At01_SOW_LittleCreekCampground_Feb26.pdf
PDF 509 KB Posted
- Attached to
- LITTLE CREEK CAMPGROUND DESIGN-BUILD
- Solicitation number
- 140L0626R0005
About this file
This is a Design-Build Statement of Work (SOW) for the Little Creek Campground Improvements project under the Bureau of Land Management's Salt Lake Field Office, dated February 2026.
The Design-Build Contractor (DBC) shall perform both design and construction services for campground improvements located approximately 3 miles west of Randolph, Utah. The project scope includes redesigning and constructing nine individual campsites with shade pavilions, tent pads, fire rings, and gas stove platforms; replacing a group site pavilion with capacity for 8 picnic tables and 50 people; installing two metal information kiosks; remediating storm drainage issues; installing water distribution and irrigation systems; adding approximately 35 shade trees; and constructing parking areas and access routes compliant with ADA/ABA standards. Phase 1 construction focuses on the main entrance parking lot and group site, with Phase 2 to be constructed when future funding becomes available. All Architect-Engineer services must be performed by licensed Landscape Architects and Engineers registered in Utah.
Design deliverables follow a phased approach: Conceptual Site Design due 45 days after award with three alternative site plans; 65% Construction Documents due 30 days after conceptual approval; 95% Construction Documents due 30 days later; 100% Construction Documents due 30 days after that; and Complete Stamped and Signed Construction Documents due 15 days after 100% approval. The DBC must comply with BLM standards, ADA/ABA accessibility guidelines, ABAAS, MUTCD, ACI concrete standards, and National Park Service campground design guidelines. Construction shall not begin until the Government issues a DB Construction Start Work Notice. All work and deliveries occur Monday-Friday from sunrise to sunset unless approved otherwise. Progress payments during design phase are based on submission and acceptance of design deliverables, while construction phase payments are based on percentage of work completed per an approved Schedule of Values. The DBC must establish a file sharing site for document exchange, submit all materials electronically in both original software format and PDF, and comply with specific formatting requirements for drawings (ANSI B size, AutoCAD 2024 or Revit 2024) and specifications (MasterFormat organized). Key contacts include Contracting Officer Lisa McKeon and a BLM Project Engineer and Contracting Officer Representative to be identified after award. The contract includes environmental sustainability requirements, quality control plans with daily reporting, accident prevention programs, and submission of As-Constructed Drawings within 21 days of Substantial Completion.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| At05_RFI_Responses_AM01_22Jul_0001.pdf | ||
| Sol_140L0626R0005_Amd_0001.pdf | ||
| 26R0005_SiteVisitSignInSheet_0001.pdf | ||
| 26R0005_ContPages_AM01_22Jul_0001.pdf | ||
| Sol_140L0626R0005.pdf | ||
| At04_BLMCodesandStandards_Jul23.pdf | ||
| At02_CampgroundSchematicDesign_Feb26.pdf | ||
| At03_CampgroundFurnishingExamples_Feb26.pdf | ||
| At12_RFI_Form.docx | DOCX document | |
| At11_PastPerformanceQuestionnaire.docx | DOCX document | |
| At10_Experience_ProjectDataSheet.docx | DOCX document |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Design Build Services
Statement of Work
Little Creek Campground Improvements Salt Lake Field Office
February 2026
US Department of the Interior Bureau of Land Management
Design-Build Statement of Work
Table of Contents
1 Project Introduction
1.1 Scope
1.2 Location
1.3 Background / Description
1.4 Schedule & Milestones
1.5 Information
1.6 Government Furnished Documents
1.7 DBC Submissions Requirements
2 Project Requirements
2.1 General Requirements
2.1.1 Scope of Work and Project Summary Requirements
2.1.2 Definition of Contract Line Items
2.1.3 Progress Payments
2.1.4 Project Meetings
2.1.5 Project Schedule
2.2 Design Requirements
2.2.1 Conceptual Site Design
2.2.2 65% Construction Documents
2.2.3 95% Construction Documents
2.2.4 100% Construction Documents
2.2.5 Complete Stamped and Signed Construction Documents
2.3 Construction Requirements
2.3.1 Environmental and Sustainability Requirements
2.3.2 Schedule of Values
2.3.3 Construction Support
2.3.4 Submittals During Construction
2.3.4.1 Construction Submittals:
2.3.4.2 Construction Submittal Types:
