combatant Commander
4.3 Base Closures
4.4 Security Requirements
4.5 Safety Requirements
4.6 Contractor/Employee Base Pass and Identification, Special Clearances and Vehicle Passes
4.7 Hazardous Material Identification
4.8 HAZMART
Dryer Vent Cleaning Services
4.9 Spill Response
4.10 Hazardous Material/Waste Management
4.11 Hazardous Material Handling
4.12 Certification
4.13 Weapons, Firearms, and Ammunition
4.14 Controlled Unclassified Information (CUI)
4.15 Contract Lead
4.16 Vehicles/Equipment
5.0 Personnel
5.1 Professional Appearance
5.2 Employees
5.3 Alcohol/Drug Use
5.4 Substance Abuse Testing
5.5 Cleanup Procedure
Service Abbreviations
Technical Exhibit
Dryer Vent Cleaning Services
1.0 GENERAL.
This is a non-personal services contract to clean dryer vents. The Government must not exercise any supervision or control over the contract service providers performing the services herein. Such contract service providers must be accountable solely to the Contractor who, in turn, is responsible to the Government. This is a performance-based contract which will have success measured by the outcome of the Contractor’s performance.
1.1 Background.
Joint-Base Elmendorf-Richardson (JBER) is United States military installation located near Anchorage, Alaska. JBER experiences frequent mission changes which may increase or decrease requirement.
Contractor must be flexible and must be prepared to adjust the schedule to accommodate changes within 72 hours of notice and send an updated copy of the schedule to the Contracting Officer’s Representative
(COR).
1.2 Dryer Vent Cleaning Service Description.
Contractor must provide all personnel, equipment, tools, materials, vehicles, management and labor necessary to perform dryer vent cleaning services on JBER, Alaska in accordance with (IAW) manufacturer’s recommendations, National Fire Protection Agency (NFPA), Occupational Safety and Health Act (OSHA) codes, commercial practices, local, state, and federal regulations. Contractor must submit a report to the COR on all dryer vent services, noting discrepancies, system impairments and recommendations, within 5 business days after each semiannual (SA); annual (AN) service has been performed.
1.3 Dryer Vent Maintenance.
Contractor must maintain, inspect, and clean all dryer vent equipment listed on Tech exhibit IAW manufacturer’s recommendations, NFPA, OSHA codes, commercial practice, local, state, and federal regulations also as defined in this Performance Work Statement (PWS).
a. Remove all dirt and debris, to include lint, from the permanently installed central dryer vent line system to include any registers, dampers, fans, equipment and other devices where dryer vent exhaust passes through or over that register, damper, fan, equipment or other device.
b. Remove all lint, debris buildup, clogs or obstructions from the entire run of the vent, including but not limited to the entry and termination points from dryer vent and immediate areas around dryers, from inside transition ducting, through wall ducting and from exterior vent termination caps.
c. Remove lint from walls up to the ceiling to and including the ceiling, floors, and under dryers.
d. Remove lint up to the exterior termination, exterior wall, and exit hole.
e. Bldg. 651 on JBER-Richardson dryer vent cleaning will not include the air exchanger.
Dryer vent will include the transition venting and 24” trunk immediately behind the dryers.
Dryer Vent Cleaning Services
f. There are numerous multi-floor buildings with duct termination caps.
1.4 Label/Equipment Tag.
Contractor must label serviced equipment immediately after service is completed by applying a decal (stick-on label), indicating company’s name, address, phone number, date work was completed, month and year when next service will be performed, and frequency of service for the system (i.e., semi-annual, or annual). Contractor must use a numbering system on the label to easily identify the dryer vents during inspection. Contractor shall affix the decal on the front corner near the control & monitor of the dryer so that it is readily visible. When performing services and the Contractor finds the label on the equipment is loose, unreadable, or missing, the label must be replaced.
1.5 Preventive Maintenance Schedule.
Contractor must submit a preventive maintenance schedule to the COR for dryer vent cleaning by 1 May for summer cleaning and by 1 November for winter cleaning. Contractor is responsible for coordinating access to equipment with the facility manager, COR will provide facility manager contact information after award. Contractor must provide an updated schedule to the COR within 5 business days of the dates above, if changes to the original are made. The Contractor will need to clean all facilities (annual and semi-annual) covered under this PWS during their initial summer cleaning to maintain the current frequency.
