ATCH-03_1240BE26Q0002_QASP.pdf
PDF 476 KB Posted
- Solicitation number
- 1240BE26Q0002
- Issued by
-
Department of Agriculture Forest Service
About this file
Quality Assurance Surveillance Plan Summary
This is a Quality Assurance Surveillance Plan (QASP) for roadway maintenance services on the Umatilla National Forest under solicitation 1240BE26Q0002. The USDA Forest Service will use this plan to monitor contractor performance on an estimated 269.7 miles of road in the south zone and 165.6 miles in the north zone. The plan establishes systematic procedures for measuring performance, defining roles and responsibilities, identifying performance objectives, and evaluating whether the contractor meets standards specified in the Performance Work Statement (PWS). The Contracting Officer (CO) administers contract compliance and cost control, while the Contracting Officer Representative (COR) executes the quality assurance function, conducts surveillance, and makes recommendations for corrective action or commendation. The contractor must implement a Quality Control Plan (QCP) describing methods to ensure products and services meet established performance standards and Acceptable Quality Levels (AQLs).
Performance is evaluated through 100 percent monthly inspections using AQLs calculated by dividing acceptable occurrences by total possible occurrences. Contractors receive performance ratings of Exceptional, Very Good, Satisfactory, Marginal, or Unsatisfactory based on compliance with contractual requirements and effectiveness of corrective actions. Appendix A specifies maintenance standards for road surface maintenance (Section 811) on passenger car roads and high clearance roads, including requirements for moisture, material reclamation, cutting passes, shoulder clearing, surface spreading to specified widths (14 feet for single lane, 24 feet for double lane), and finished surface quality. Section 842 covers roadway vegetation maintenance requiring vegetation removal, damaged tree treatment, and debris disposal. Both sections include requirements for controlling non-native invasive plant species by cleaning equipment before moving between areas. Major and minor defects are defined with allowable thresholds; rework is required if defects exceed tolerances. The COR documents non-conformance with contract requirements and recommends corrective actions or penalties to the CO.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ATCH-03 1240BE26Q0002_QASP Page 1 of 13 Pages
US Department of Agriculture (USDA)
Quality Assurance Surveillance Plan
Roadway Maintenance Service for the Umatilla National Forest
Solicitation: 1240BE26Q0002
Purchase Order: TBD
ATCH-03 1240BE26Q0002_QASP Page 2 of 13 Pages
Contents Project Name Solicitation / Contract Number Section 1: Introduction
1.1 Purpose
1.2 QASP Relation to the Contract
1.2.1 QASP Revisions
1.2.2 Surveillance of Performance Progression
1.3 QASP Relation to the Quality Control Plan (QCP)
Section 2: Performance Description
2.1 Performance Standards and Acceptable Quality Levels (AQLs)
2.1.1 Allowable Deviation
2.1.2 Substantially Complete
2.2 Non-Performance
2.2.1 Documentation
2.2.2 Remedial Actions
Section 3: Contractor and Government Responsibilities
3.1 Contractor Responsibility
3.2 Government Responsibility
3.2.1 Contracting Officer (CO)
3.2.2 Contracting Officer Representative (COR)
3.2.3 Customers
Section 4: Surveillance Methods to Perform Quality Assurance
4.1 Surveillance Methods
4.2 Analysis and Results
Appendix A: Maintenance Standards and Quality Levels Appendix B: US Forest Service Daily Diary
ATCH-03 1240BE26Q0002_QASP Page 3 of 13 Pages Project Name Road Maintenance Service for the Umatilla National Forest
Solicitation / Contract Number
Section 1: Introduction This Quality Assurance Surveillance Plan (QASP) is pursuant to the requirements listed in the performance work statement (PWS) Roadway surface and vegetation maintenance on an estimated 269.7 miles of road in the south zone, and 165.6 miles in the north zone. Specific performance tasks are listed in PWS Paragraph 3.
This plan sets forth the procedures and guidelines that the USDA, Umatilla National Forest will use in ensuring the required performance standards or services levels are achieved by the contractor.
1.1 Purpose
The purpose of the QASP is to describe the systematic methods used to measure performance and to identify the reports required and the resources to be employed. The QASP provides a means for evaluating whether the contractor is meeting the performance standards identified in the Performance Work Statement, PWS.