2.3.4.3 Contractor’s Review:
2.3.4.4 General Submittal Procedures:
2.3.4.5 Government’s Review:
2.3.4.6 Submittal List:
2.3.4.7 Use for Construction:
2.3.5 Construction Coordination
Design-Build Statement of Work February 2026
2.3.6 Digital Images
2.3.7 Quality Control
2.3.7.1 General:
2.3.7.2 Quality Control Staff:
2.3.7.3 Testing Laboratory and Equipment:
2.3.7.4 Submittals:
2.3.7.5 Execution:
2.3.7.6 Quality Control Phases:
2.3.7.7 Documentation:
2.3.7.8 Enforcement:
2.3.8 Working Hours Restrictions
2.3.9 Temporary Services
2.3.10 Access
2.3.11 Preservation of Adjacent Features
2.3.12 Utilities
2.3.13 Hauling Restrictions
2.3.14 Accident Prevention
2.3.15 Temporary Controls
2.3.16 Field Engineering
2.3.17 Project Close-out
2.3.18 Substantial Completion and Final Inspection
2.4 Forms
3 Performance Requirements
3.1 Design Imperatives
3.2 Facility Performance
3.3 Elements and Products
Design-Build Statement of Work February 2026
1 Project Introduction Project Title: Little Creek Campground Improvements
1.1 Scope
In accordance with the terms and conditions of the Contract, the Design-Build Contractor (DBC, or “Contractor”) shall perform the work of this Statement of Work (SOW) for the Bureau of Land Management (BLM) as described below.
All Architect-Engineer (A-E) Services required in this SOW shall be performed by licensed Landscape Architects and Engineers registered in the State of Utah.
The schematic design provided by the BLM shall be used as the basis of the design, see Attachment Att-01.
The Contractor shall be responsible for developing an integrated design solution, preparing phased construction documents, and final construction of phase 1 of the project based on available funding.
The design of the Little Creek Campground will require review and coordination with the BLM. The improvements proposed includes but not limited to redesign and construction of 9 campsites, installation of shade pavilions, tent pads, remediation of storm drainage issues, installation of kiosk(s), replacement of group pavilion, installation of picnic tables, and redesign of site layout.
The project scope shall include a full and complete campground design with a phased construction process based on funding available to the BLM. Phase 1 of construction shall include all work around the main entrance parking lot and group site, re-grading/shaping the entrance area to provide for storm water remediation, demolishing and replacing the group site pavilion and re-constructing the group site area. Phase 2 will be constructed at a future time as funding becomes available.
Little Creek Campground Improvements Goals and Project Scope:
1. General Site:
a. Site Clearing: Remove existing vegetation, debris, obstructions, etc. as necessary for construction
b. Grading and drainage: Ensure proper grading and positive drainage for campsites, roads, parking, and common spaces.
i. Existing culverts appear to have insufficient hydraulic and structural capacity. Design needs to analyze existing site drainage and repair/replace culverts where needed
ii. Fill and regrade low area West of Site 7
iii. Install new vegetation along clear area West of Site 7.
c. Pavements
i. Repair all existing gravel surfaces to ensure smooth rideability and positive drainage
ii. Re-design roadway, parking, and camping areas to accommodate design vehicle
d. Install approximately thirty (35) shade trees throughout campground
i. Locations to be discussed during site visit
ii. See technical requirements/ design considerations
e. Provide native perennial grass and forbs where seeding will be necessary
i. Ensure the use of certified weed-free seed
f. Water system:
i. Install water spigot(s) at the group site and spaced around the campground loop. One
(1) spigot to be located adjacent to ABA complaint campsite and must meet ABA standards
ii. Install irrigation system for vegetation in compliance with the Town of Randolph
iii. Water system is owned/maintained by the Town of Randolph, design must meet all requirements of the State of Utah, Division of Drinking Water as well as Town of Randolph
2. Entrance Area
a. Remove and dispose of existing wooden kiosk
Design-Build Statement of Work February 2026
b. Provide one new three (3) panel metal kiosk immediately inside of entrance to campground and one new three (3) panel metal kiosk adjacent to group area. Kiosks to include:
i. Map
ii. Campground rules and QR code for rec.gov reservation and payment
iii. Pack it in-pack it out for trash, shooting closure, and adjacent Little Creek Reservoir interpretive information.