1.6 Inspection Reports/Documentation.
Contractor must prepare and submit a written electronic report semi-annually covering all work completed the previous maintenance cycle. The report must be submitted on company letterhead containing the point of contact’s information (name, telephone, & email address) and contract number.
Report must outline each piece of equipment, all cleaning performed, and identifying any system impairments along with recommended remedies. The report is due to the COR NLT 5 business days after end of the maintenance cycle, and at a minimum report must include the following information:
a. The inspection/cleaning date
b. Equipment location’s building/facility number
c. Describe the overall condition of the equipment/unit
d. Details on service provided
e. Print full name of technician(s) and service date performed
f. Number of man-hours to complete maintenance
2.0 SERVICE SUMMARY (SS).
The SS captures the requirements that can be measured and are critical operational requirements.
Performance Objective identifies desired end results the Contractor must achieve.
Performance Thresholds describes the minimum acceptable performance in terms of quality, timeliness
Dryer Vent Cleaning Services and quantity in achievable standards. The SS outlines the Acceptable Quality Levels (AQL) which establishes the maximum number of minor discrepancies for each assessment category to meet determined quality level. The SS and Contractor’s Quality Control Plan (QCP) provide information on contract requirements, the expected level of contractor performance and the expected method of government surveillance and confirmation of services provided. These thresholds are critical to mission success.
Performance Objective PWS
Paragraph Performance Threshold
SS1: Dryer Vent 1.3, 1.4 Excellent: 0-5 defects Very Good: 5-10 defect Satisfactory: 10-20 defects
Maintenance & Labeling
SS2: Preventive Maintenance Schedule
1.5 Schedule submitted IAW the requirements in
para 1.5
SS3: Inspection Reports & Documentation
1.6 Inspection Reports & Documentation
submitted IAW the requirements in para 1.6
2.1 Quality Control Plan (QCP).
Contractor must develop and maintain a QCP to ensure services are performed IAW this PWS. The overall control of quality must meet the specified performance thresholds for each requirement in the Services Summary. QCP must be submitted to the CO/COR 10 business days after contract award. After acceptance of the QCP, the Contractor must receive the CO’s acceptance in writing of any proposed changes. Contractor must maintain the QCP throughout the period of performance of the contract.
2.2 Quality Assurance (QA).
COR will inspect and evaluate the Contractor’s performance to ensure services received are IAW requirements set forth in this contract. When a performance threshold has not been met or scheduled service has not been accomplished, the COR may initiate and provide the CO a Corrective Action Report (CAR) for issuance to the Contractor. Response(s) must be in writing to the COR IAW instructions provided in the CAR.
2.3 Surveillance Methods.
The Government may use but are not limited to the following surveillance methods; 100% inspection, periodic surveillances, random sampling, customer complaints. Required reperformance must occur within the notification timeline reperformance provided by the COR, but not shorter than 5 days.
Dryer Vent Cleaning Services
2.3.1 Periodic Surveillance.
This method requires the COR to employ a “spot check” style of evaluation based on the Contractor’s incorporated cleaning schedule. Periodic surveillances and/or validations will be conducted on a scheduled basis (daily, weekly, monthly, quarterly, semi-annual or annually) and may be adjusted based on quality trends. The cleaning schedule or modified version thereof will be used for COR periodic inspections and results documentation.
2.3.2 Customer Complaints.
COR will investigate all discrepancy records received from customers. COR must be responsible for initially validating discrepancy record. The CO must make final determination of the validity of discrepancy record(s) in cases of disagreement with the COR and the Contractor. Validated discrepancy record must be re-performed IAW PWS 2.3, but prior to the next service period. Re-performance does not eliminate the customer complaint, and it still applies against the Contractor’s performance threshold.
2.3.3 100% Inspection.
This method requires 100% validation from the COR. Performance is inspected, evaluated, and/or validated to ensure work is completed.
2.3.4 Random Sampling.
The CORs will calculate a random sample lot size to inspect based on the total number of completed Work Tasks. Required re-work discovered by random sampling must be performed within the timeline directed within 5 business days after notification by the COR.