This QASP is designed to define roles and responsibilities, identify the performance objectives, define the methodologies used to monitor and evaluate the contractor’s performance, describe quality assurance reporting, and describe the analysis of quality assurance monitoring results.
1.2 QASP Relation to the Contract
1.2.1 QASP Revisions
The Contracting Officer Representative (COR) may make revisions or changes to the QASP procedures and surveillance methods or increase or decrease the degree of surveillance methods at any time during the contract performance period. Changes to the Metric must be incorporated into the PWS, Performance Requirement Summary (PRS) and QASP by a bilateral modification to contract that is issued by the Contracting Officer (CO). A copy of the QASP is provided to the contractor to enable the contractor to enhance its Quality Control (QC) program to perform in accordance with its Quality Control Plan (QCP).
1.2.2 Surveillance of Performance Progression
As the performance period progresses, the levels of surveillance may be altered for service areas where performance is either consistently excellent or unsatisfactory. If consistently good performance, then the amount of surveillance may be reduced. If observations reveal consistent deficiencies, increased surveillance may be implemented.
1.3 QASP Relation to the Quality Control Plan (QCP)
The QCP is a required element of contract and the Contractor shall adhere to its established quality control processes and procedures in managing and performing work as described in the contract. While the QCP represents the way in which the Contractor will ensure its quality and timeliness of services, as defined in the PWS, the QASP represents the way in which the Government personnel specified in Section 3: Contractor and Government Responsibilities, Paragraph 3.2, Government Responsibilities will evaluate the contractor’s performance. The contractor’s QC program and the residual organization’s QASP should be complementary programs that ensure successful contractor performance.
Section 2: Performance Description Performance of the contractor will be monitored through the surveillance methods described in Section 4:
Surveillance Methods to Perform Quality Assurance to assess the Contractor’s performance against PWS requirements.
2.1 Performance Standards and Acceptable Quality Levels (AQLs) For selected activities in the PWS, the PRS provides a performance standard and an AQL. A performance standard is the expected level of contractor performance. An AQL defines the level of performance that is satisfactory. Depending on the service evaluated and the evaluation method selected, performance standards and AQLs may be stated as a number of occurrences or as a percentage. Performance standards and AQLs for random sampling and 100 percent inspection are generally stated as percentages. For periodic inspections, performance standards may be stated as either percentages or as absolute numbers.
ATCH-03 1240BE26Q0002_QASP Page 4 of 13 Pages
The contract requires the Contractor to perform all work as specified. Any inaccuracies or omissions in services or products are referred to as “defects” on the part of the Contractor. The Contractor shall be responsible for all identified defects and may be required to perform the work at no cost to the government.
The AQLs take into account that in some instances an allowable level of deficiencies (deviations) is possible while overall performance continues to meet the government’s desired level of service.
2.1.1 Allowable Deviation
The AQLs define the level or number of performance deficiencies the Contractor is permitted to reach under this contract. AQLs take into account the difference between an occasional defect and a gross number of defects. AQLs can be expressed as a percentage of or as an absolute number (e.g., three per month). There may be instances where 100 percent compliance is required, and no deviation is acceptable (e.g., where safety is involved).
2.1.2 Substantially Complete
In some cases, service outputs are evaluated using subjective values (e.g., excellent, satisfactory, unsatisfactory). The criteria for acceptable performance and for defects must be defined for these service outputs. The concept of “substantially complete” should be the basis for inspections based on subjective scales. Work is considered “substantially complete” where there has been no significant departure from the terms of the contract and no omission of essential work. In addition, the Contractor has performed the work required to the best of its ability and the only variance consists of minor omissions or deficiencies.
2.2 Non-Performance
Non-performance occurs when the contractor’s performance does not meet the AQL for a given requirement.
Requirements may contain multiple performance elements, and therefore, deficiencies may occur in one or more aspects of performance (e.g., timeliness, accuracy, completeness, etc.) or subject areas of effort.
When surveillance indicates that the contractor's service output is not in compliance with the contract requirements, the Contracting Officer’s Representative (COR) must determine whether the Contractor or the Government caused the deficiency. If the cause of the defect rests with the Government, corrective action must be taken through Government channels. If the cause of the defect is due to action or inaction by the contractor, the contractor is responsible for correction of the problem at no additional expense to the Government.