iv. Include message encouraging public land users before entering campground, to inspect and clean motorized and mechanized vehicles of weeds and their seeds
c. Regrade and gravel the entrance area
d. Provide delineation to improve traffic flow such as natural features or concrete parking bumpers
e. Provide improvements to alleviate circulation concerns with RV’s and large trailers occupying the entrance area. Improvements would direct new arriving visitors to the entrance kiosk for campground information.
f. Provide a minimum of six designated parking stalls at the entrance area directly adjacent to the information kiosks. Use natural delineation, concrete bumpers, and/or short rust-brown metal fencing for parking containment
g. Provide native perennial grass and forbs where seeding will be necessary
i. Ensure the use of certified weed-free seed
3. Individual campsites - Nine (9) Total:
a. Redesign nine (9) existing individual campsites
i. Redesign minimum of two (2) campsites to be “pull through”
ii. Redesign minimum of one (1) campsite to meet ABA compliance requirements (BLM recommends site 1, 2, or 4). (Cross slopes of campsite parking of 0.5-1% and longitudinal slope no greater than 3%. tent pads and picnic shelters maximum of 1.5% for positive drainage.
b. Provide new delineation
i. Use natural features where possible
c. Provide the following at each site:
i. Shaded pavilion installed on top of concrete pad
1. Minimum roof area of 200 square feet with dimensions of approximately 14’x14’
2. Minimum concrete pad size shall be 16’x16’ or 256 square feet
3. Relocate existing picnic table under pavilion
4. See Attachment 02 for typical architectural style of pavilion
ii. Fire ring
1. 4’ diameter, concrete – See Attachment 02 for example fire ring
2. Existing fire ring to be salvaged, stockpiled on site, and returned to the
Government
iii. Tent pad
1. Preferred size:16’ x 16’
a. Minimum size: 12’ x 12’
i. Only use if site is unable to accommodate preferred size
2. Tent pad perimeter to be constructed of 8” x 8” treated timber
3. Install weed barrier fabric and fill interior of pad with crushed stone for drainage and stability
iv. Gas stove platform
1. See Attachment 02 for example platform
d. Provide native perennial grass and forbs where seeding will be necessary
i. Ensure the use of certified weed-free seed
4. Group site:
a. Pavilion:
i. Demolish and dispose of existing pavilion and concrete pad, including foundation
ii. Remove and dispose of existing picnic tables
iii. Construct new steel frame pavilion, including concrete foundation and floor
Design-Build Statement of Work February 2026
1. Pavilion to be sized to accommodate 8 picnic tables and up to 50 people
2. Pavilion to include provisions for future lighting/electrical installation
3. See Attachment 02 for typical architectural style of pavilion
iv. Provide 6 picnic tables
1. Table to match existing tables at individual campsite. Table must be at least
92” long, constructed of concrete, have a smooth top. Table finishes must include the BLM logo, tan color, and coated with an acrylic sealer.
2. 6 tables will be installed underneath new pavilion
3. See Attachment 02 for example picnic table
4. Ensure correct number of tables meet ADA/ABA standards
v. Provide 2 concrete service tables
1. Service tables shall be 96” L, 36” D, x 31” T
2. Colors and finish shall match picnic tables
3. Will be installed outside but adjacent to pavilion
4. See Attachment 02 for example service table
vi. Install new fire ring and concrete pad around ring
1. 6’ diameter, concrete – See Attachment 02 for example fire ring
2. Existing fire ring to be stockpiled on site and returned to the Government
3. Concrete pad to be sized adequately to allow proper pedestrian circulation around fire pit.
b. General Site:
i. Repair/ Expand adjacent parking area to accommodate 20 vehicles
1. Use natural features to delineate parking areas
ii. Provide ADA compliant access between parking area, pavilion, and existing vault toilet