2.4 Safety and Fire Protection Requirements.
Contractor must initiate and maintain programs to comply with the provisions of the OSHA as well as the most current version of NFPA 211. Contractor must perform work in a safe manner as required by OSHA Safety & Health Requirements. Contractor must provide a verbal report to the CO/COR as soon as possible of each occurrence of damage to government property or an accident resulting in death, injury, occupational disease, or adverse environmental impact. Contractor must provide a completed copy of required Accident Investigation Reports to the CO/COR five business days of each occurrence. Contractor must immediately notify the COR when damage to government property, whether due to accident, abuse or misuse is discovered. Contractor must annotate the damage on the inspection checklist/report.
2.5 Progress Meetings.
The CO, Functional Commander, COR, other government personnel as appropriate, and the Contractor must meet at the discretion of the CO. The Contractor may request a progress meeting as needed. The following issues may be discussed: opportunities to improve the contract, any modifications required of the contract, unsatisfactory inspections and valid customer complaints against each performance objective observed and steps taken by the Contractor to prevent occurrences in the future. Contractor must provide a summation of unsatisfactory inspections and customer complaints and provide insight into any identified trends. Written minutes, signed by the CO or designated alternate, will be distributed to meeting attendees. Should the Contractor not concur with the minutes, the Contractor must provide a written notification to the CO identifying areas of non-concurrence for resolution.
Dryer Vent Cleaning Services
3.0 GOVERNMENT FURNISHED PROPERTY AND SERVICES.
3.1 Furnished Facilities.
Reserved
3.2 Furnished Supplies and Equipment.
There will be no government furnished property.
3.3 Furnished Services.
Government will provide the following limited services: medical emergency, security, telephone, utilities, and access to information.
3.4 Medical Emergency Services.
For medical emergencies, the Contractor must call 911 and indicate they are on JBER. In the event of a medical emergency, base ambulance service for transporting an injured individual or one who has become critically ill to a local hospital is available on a cost reimbursement basis. All mishaps will be promptly reported to the base Safety Office through the CO/COR.
3.5 Security Police and Fire Protection.
Call 673rd Security Forces Squadron at 552-7070 to report any type of security violations. Call 911 for emergencies and indicate they are on JBER.
3.6 Utilities.
Government will provide electricity and water at no additional cost to the Contractor. Contractor must adhere to all base level utility conservation practices or requirements. Contractor must be responsible for operating under conditions that prevent waste of utilities.
3.7 Preservation of Government Property.
Contractor must use reasonable care to avoid damaging existing buildings, equipment, and vegetation on the Government installation. If the Contractor’s failure to use reasonable care causes damage to any of this property, the Contractor must replace or repair the damage at no expense to the Government as the CO directs. If the Contractor fails or refuses to make such repair or replacement, the Contractor will be held liable for the cost, which may be deducted from the contract price.
4.0 GENERAL INFORMATION.
4.1 Hours of Operation.
Contractor must perform work during the hours that will cause the least amount of conflict with the user’s operations if required, to allow a minimum interference and inconvenience to occupants.
Contractor must be flexible with the cleaning scheduled as JBER experiences frequent mission changes which may increase or decrease the requirement. Contractors are not required to perform services on Federal Holidays. If the holiday falls on a Saturday, it will be observed on the preceding Friday.
If the holiday falls on Sunday, it will be observed on the following Monday.
Dryer Vent Cleaning Services
4.2 Performance of Services During Crisis Declared by the National Command Authority or Overseas Combatant Commander.
Dryer Vent Cleaning Services requirement under this PWS is determined not essential to be performed during a crisis.
4.3 Base Closures.
Scheduled work not accomplished because of base closure due to weather, exercises, or actual alert, will be rescheduled after base returns to normal status.
4.4 Security Requirements.
Contractor and all employees will comply with all JBER security requirements imposed by the Installation Commander while on the premises. Contractor will obtain all necessary passes, decals, badges, or items required for access to dryer vent cleaning services at JBER.