2.2.1 Documentation
Documentation of work non-performed or unacceptable work is essential for tracking Contractor performance. The COR will document deficient work by compiling facts describing the inspection methods and results and to substantiate nonconformance with the contract. A sample documentation reporting form is provided in Appendix B, Example Discrepancy Report. The documentation, with any recommendations, will be forwarded to the CO. In the case of the Contractor, the COR will decide whether to elevate the problem to the CO for corrective action.
2.2.2 Remedial Actions
The Federal Acquisition Regulation allows for penalties in the event that the Contractor fails to perform the required services. Penalties are defined as those actions taken under the direction of the CO against the contractor within the general provisions of the contract for nonconformance to the PWS and PRS.
Section 3: Contractor and Government Responsibilities
3.1 Contractor Responsibility
The Contractor is responsible for delivering products or services in accordance with the contract.
Implementing its QCP, which describes the Contractor’s methods for ensuring all products and services under the contract meet established performance standards and AQLs. Maintaining, and providing for audit, quality control records and reports and all records associated with the investigation and complaint resolutions.
Appointing a single quality control point-of-contact to act as a central recipient of communication from the COR or CO.
ATCH-03 1240BE26Q0002_QASP Page 5 of 13 Pages
3.2 Government Responsibility
3.2.1 Contracting Officer (CO)
The CO is responsible for administering and monitoring contract compliance, contract administration, and cost control and for resolving any differences between the observations documented by COR and the contractor’s performance. The CO may delegate various day-to-day contract administration duties to the COR for performance management and administrative actions such as invoice approval and issuance of Contract Discrepancy Reports may be, and normally are, delegated by the CO to the COR. The CO shall approve any revisions to the QASP processes or standards.
3.2.2 Contracting Officer Representative (COR)
The COR, is designated in writing, by the CO. The COR will ensure that the QA function is properly executed, plays a key role in contract administration and performs the contract surveillance and monitoring.
Some key contract administration duties include, but are not limited to, performs surveillance as required by this QASP; make recommendations to the CO for issuance of Contract Discrepancy Reports or letters of commendation and acceptance or rejection of completed work and for administrative actions based on unsatisfactory or non-performed work, and revisions or changes to the QASP; and assists the CO in identifying necessary contract modifications and preparing reports of Contractor performance and cost.
The COR may use the form(s) included in the Appendices to perform the inspection or other forms as approved by the CO.
3.2.3 Customers
Customers or organizations/offices that the Contractor provided support may be requested to assist the COR in conducting QA to provide information relating to the Contractor’s performance through Customer Feedback. Information gained from the Customer Feedback may be used in conjunction with other methods of observation to rate the performance of the Contractor.
Section 4: Surveillance Methods to Perform Quality Assurance
4.1 Surveillance Methods
The surveillance methods used in the QA process are the Government’s tools to monitor the Contractor’s products and services. The best means of determining whether the Contractor has met all contract requirements is to inspect the Contractor’s service products and analyze the results. Further, documented inspection results are an effective tool in contract administration that can confirm the successful achievement of all performance requirements or highlight areas where defects exist and improvements are necessary.
4.1.a 100 Percent Inspection The 100 percent inspection method requires complete inspection each month and will be used for critical contract requirements.
4.1.b Performance Standards and AQLs Calculating Acceptable Quality Level, AQL: Acceptable quality levels AQL will be calculated by dividing the number of acceptable occurrences observed by the number of possible occurrences observed. For example: Paragraph 3.2 in month one the COR observed 20 roadway maintenance services. Of the 20 observed services, 18 were satisfactory. 18 satisfactory observations divided by 20 possible observation equals 0.9 or 90%.