1. Move existing vault toilet in parking lot to the east along edge of disturbed area.
iii. Remove and dispose existing briquet-style raised grill
iv. Install 4 raised tent pads
1. Preferred size:16’ x 16’
a. Minimum size: 12’ x 12’
b. Only use if site is unable to accommodate preferred size
2. Tent pad perimeter to be constructed of 8” x 8” treated timber
3. Fill interior of pad with crushed stone for drainage and stability
v. Install new barrier or fence around group site picnic area
1. Replace with natural features or rust-brown metal fence
vi. Provide native perennial grass and forbs where seeding will be necessary
1. Ensure the use of certified weed-free seed
5. Design Standards – All work and products shall be accomplished and produced in accordance with the following standards:
a. BLM Guidelines for a Quality Built Environment
b. ABAAS (Architectural Barriers Act Accessibility Standards)
c. BLM Roads Manual 9113
d. Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects
“FP-24”
e. National Park Service Campground Design Guidelines (May 2021)
i. Design vehicle for horizontal alignment – Truck with fifth wheel trailer (55 ft total)
ii. Minimum 50 ft turning radius
f. 11th Edition of the Manual on Uniform Traffic Control Devices (MUTCD), December 2023
g. American Concrete Institute (ACI) 318-14, “Building Code Requirements for Structural
Concrete”.
h. ACI 301-16, “Specifications for Structural Concrete”.
i. BLM National Sign Handbook https://www.blm.gov/services/national-operations-center/national-sign-program.
6. Technical Requirements/ Design Considerations:
Design-Build Statement of Work February 2026
a. Roadways and Parking:
i. All pavements shall be designed for a 20-year design life without major repair. All pavement systems shall be composed of aggregate, unless otherwise noted.
Pavement systems shall be designed for site subsoil conditions as determined in the geotechnical report and shall include any subsoil drainage required by the design.
ii. All concrete paving, curbs, gutters, and wheel stops shall be in accordance with ACI 318 for design and in accordance with ACI 301 for concrete materials. Concrete paving shall be air entrained for exterior exposure. Minimum compressive strength at 28 days for concrete paving shall not be less than 4000 psi.
iii. Vehicular pavement markings and signage shall be in accordance with the MUTCD.
iv. Handicap parking and associated ramps/walks shall meet the requirements of ADA and
ABA accessibility guidelines.
b. Sidewalks
i. All walks around the group camp site, and elsewhere on the site shall be concrete, minimum 4 inches thick, with a minimum width of 5 feet, unless designated otherwise.
Furnish base course under pedestrian paving if required by the geotechnical report.
ii. Site walkway grades shall not exceed ADA and ABA accessibility requirements.
Provide accessibility ramp at main building entrances in accordance with ADA and ABA accessibility requirements.
c. Concrete Pads:
i. Concrete Pads: Provide concrete pads for all shade structures (Individual campsites
(9) and group camp site (1)). Concrete pads shall be a minimum of 4 inches thick, and shall be sized to meet the loads, dimensions, and requirements of each item.
ii. Provide thickened edge along all concrete pads to help protect and mitigate potential effects of erosion.
iii. All concrete pads shall be in accordance with ACI 318 for design and in accordance with ACI 301 for concrete materials. Concrete paving shall be air entrained for exterior exposure. Minimum compressive strength at 28 days for concrete paving shall not be less than 4000 psi.
d. Structures (Shade Pavilions):
i. Structures to be constructed of metal construction intended for outdoor use in public parks, campgrounds, or similar public areas. All structure components shall be powder coated free of sharp edges, exposed hardware, and similar features that could present a hazard to user.
ii. Structure to be supported by four corner posts and open on all sides. Group shelter may have a western windbreak wall. Structure shall be designed to be anchored to permanent concrete footings.
iii. Professional engineer to design structure for applicable site design loads.
iv. Structures shall be designed and built with materials such that hollow spaces cannot be created or breached by wildlife (for example, avoid hollow wooden walls that woodpeckers can drill into, or small openings that bats can squeeze through).
v. Structures will be designed and built with materials such that surfaces that could support bird nests are not created (such as ledges and rafters).
e. Landscaping:
i. Landscaping Goals: Landscaping shall match existing features.
ii. Planting Restrictions: Plant during one of the following periods. Coordinate planting periods with initial maintenance periods to provide required maintenance from date of Substantial Completion.