4.5 Safety Requirements.
Contractor must perform work in a safe manner as required by OSHA. Contractor must provide a verbal report to the CO as soon as possible of each occurrence of damage to government property or an accident resulting in death, injury, occupational disease, or adverse environmental impact. Contractor must provide a completed Accident Investigation Report copy to the CO within five business days of each occurrence. The Contractor must initiate and maintain programs to comply with the provisions of OSHA and the Air Force Occupational Safety and Health (AFOSH), DAFI 91-202. Contractor must safeguard all materials and parts removed from the systems, as well as replacement parts. Contractor must immediately notify the COR when damage to government property, whether due to accident, abuse or misuse is discovered. Contractor must annotate the damage on the inspection checklist/report.
4.6 Contractor/Employee Base Pass and Identification, Special Clearances and Vehicle Passes.
During performance of the contract, Contractor is responsible for obtaining required identification for newly assigned personnel and for prompt return of credentials and vehicle passes for any employee who no longer requires access to the worksite. Additionally, upon termination of employment or end of the contract, the Contractor is to gather and return all passes and Identification Documents as directed by the COR or CO. Contractor must comply with all base access requirements and procedures set forth by Security Forces, Base Access Program.
4.7 Hazardous Material Identification.
Contractor must provide a copy of the Safety Data Sheet (SDS) for all products used to perform services to the CO and COR, 10 days prior to the contract start date. SDS are required as specified in the latest version of AF Form 3000. SDS must be submitted by the Contractor upon contract award and updated as inventory is added or deleted. Failure to provide SDS or certificate when requested could result in the Contractor being considered non-responsive and may result in termination of the contract. Contractor must provide an inventory of materials being brought onto JBER. A copy of the inventory list must be furnished to the COR and 673 CES/CEIEC at (552- 3435). If applicable, SDSs will be readily available to personnel working with hazardous materials.
Dryer Vent Cleaning Services
4.8 HAZMART.
Contractors conducting operations on JBER are required to comply with the Federal Emergency Planning and Community Right-to-Know Act (EPCRA). To meet compliance, the Contractor must supply the HAZMART, the Government hazardous materials distribution unit (HAZMART personnel) and must supply HAZMART with a Chemical Authorization List (CAL) of all chemicals proposed to be used on base 30 days prior to conducting any work on base. All hazardous materials must be approved of by HAZMART prior to being transferred to, or used on, the base. An inventory of the hazardous materials must be performed prior to commencement of work. Contractor must comply with Annex's "E" and "F" of the JBER environmental management document, the "OPLAN 19-3 EMP", for the management of hazardous materials, in particular Annex "F" Section 3, Subsections b, c and d. All Contractors conducting operations on JBER are required to comply with the federal regulations regarding the management of hazardous waste (Subpart C of 40 CFR 261) "Criteria for identifying hazardous waste"). Contractor must comply with the Annex "C" of the JBER environmental management document, the "OPLAN 19-3 EMP", for the management of hazardous waste. All Hazardous Waste must be characterized, profiled, and approve all manifests by the JBER Hazardous Waste Center prior to removing them from the base.
4.9 Spill Response.
Contractor will be briefed on JBER spill response procedures at the postaward conference. Contractor is responsible to report and promptly cleanup all spills in a manner consistent with current environmental regulations, if it is necessary to utilize government material, equipment or personnel to clean up a contractor caused spill, the Contractor is required to reimburse the Government for all associated costs.
4.10 Hazardous Material/Waste Management.
Contractor will be briefed on JBER Hazardous Material/Waste Management Plan at the postaward conference.
4.11 Hazardous Material Handling.
Contractor must supply an inventory of all materials brought on to JBER. The inventory must include product, the SDS number, quantity and be updated every 90 days. A copy of the inventory must be provided to the COR, HAZMART with 673 CES/CEIEC at (552-3435). The purpose of the inventory is to provide information to JBER for EPCRA reporting
4.12 Certification.
Individuals skilled in the trade of inspection and cleaning of dryer vent must accomplish all work and repair. Contractor must provide any applicable employee certificates to the COR/CO within 60 days of contract start date and maintain certification throughout the life of the contract. Contractor employees are required to have all appropriate local, state, and/or federal certifications and licenses to operate required vehicles.