4.2 Analysis and Results
When the inspections and validations have been completed, the COR will perform an analysis of the Contractor’s performance. The purpose of the analysis is to ensure Government is receiving high-quality products and services from the Contractor. The COR will review the results, rate the Contractor’s compliance with the performance standards and AQLs, and characterize the Contractor’s overall performance. Analysis of all types of contract monitoring will result in one of the following outcomes:
ATCH-03 1240BE26Q0002_QASP Page 6 of 13 Pages
Performance Rating
Criteria
Exceptional
Performance meets contractual requirements and exceeds many to the Government’s benefit. The contractual performance of the element or sub-element being evaluated was accomplished with few minor problems for which corrective actions taken by the contractor were highly effective.
Very Good
Performance meets contractual requirements and exceeds some to the Government’s benefit. The contractual performance of the element or sub-element being evaluated was accomplished with some minor problems for which corrective actions taken by the contractor were effective.
Satisfactory Performance meets contractual requirements. The contractual performance of the element or sub-element contains some minor problems for which corrective actions taken by the contractor appear or were satisfactory.
Marginal
Performance does not meet some contractual requirements. The contractual performance of the element or sub-element being evaluated reflects a serious problem for which the contractor has not yet identified corrective actions. The contractor’s proposed actions appear only marginally effective or were not fully implemented.
Unsatisfactory
Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The contractual performance of the element or sub-element contains a serious problem(s) for which the contractor’s corrective actions appear or were ineffective.
ATCH-03 1240BE26Q0002_QASP Page 7 of 13 Pages Appendix A: Maintenance Standards and Quality Levels
811 – Road Surface Maintenance Passenger Car Roads and High Clearance Roads
Umatilla National Forest (02/09)
811.01
Services Required
Perform maintenance on roadway surfaces to facilitate safe travel on passenger car or high clearance roads.
811.02
Performance Standards
Passenger Car Road Surface Maintenance
Roadway surfaces are maintained to standard when:
• There is adequate moisture present to facilitate cutting to a depth to completely remove washboards and potholes (see note regarding watering in Section 811.05).
• Retrievable suitable materials outside the standard traveled way widths (described below) have been reclaimed and incorporated into the remaining surface course.
• A cutting pass has been made (where adequate crushed aggregate depths exist) over the entire width of the traveled way, including turnouts.
• Shoulders, turnouts, and intersections are free of washboards, potholes, unsuitable materials, or other irregularities.
• There is adequate moisture present to adequately bind the surface materials for compaction by traffic at the time of the spread.
• The surface materials have been spread to the following approximate standard traveled way widths:
o Single Lane Road Segments: Width = 14 Feet, Turnouts = 10 Feet o Double Lane Road Segments: Width = 24 Feet
• Finished surfaces are smooth, uniform, and crowned/sloped to drain.
High Clearance Road Surface Maintenance
Roadway surfaces are maintained to standard when:
• Retrievable suitable materials outside the standard traveled way width (single lane road segments as described above) have been reclaimed and incorporated with the surface course.
• A cutting pass has been made (where adequate crushed aggregate depths exist) over the entire width of the traveled way, including turnouts.
• The traveled way is uniform, shaped to drain, has no continuous ruts or rills, and is free of concentrations of unsuitable materials and obstructions inhibiting high clearance vehicle travel.
ATCH-03 1240BE26Q0002_QASP Page 8 of 13 Pages Requirement for Non-native Invasive Plant Species Control
Prior to entering National Forest lands, all road maintenance equipment shall be cleaned to minimize the potential spread of non-native invasive plant species. Prudent actions, such as washing or using compressed air, shall be taken to clean equipment, prior to moving from one project area to another within the National Forest, to ensure that these species are not spread.
811.03
Location of Work
Work will apply to those road segments shown on the road listings. Work on additional road segments may be ordered by the Contracting Officer.
811.04
Measurement
Measurement will be made of each item or unit of work, as shown in the Schedule of Items, completed and accepted in accordance with the contract provisions, specifications, and drawings.
• Mile - All work under this specification will be measured along the linear centerline of the roadway, and rounded to the nearest tenth (0.1) of a mile.
811.05
Payment
Accepted quantities will be paid at the contract price per unit of measurement for the Section 811 pay items listed in the Schedule of Items. Payment will be full compensation for the work prescribed in this section.
NOTES: Mobilization, removal of obstructions, and watering are incidental to pay items.
Removal of Obstructions - Efforts shall be made to have debris removed from roads prior to commencement of surface maintenance. However, obstructions encountered during surface maintenance activities shall be removed by the contractor in accordance with the Standard Logout Typical.