1. Spring Planting: April 1 to June 1.
iii. Weather Limitations: Proceed with planting only when existing and forecasted weather conditions permit planting to be performed when beneficial and optimum results may be obtained. Apply products during favorable weather conditions according to manufacturer's written instructions.
iv. Maintenance Service
Design-Build Statement of Work February 2026
1. Initial Maintenance Service: Provide full maintenance by skilled employees of landscape Installer. Begin maintenance immediately after each area is planted and continue until site is accepted by BLM as fundamentally complete
2. Shrubs and Turf: 60 days from date of Substantial Completion.
a. When initial maintenance period has not elapsed before end of planting season, or if turf is not fully established, continue maintenance during next planting season.
v. Suggested Species:
1. Narrowleaf Cottonwood (Populus angustifolia)- Recommend planting closer to riparian area (south side of campground)
2. Quaking aspen (Populus tremuloides)
3. Bigtooth maple (Acer grandidentatum)
4. Gambel oak (Quercus gambelii)
5. Lodgepole pine (Pinus contorta)
6. Ponderosa pine (Pinus ponderosa)
7. Species to not consider: Bristlecone pine (Pinus longaeva (aristata))
8. Other protective measures: space the pine trees at least 20-24 feet away from any fast-growing deciduous trees to prevent them from shading the pines.
f. Site Preparation:
i. A stormwater pollution prevention plan (SWPPP) shall be prepared by the DBC.
ii. DBC shall be responsible for preparing and submitting Notice of Intent (NOI), and
Construction General Permit (CGP) with Utah Pollutant Discharge Elimination System
(UPDES)
iii. Do not begin site-clearing operations until temporary erosion protection and sedimentation control measures are in place. Provide temporary erosion and sedimentation control measures to prevent soil erosion and discharge of soil-bearing water runoff or airborne dust to adjacent properties and walkways, according to the Erosion Protection and Sediment Control Plan, specific to the site, that complies with EPA document No. EPA 832/R-92-005 or requirements of authorities having jurisdiction, whichever is more stringent.
iv. Locate and clearly identify trees, shrubs, and other vegetation to remain.
v. DBC is responsible for coordinating markings of utilities before site clearing or excavation.
vi. DBC Furnished Materials: All imported materials, including borrow and aggregates, shall be furnished from approved locations outside of the BLM site boundaries.
vii. Clearing and Grubbing: Once salvage operations are complete, and tree protection fencing is in place, clear and grub all remaining vegetation to be removed. Remove all stumps a minimum of 2 feet below proposed subgrade and remove roots and debris a minimum of 6 inches below proposed subgrade.
g. Water supply:
i. Provide a closed loop water distribution system which will meet flow requirements for the new site features that use water.
ii. The water distribution system shall be connected to the municipal water supply.
1. Water distribution system/irrigation system must meet all requirements of the State of Utah, Division of Drinking Water as well as Town of Randolph including any necessary design reviews and construction permits necessary.
iii. Burial depth and cover shall be adequate to prevent freezing of water distribution system piping.
iv. Provide backflow prevention in accordance with AWWA Manual M14-15, and as required by state and local regulatory agencies.
v. All lines shall be leak tested prior to acceptance.
h. Storm Drainage:
i. As needed, provide grading, drainage pipe and appurtenances to facilitate positive drainage away from the campsites and roadways. As needed, provide structures which channel drainage away from roads, sidewalks, and parking lots. New storm drainage features shall connect to and complement existing storm drainage features.