4.13 Weapons, Firearms, and Ammunition.
Contractor employees are prohibited from possessing weapons, firearms, or ammunition on
Dryer Vent Cleaning Services themselves or within their contractor-owned or privately owned vehicle while on JBER.
4.14 Controlled Unclassified Information (CUI).
Contractor must comply with DoDI 5200.48, Controlled Unclassified Information (CUI) Program requirements. This regulation sets policy and procedures for the disclosure of records to the public and for marking, handling, transmitting, and safeguarding CUI material.
4.15 Contract Lead.
Contractor must provide a contract lead who is responsible for the performance of the work. The name of this person and alternate(s) who will act for the Contractor when the manager is absent must be designated in writing to the CO. Contract Lead and alternate must have full authority to act for the Contractor on all contract matters relating to daily operation of this contract. Contract Lead and alternate(s) must be able to read, write, speak, and understand the English language. Contractor is responsible to provide contract lead/alternate names whenever there are changes/updates.
4.16 Vehicles/Equipment.
Contractor vehicle operators must comply with all base traffic regulations. Any parking space on the installation must not be used for overnight parking of contractor and/or employee-owned vehicles, trailers, snowmobiles, all-terrain vehicles or other conveyances. Vehicles must be in operable condition, be marked with company name or logo to identify it as a contractor’s vehicle, and meet all local, state, and federal safety requirements.
5.0 PERSONNEL.
5.1 Professional Appearance.
Contractor personnel must present a neat appearance. Contractor personnel must be easily recognizable while on the installation in conjunction with this contract. This must be accomplished through the wear of distinctive clothing, overcoat, or hats, bearing the company name or logo. The coloring or design of the items selected must be such that personnel are easily and quickly identified for reasons of safety and personal protection.
5.2 Employees.
The Government is authorized to restrict the employment under the contract of any contractor employee or prospective contractor employee, who is identified as a potential threat to health, safety, security, general well-being, or operational mission of the installation and its population. All employees and potential employees must have a local background investigation prior to being granted base access. First, middle, & last name, sex, date of birth, driver’s license or ID # w/state of issue (Real ID), citizenship, passport number, company name, access start/end dates, days of the week and hours of access are currently required for all base access requests.
5.3 Alcohol/Drug Use.
The consumption of alcoholic beverages or illegal drugs by contractor personnel, while on duty, is strictly forbidden. Contractor must immediately remove any employee who is under the influence of alcohol or drugs.
Dryer Vent Cleaning Services
5.4 Substance Abuse Testing.
Contractor employees must be subject to substance abuse testing as a result of a mishap investigation when an individual’s actions or inactions are suspected as factors in a mishap sequence. The CO may identify the employees to be tested and the drugs and substances for which those employees must be tested. The service provider must accomplish the specified testing using a certified (i.e., a certified lab that meets Department of Health and Human Services (DHHS)/Substance Abuse and Mental Health Services Administration (SAMHSA) certification) medical substance abuse testing facility. Results of the test(s) must be provided to the Government solely for the purpose of completing an investigation.
5.5 Cleanup Procedure.
The Contractor must maintain and secure work areas in or near work sites and keep them free from accumulations of material and rubbish. Any hazardous or environmental waste generated from work performed must be handled in accordance with Paragraph 4.11 of this PWS upon completion of the job, the Contractor must restore the premises to its original condition.
Dryer Vent Cleaning Services
APPENDIX A
ACRONYMS & DEFINITIONS
Acronyms:
AFI – Air Force Instruction AFMAN – Air Force Manual AFOSH – Air Force Occupational Safety and Health Act AN - Annual AQL – Acceptable Quality Level CAL - Chemical Authorization List CAR – Corrective Action Report CES/CEIEC – Environmental Office COR – Contracting Officer’s Representative DHHS/SAMHSA - Department of Health and Human Services/Substance Abuse and Mental Health Services Administration DoDI - Department of Defense Instruction EMP – Environmental Management Plan EPCRA - Federal Emergency Planning and Community Right-to-Know Act IAW – In Accordance With JBER - Joint-Base Elmendorf-Richardson JBERI - Joint-Base Elmendorf-Richardson Instruction NFPA - National Fire Protection Agency OPLAN – Operations Plan OSHA - Occupational Safety and Health Act PWS – Performance Work Statement QA – Quality Assurance QCP – Quality Control Plan SDS – Safety Data Sheet SA - Semiannual SS – Service Summary
Definitions:
Corrective Action Report (CAR). A report issued to the Contractor, citing unsatisfactory services or performance for which the Contractor is responsible under the PWS.
