At10_PriceSchedule.xlsx
XLSX spreadsheet 22 KB Posted
- Attached to
- GAOA BAR ISLAND DAM RECONSTRUCTION
- Solicitation number
- 140L0626R0006
About this file
This is a price schedule (bid schedule) for the Bar Island Dam Reconstruction project under GAOA funding, managed by the Department of the Interior Bureau of Land Management. The schedule itemizes 21 base line items and one optional item for which bidders must provide unit prices and total prices.
The base work scope includes mobilization and preparatory work, site clearing and restoration, demolition of the existing primary spillway, and excavation of approximately 35,000 cubic yards of common excavation and 2,700 cubic yards of muck excavation. The project requires construction of compacted embankment (32,000 cubic yards), lime-amended embankment (2,150 cubic yards), filter sand (780 cubic yards), and drain gravel (350 cubic yards). Additional items include installation of an 18-inch CMP culvert (27 linear feet), primary spillway riser and inlet structure, primary spillway conduit, stilling basin, toe drain, class 1 riprap slope protection (240 tons), water control and dewatering, stabilization fabric (2,000 square yards), and filter fabric (400 square yards). The optional item includes spillway armoring. All item prices are fully burdened and must include overhead, profit, and bond costs, with bidders required to specify their respective overhead, profit, and bond rates. Quantities noted are not guaranteed, with measurement and payment defined separately in the contract documents.
View the file
Other files
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BarIsland BidSched
| BAR ISLAND DAM RECONSTRUCTION |
| SCHEDULE OF ITEMS |
| Item | |||||
| No. | Description | Quantity* | 0 | Unit Price | Total Price** |
| 1 | Mobilization and Preparatory Work | 1 | LS | $0.00 | |
| 2 | Site Clearing and Restoration | 1 | LS | $0.00 | |
| 3 | Existing Primary Spillway Demolition | 1 | LS | $0.00 | |
| 4 | Common Excavation | 35,000 | CY | $0.00 | |
| 5 | Muck Excavation | 2,700 | CY | $0.00 | |
| 6 | Compacted Embankment | 32,000 | CY | $0.00 | |
| 7 | Lime Amended Embankment | 2,150 | CY | $0.00 | |
| 8 | Filter Sand | 780 | CY | $0.00 | |
| 9 | Drain Gravel | 350 | CY | $0.00 | |
| 10 | Road Gravel | 280 | TON | $0.00 | |
| 11 | 18" CMP Culvert | 27 | LF | $0.00 | |
| 12 | Primary Spillway Riser and Inlet Structure | 1 | LS | ||
| 13 | Primary Spillway Conduit | 1 | LS | ||
| 14 | Stilling Basin | 1 | LS | ||
| 15 | Toe Drain | 1 | LS | ||
| 16 | New Class 1 Riprap Slope Protection | 240 | Ton | ||
| 17 | Water Control/Dewatering | 1 | LS | ||
| 18 | Stabilization Fabric | 2,000 | SY | ||
| 19 | Filter Fabric | 400 | SY | $0.00 | |
| 20 | General Construction Operations | 1 | LS | $0.00 | |
| BASE PRICE | $0.00 |
| OPTION(S) | |||
| 21 | Spillway Armoring | 1 | LS |
| OPTION(S) PRICE |
TOTAL PRICE (BASE + OPTION(S))
| Rate*** | |
| Overhead | % |
| Profit | % |
| Bonds | % |
| *Quantities are not guaranteed. Measurement and payment for each Item is defined in Section 01150, Measurement and Payment. |
| ** Total Price for each Item is fully burdened and includes Overhead, Profit, and Bond. |
| *** Overhead, Profit, and Bond rates used in the total price to be provided. |
&"Arial,Regular"&8&Z&F &"Arial,Regular"&9BID SCHEDULE&"MS Sans Serif,Regular"&8
File details come from the government source that posted it. Updated .