Design-Build Statement of Work February 2026
ii. Overland flow values and associated design parameters such as rainfall data, storm frequency, storm water quality standards and hydrograph computation methods shall be computed in accordance with local regulatory requirements.
iii. Storm drainage pipe shall have a minimum inside diameter of 12 inches.
iv. Pipe material selection and bedding/backfill requirements shall ensure the load carrying capacity of the pipe is not exceeded.
v. Drainage piping may be either reinforced concrete pipe conforming to ASTM C76 or corrugated aluminum or galvanized steel piping. The inside of the corrugated pipe should be lined for improved hydraulic performance. Both the aluminum and steel pipe shall have an appropriate coating (i.e. bituminous, zinc, polymer, etc.) based on the corrosiveness of the soil and drainage the pipe will be exposed to (i.e. highly acidic or highly alkaline soils, etc.).
i. Fencing:
i. Fences will be designed to meet BLM standards for wildlife movement (H-1741-1
Fencing).
The DBC remains fully responsible for determining if the standards or provisions cited have been revised or updated. Any such conflicts between the specifications and the identified standard or provisions shall be brought to the attention of the Government requesting direction
1.2 Location
This project is located at Little Creek Campground, located on Little Creek Road approximately 3 miles West of Randolph, Utah. (LAT/LON: 41.677694°N, 111.226138°W)
1.3 Background / Description
Little Creek Campground is located three miles West of the Town of Randolph adjacent to Little Creek Reservoir. The campground was constructed in 1995 and consists of a group site that includes 1 large pavilion and 4 picnic tables. Additionally, there are 9 individual campsites. Each campsite has 1 picnic table, 1 fire ring, and 1 parking stall. Potable water is available (seasonally) and is connected to the Town of Randolph’s culinary water systems. The site also includes 2 single-vault pit toilet restrooms. The campground is roughly 5.5 acres and enclosed by a perimeter fence.
Visitor feedback and monitoring at the campground indicates the location receives heavy sun exposure and has little to no shade, making it a less desirable destination during peak visitation in the summer. The campground also has limited capacity for larger RV’s and fifth wheel trailers with insufficient pull-through parking to accommodate these increasingly popular rigs. Additionally, the existing group site pavilion has increased maintenance and cleaning needs due to nesting swallows under the pavilion canopy. Also, the existing group site parking area has limited capacity and overflows into the entrance area as it has little to no delineation.
1.4 Schedule & Milestones
The work shall be completed in accordance with the following schedule:
Conference Call:
Prior to the Kickoff Meeting and Site Visit, the DBC shall initiate and conduct a conference call with the Government. The purpose of this call is to preview the project, interview the client on overall expectations for the project, review Government-provided materials, and generally discuss plans for the design effort.
The meeting must be attended by the key members of the DBC team, including a licensed landscape architect. The DBC shall determine which other team members shall be required to attend the site visit and will have the opportunity to ask questions about the project to be better prepared for the site visit.
Within (3) three calendar days of the conference call, the DBC shall provide detailed meeting notes outlining the discussion.
Design-Build Statement of Work February 2026
Kickoff Meeting and Site Visit (1-10 calendar days into performance):
Key members of the DBC team shall attend a one-day meeting at the Little Creek Campground. Within
(3) three calendar days of the kickoff meeting and site visit, the DBC shall provide detailed meeting notes.
Meeting and site visit will include the following:
• Review and discussion of project scope, deliverables, and schedule.
• Review of Government-provided information.
• Review and discuss BLM project goals and objectives
• Site familiarization tour.
Conceptual Site Design The required deliverables to be included with the Conceptual Site Design documents are outlined in the Design Requirements section of this SOW. The Conceptual Site Design Documents are to be submitted 45 calendar days after award. BLM review comments, selected concepts and options feedback shall be completed and returned to the DBC no later than 15 calendar days after submission.
65% Construction Documents The required deliverables to be included with the 65% Construction Documents are outlined in the Design Requirements section of this SOW. The 65% Construction Documents are to be submitted no later than 30 calendar days after acceptance of the Conceptual Site Design. BLM review comments on the 65% Construction Documents shall be completed and returned to the DBC no later than 15 calendar days after submission.
95% Construction Documents The required deliverables to be included with the 95% Construction Documents are outlined in the Design Requirements section of this SOW. The 95% Construction Documents are to be submitted no later than 30 calendar days after acceptance of the 65% Construction Documents. BLM review comments on the 95% Construction Documents shall be completed and returned to the DBC no later than 15 calendar days after submission.