Contracting Officer’s Representative (COR). An individual designated in writing by the CO and authorized to perform specific technical or administrative functions.
Damage to Government Property. Damage or abnormal deterioration caused by physical abuse or negligence.
Dryer Vent Cleaning Services
Escort. One or more persons accompanying the Contractor in high security areas on JBER.
Inspection (As performed by contractor on equipment). Means visual and/or mechanical checking of the condition of the systems to determine the extent of the maintenance required and to ensure the proper operation of the system.
Listed. Equipment or materials included in a list published by an organization acceptable to the authority having jurisdiction and concern with product evaluation, that maintains periodic inspection of listed equipment or materials and whose listing states either that the equipment or material meets appropriate standards or has been tested and found suitable for use in the specified manner.
Quality Control Plan (QCP). A quality control program providing self-inspection to ensure maintenance and repair services are performed satisfactorily.
Service. A job performed to the standard and within the acceptable quality level. Contractor must perform the specific job, meet the standard, meet the acceptable quality level before one can say that performance has been acceptable, and the work approved for payment.
Service Abbreviations.
(AN) = Annual (SA) = Semi-Annual
Services Summary (SS). Identifies the key service outputs of the contract being evaluated by the Government to assure contract performance.
Dryer Vent Cleaning Services
Technical Exhibit Dryer Vent Services This tech exhibit is a representation of the locations and quantity of workload and is subject to change; any future issued tech exhibits will supersede this document without the need for a mod so long as the scope is not changed.
Highlighted may be readded in the future.
BLDG#
FACILITY NAME/TYPE
LOCATION
QTY
FREQUENCY
CLEANING
TOTAL
CLEAN
6 Kodiak CDC room 11 2 2 (SA) 4 11 Talkeetna CDC room 108 3 2 (SA) 6 55 Barracks room B012 3 2 (SA) 6
602 Barracks rooms 156, 260, 360 12 2 (SA) 24 620 Barracks rooms 118, 216, 316 14 2 (SA) 28 622 Barracks rooms 118, 216, 316 14 2 (SA) 28 624 Barracks rooms 118, 216, 316 14 2 (SA) 28 626 Barracks rooms 117, 215, 315 14 2 (SA) 28 628 Barracks rooms 117, 215, 315 14 2 (SA) 28 630 Barracks rooms 118, 216, 316 14 2 (SA) 28 632 Barracks rooms 118, 216, 316 14 2 (SA) 28 641 Barracks rooms 113, 145, 206, 245, 313, 36 2 (SA) 72
649 Barracks rooms 112, 212 8 2 (SA) 16 651 Barracks room 013 28 2 (SA) 56 654 Fire Station #4 Truck Bay 7 1 1 (AN) 1 668 Barracks rooms 113, 220, 320 9 2 (SA) 18
Barracks rooms 158, 178, 258, 272, 358, 368, 458, 558, 566
2 (SA)
682 Barracks rooms 128, 172, 228, 272, 328, 372, 428 56 2 (SA) 112
688 Barracks each suite 96 2 (SA) 192
Buckner Physical Fitness
Center room 127 2 1 (AN) 2 791 Barracks 356 30 2 (SA) 60