Watering – This requirement shall be waived if there is not an adequate (readily recoverable) water source within 5 miles of the segment being maintained.
Pay Item Pay Unit
811(02) Road Surface Maintenance Mile Double Lane Passenger Car Roads
811(03) Road Surface Maintenance Mile Single Lane Passenger Car Roads
811(05) Road Surface Maintenance Mile High Clearance Roads
811.06
Acceptable Quality Levels
Acceptance will be determined by visual inspection. If visual inspection finds that all work conforms to performance standards (811.02), the work will be acceptable. If visual inspection finds that occasional work elements do not completely conform to performance standards, but non-conforming work is not representative of the overall quality of work, the work will be acceptable. If visual inspection finds that non-conforming work is representative of the overall quality of work, rework will be required.
ATCH-03 1240BE26Q0002_QASP Page 9 of 13 Pages
842 - Roadway Vegetation Maintenance Umatilla National Forest
(02/13)
842.01
Service Required
Remove and dispose of vegetation to provide for user safety, and to facilitate roadway surface and drainage maintenance.
842.02
Performance Standards
1. Vegetation Maintenance
Vegetation maintenance is attained when vegetation has been removed, damaged trees have been removed or treated, and residual debris has been properly disposed of (as shown on the Standard Brushing Typical and described in the Acceptable Quality Levels).
NOTE: Standards for double lane road segments are greater than those for single lane road segments (see Brushing List and Standard Brushing Typical).
2. Requirement for Non-native Invasive Plant Species Control
Prior to entering National Forest lands, all road maintenance equipment shall be cleaned to minimize the potential spread of non-native invasive plant species. Prudent actions, such as washing or using compressed air, shall be taken to clean equipment, prior to moving from one project area to another within the National Forest, to ensure that these species are not spread.
834.03
Location of Work
Work will apply to those areas shown on the task order or drawings. Additional work may be ordered by the Contracting Officer.
842.04
Measurement
Measurement will be made of each item or unit of work, as shown in the Schedule of Items, completed and accepted in accordance with the contract provisions, specifications, and drawings.
Mile: Work activities by the mile will be measured along the linear centerline of the roadway, and rounded to the nearest tenth (0.1) of a mile.
ATCH-02_1240BE26Q0002 QASP Page 10 of 15 Pages 842.05
Payment
Accepted quantities will be paid at the contract price per unit of measurement for the Section 842 pay items listed in the Schedule of Items. Payment will be full compensation for the work prescribed in this section.
3. NOTE: Mobilization is incidental to pay items.
Pay Item Pay Unit
842(01) Roadway Vegetation Maintenance
Double Lane Road Segments Mile
842(02) Roadway Vegetation Maintenance
Single Lane Road Segments
ATCH-02_1240BE26Q0002 QASP Page 11 of 15 Pages
Description
Major Defect Allowable
Major Defects
Action Required to Correct Major
Defects Minor Defect Allowable
Minor Defects
Action Required to Correct Minor
Defects
Vegetation Removal
Vegetation remaining within the brushing window, above the traveled way
None
Rework
Vegetation remaining within the brushing window, not above the traveled way
An aggregate total of 100 linear feet in any one mile segment.
Spot occurrences shall count for a minimum of 10 linear feet.
Rework, if more than 100 linear feet in any one mile segment exist.
Vegetation not removed to within 4 inches above the ground over the entire traveled way
Vegetation not removed to within 6 inches above the ground outside the traveled way, within the brushing window
An aggregate total of 100 linear feet in any one mile segment.
Spot occurrences shall count for a minimum of 10 linear feet.
Rework, if more than 100 linear feet in any one mile segment exist.
Vegetation remaining that obscures clear view of signs and markers.
Vegetation remaining within the brushing window, not removed to within 18 inches of an obstruction
Continued next page…
ATCH-02_1240BE26Q0002 QASP Page 12 of 15 Pages
Description
Major Defect Allowable
Major Defects
Action Required to Correct Major
Defects Minor Defect Allowable
Minor Defects
Action Required to Correct Minor
Defects
Tree Damage
Bark peeled more than 4 inches in any dimension on trees outside the brushing window
Fell tree and scatter with other brushing debris
Bark peeled less than 4 inches in any dimension on trees outside the brushing
A total of 10 occurrences in any one mile segment.