100% Construction Documents (CD The required deliverables to be included with the 100% Construction Documents are outlined in the Design Requirements section of this SOW. The 100% Construction Documents are to be submitted no later than 30 calendar days after acceptance of the 95% Construction Documents. BLM review comments on the 100% Construction Documents shall be completed and returned to the DBC no later than 15 calendar days after submission.
Complete Stamped and Signed Construction Documents (CD) The required deliverables to be included with the Complete Stamped and Signed Construction Documents are outlined in the Design Requirements section of this SOW. The Complete Stamped and Signed Construction Documents are to be submitted no later than 15 calendar days after the acceptance of the 100% CD submittal. BLM review of the Complete Stamped and Signed Construction Documents shall be completed and returned to the DBC no later than 10 calendar days after submission.
Construction Construction shall not begin until the Government has issued the DB Construction Start Work Notice.
As-Constructed Drawings As-Constructed Drawings shall be submitted to BLM no later than 21 days after Substantial Completion.
1.5 Information
The BLM Points of Contact for this project are as follows:
Contracting Officer (CO) Lisa McKeon lisa_mckeon@ios.doi.gov
Design-Build Statement of Work
850-890-6395
Contract Specialist (CS)
TBD
BLM Project Engineer Contact information to be provided after award
Contracting Officer Representative (COR) Contact information to be provided after award
1.6 Government Furnished Documents
The following data and materials will be provided to the DBC and are included in Section 5 of this SOW (additional items not listed may be available, and can be provided upon request by the DBC in coordination with
BLM):
● Little Creek Campground Schematic Design
● Campground Furnishing Examples
● BLM Codes and Standards
1.7 DBC Submissions Requirements
All DBC Submissions should be submitted electronically. Electronic copies shall be provided in both the original software file format (AutoCAD/Revit, MS Word, etc.) and PDF format.
All drawing sheets must be consecutively numbers (1 of xx, 2 of xx, etc.) through the full set, in addition to the discipline numbering (e.g. M1, S1, etc.), and electronic Drawing File Names must begin with overall sheet number.
Drawings in PDF format shall consist of the entire set of design documents, be in consecutive order and have, at a minimum, bookmarks to the beginning of each discipline (Cover, Civil, Structural, Architectural, Mechanical, Electrical, Plumbing, etc.).
Specifications in PDF format shall be in a single file and organized with separate bookmarks for each of the MasterFormat divisions and each specification section. Additional required formatting is as follows:
Drawings:
Drawings shall be submitted in digital format only.
Sheet Size: ANSI B (11” x 17”).
Digital File Format: AutoCAD 2024 or Revit 2024 and Adobe PDF. If BIM is used, the electronic BIM file(s) must also be provided to the BLM.
Organization: National CAD Standard.
PDF Document: Set to open with Bookmark tab open to the left, document to be bookmarked to open to Cover, and then at minimum to the first page of each design discipline thereafter. PDF document shall also be set to open with Magnification “Fit Page” and Page Layout “Single Page.”
Specifications:
Specifications shall be submitted in digital format only.
Sheet Size: 8 ½” x 11”.
Digital File Format: MS Word and Adobe PDF.
Organization: MasterFormat with BLM header and footer.
PDF Document: Set to open with Bookmark tab open to the left, document to be bookmarked to open to Cover, Table of Contents and then the first page of each section
Design-Build Statement of Work February 2026 thereafter. PDF document shall also be set to open with Magnification “Fit Page” and Page Layout “Single Page Continuous.”
Design Calculations:
Design Calculations shall be submitted in digital format only.
Sheet Size: 8 ½” x 11”.
Digital File Format: Adobe PDF.
Distribution:
All submittals shall be via electronic copy to the COR identified in the contacts section above.
File Transfer:
The DBC is responsible for establishing a file sharing site for communication of large documents and files.
2 Project Requirements
2.1 General Requirements
2.1.1 Scope of Work and Project Summary Requirements
The project will consist of the design and construction of various improvements to the Little Creek Campground.
The work will include, but may not be limited to, the following:
• Evaluate the project scope, concept drawings and performance specifications.
• Review site data.
• Upon award, provide design schedule of work, with milestone submittal dates indicated. Coordinate proposed milestone dates with the BLM.