1107 Lodging laundry room 3 2 (SA) 6 3786 Fire Station #3 Truck Bay 1 1 1 (AN) 1 4995 dormitory 1st floor, laundry room 4 2 (SA) 8 4995 dormitory 2nd floor, laundry room 4 2 (SA) 8
4995 dormitory rooms 131, 132, 133, 134, 145, 147, 148, 149, 151 9 2 (SA) 18 dormitory rooms 231, 232, 233, 234, 235, 246, 247, 248, 251
2 (SA)
5126 Fire Station #2 Truck bay 3 1 1 (AN) 1 6210 Fire Dept Truck bay 1 1 1 (AN) 1 6376 Sitka CDC kitchen 3 2 (SA) 6 7053 dormitory 1st floor 8 2 (SA) 16 7053 dormitory 2nd floor 8 2 (SA) 16 7053 dormitory 3rd floor 8 2 (SA) 16 7079 dormitory 2nd floor 10 2 (SA) 20 7079 dormitory 3rd floor 5 2 (SA) 10 7083 dormitory 1st floor 10 2 (SA) 20 7083 dormitory 2nd floor 10 2 (SA) 20
Dryer Vent Cleaning Services
7083 dormitory 3rd floor 10 2 (SA) 20 7113 dormitory 1st floor 4 2 (SA) 8 7148 Lodging 1st floor laundry room 3 2 (SA) 8 7153 Lodging 1st floor, room 1128 (west end) 3 2 (SA) 6 7153 Lodging 2nd floor, room B113 (east end) 3 2 (SA) 6 7153 Lodging 2nd floor, room B103 (west end) 3 2 (SA) 6 7153 Lodging 3rd floor, room C113 (east end) 3 2 (SA) 6 7153 Lodging 3rd floor, room C103 (west end) 3 2 (SA) 6 7136 Ketchikan School Age room 133 1 1 (AN) 1 7179 Lodging 1st floor, room 2152 (east end) 3 2 (SA) 6 7179 Lodging 1st floor, room 2112 (west end) 3 2 (SA) 6 7179 Lodging 2nd floor, room 2247 (east end) 3 2 (SA) 6 7179 Lodging 2nd floor, room 2212 (west end) 3 2 (SA) 6 7179 Lodging 3rd floor, room 2348 (east end) 3 2 (SA) 6 7179 Lodging 3rd floor, room 2312 (east end) 3 2 (SA) 6 7181 Katmai CDC laundry room (Rm 2) 2 2 (SA) 4 7371 ADA rooms 4332 1 1 (AN) 1 7373 ADA rooms 4402 1 1 (AN) 1 7377 Denali CDC room 122 3 1 (AN) 3 7474 Lodging rooms 1724 – 1727 4 2 (SA) 8 7476 Lodging rooms 1716 – 1719 4 2 (SA) 8 7478 Lodging rooms 1708 – 1711 4 2 (SA) 8 7480 Lodging rooms 1704 – 1707 4 2 (SA) 8 7482 Lodging rooms 1700 – 1703 4 2 (SA) 8 7484 Lodging rooms 1712 – 1715 4 2 (SA) 8 7486 Lodging rooms 1720 – 1723 4 2 (SA) 8 7488 Lodging rooms 1728 – 1731 4 2 (SA) 8 7490 Lodging rooms 1732 – 1735 4 2 (SA) 8 7492 Lodging rooms 1740 – 1743 4 2 (SA) 8 7494 Lodging rooms 1736 & 1739 4 2 (SA) 8 7496 Lodging rooms 1748 – 1751 4 2 (SA) 8 7498 Lodging rooms 1744 – 1747 4 2 (SA) 8 8005 dormitory 2nd floor 20 2 (SA) 40 8113 dormitory 1st floor (Renovation) 0 2 (SA) 0 8119 dormitory room 105A 6 2 (SA) 12 8119 dormitory room 202A 6 2 (SA) 12 8119 dormitory room 302A 6 2 (SA) 12 8371 Lodging room 4304 8 2 (SA) 16 8373 ADA rooms 4322 1 1 (AN) 1 8375 ADA rooms 4312 1 1 (AN) 1 8378 Lodging room 6201 6 2 (SA) 12 8450 Lodging basement (laundry room) 2 2 (SA) 4 9510 Elmendorf Fitness Center Laundry RM 104 2 1 (AN) 2
11415 Fire Station #1 Truck Bay 6 1 1 (AN) 1 14431 Fire Station #7 Bay 1 1 1 (AN) 1 16673 Fire Station # 6 Bay 1 1 1 (AN) 1 48010 Fire Station #5 Truck Bay 3 1 1 (AN) 1
Dryer Vent Cleaning Services
36‐100 Illa School Age Center room 14 1 1 (AN) 1
Total cleanings 1,443
731 TOTAL VENTS
Dryer Vent Cleaning Services
File details come from the government source that posted it. Updated .