Treat with approved material, if more than 10 occurrences in any one mile segment exist.
Brushing Debris
Disposal
Concentration of brushing debris, greater than 3 feet in height, outside the brushing window
Concentration of brushing debris, 3 feet or less in height, outside the brushing window
A total of 2 occurrences in any one mile segment.
Rework, if more than 2 occurrences in any one mile segment exist.
Brushing debris placed in a drainage facility (ditch or culvert), outside the brushing
Brushing debris placed on a cut slope, outside the brushing window
1 occurrence in any one mile segment.
Rework, if more than 1 occurrence in any one mile segment exists.
ATCH-02_1240BE26Q0002 QASP Page 13 of 15 Pages
Appendix B: USDA Forest Service, Contract Daily Diary
USDA - Forest Service FS-6300-0020 Rev 01/17
CONTRACT DAILY DIARY
(Reference FSH 6309.32)
1. FOREST
2. CONTRACT NO.
3. PROJECT
4. CONTRACTOR 5. CONTRACTOR
REPRESENTATIVE ON
SITE
6. GOVERNMENT OFFICIALS ON SITE
7. DATE 8. DAY OF WEEK 9. TIME ARRIVED 10. TIME DEPARTED 11. WEATHER
12. TEMPE
Min.
RATURE °F.
Max.
13. GROUND CONDITION 14. CONTRACT TIME 15. DAYS USED 16. COMPLETION DATE
17. TIME USED (%) 18. WORK COMPLETED (%) 19. WORK ON SCHEDULE 20. CONTRACTOR'S WORK - (X Appropriate Box)
YES NO Acceptable Unacceptable - Explain in narrative
21. CHANGE ORDERS/AMENDMENTS ISSUED 22. WORK ORDERS ISSUED (Include SUSPEND/RESUME)
23. MATERIALS FURNISHED TO JOB SITE (Furnished By: G-Govt.; C-Cont.; S-Subcont.) 24. LIST EQUIPMENT ON SITE (Furnished by G-Govt.; C-Cont.; S-Subcont.)
Type Contract Item Number and Location of Use Hours Used
25. LIST CONTRACT PAYMENTS, REPORTS, CORRESPONDENCE, ETC. 26. WORKERS ON SITE Number
Item Prep Submit Classification PRIME SUB
27. GOVERNMENT PROVIDED SERVICES ADEQUATELY AND
TIMELY
YES NO - Explain in narr ativ e
28. NARRATIVE REPORT
29. SIGNATURE 30. TITLE 31. ADDTL SPACE NEEDED
(continued on 6300-21)
| Project Name |
| Solicitation / Contract Number |
| Section 1: Introduction |
| 1.1 Purpose |
| 1.2 QASP Relation to the Contract |
| 1.2.1 QASP Revisions |
| 1.2.2 Surveillance of Performance Progression |
| 1.3 QASP Relation to the Quality Control Plan (QCP) |
| Section 2: Performance Description |
| 2 |
| 2.1 Performance Standards and Acceptable Quality Levels (AQLs) |
| 2.1.1 Allowable Deviation |
| 2.1.2 Substantially Complete |
| 2.2 Non-Performance |
| 2.2.1 Documentation |
| 2.2.2 Remedial Actions |
| Section 3: Contractor and Government Responsibilities |
| 3 |
| 3.1 Contractor Responsibility |
| 3.2 Government Responsibility |
| 3.2.1 Contracting Officer (CO) |
| 3.2.2 Contracting Officer Representative (COR) |
| 3.2.3 Customers |
| Section 4: Surveillance Methods to Perform Quality Assurance |
| 4 |
| 4.1 Surveillance Methods |
| 4.2 Analysis and Results |
| Appendix A: Maintenance Standards and Quality Levels |
| 1. Vegetation Maintenance |
| 2. Requirement for Non-native Invasive Plant Species Control |
| 3. NOTE: Mobilization is incidental to pay items. |
| Appendix B: USDA Forest Service, Contract Daily Diary |
File details come from the government source that posted it. Updated .