• Review and survey existing site, buildings, features, and utilities.
• Design site, site utilities, structures, and roadway systems.
• Submit design submittals for review and approval, as required per milestone dates outlined in the design schedule.
• Provide schedule of construction work. Coordinate proposed milestone dates with BLM and plans for construction work around active and non-active operations.
• Secure work area and provide for continued access to the facility as technically feasible.
• Construct phase 1 of project.
• Create and provide Operations and Maintenance (O&M) manuals.
• Provide As-Constructed documents.
2.1.2 Definition of Contract Line Items
The intent of this section is to explain, in general, what is included in each contract line item, limits or cut-off points where one item ends and another begins. If no item exists for a portion of the work, include the costs in a related line item.
See SF1442 Section B
2.1.3 Progress Payments
Progress payments shall be made to the DBC generally as follows and as required by the solicitation:
Design Phase:
Progress payments during the design phase of the work will be based on submission, review, and acceptance of design deliverables as outlined in this SOW.
Construction Phase 1:
Design-Build Statement of Work February 2026
Progress payments during construction will be based on the percentage of work completed on items listed on the approved schedule of values. Actual construction completed and in place will form the basis for payment. Verification of the percentage of completion shall be initiated by the Contractor under the direction of a representative of the Government, unless the Government waives this requirement in a specific instance. The Contractor shall make the computations for payment based on the Government’s verification of work completed and in place for any periods for which progress payments are requested.
The Contractor shall furnish to the Government originals of all field notes and all other records relating to the basis for payment, who shall use them as necessary to determine the final amount of progress payments. The Contractor shall retain copies of all such material furnished to the Government.
2.1.4 Project Meetings
Project meetings shall be conducted as follows:
Design Phase Progress Meetings:
The DBC shall participate in the design milestone meetings at each project milestone as outlined in section 2.2. Meeting(s) will be held virtual (Microsoft Teams) and attended by the Government and other project team members during the project Design Phase. Two (2) meetings will be held at each milestone with the following agenda items:
• Design Submittal Briefing To be held at the conclusion of current design submittal DBC will present submittal items, status of design documents, and any of interest items Focus on previous review comments and how items were addressed Schedule update o Design Comment Review Meeting To be held after submittal of government design review comments DBC will address action items for design review comments and any clarifying elements the Government or DBC needs to proceed Schedule update Other business related to the project.
Preconstruction Meeting:
After the Complete Stamped and Signed Construction Documents are approved and prior to the start of construction, the Contracting Officer (CO) will arrange an on-site Preconstruction meeting with the DBC.
The following Part 2.0 Project Requirements Deliverables shall be submitted a minimum of one week prior to the Preconstruction Meeting:
• Letter designating the DBC Project Superintendent.
• Project Schedule with construction portion fully developed.
• Schedule of Values.
• Accident Prevention Program.
• List of subcontractors for the project (must be the same as in the DBC’s proposal).
• Written statements from subcontractors certifying compliance with applicable labor standard clauses.
• Evidence of liability insurance coverage and workmen’s compensation for the Contractor and all subcontractors.
• Quality Control Plan.
• Stormwater Pollution Prevention Plan Submittal process.
• List of required permits.
The meeting agenda will include the following as a minimum:
• Correspondence procedures.
• Jobsite safety.
• Roles and responsibilities.
• Lines of Authority.
• Schedule of Values.
• Progress payments.
Design-Build Statement of Work February 2026
• Submittal process.
• Resolution to any comments provided by the BLM on the Part 2.0 Project Requirements deliverables.
• Construction schedule (provide an electronic copy in software it was created in).
• Labor standards.
• Payroll reports.
• Modifications.
• Accident reporting.
• BLM Rules and Regulations.
• Medical emergency processes, availability, emergency numbers, and contacts.
• BLM permits, burning construction waste, rules of the road, alcohol use, housekeeping, firearms, pets, natural and cultural resource concerns.
• Bridge, access road and site constraints.
• Visitation and public relations.
• Environmental and sustainability requirements for the Project.
• Saturdays, Sundays, holidays and night work.
• Traffic control.
Construction Phase Progress Meetings:
The DBC shall participate in weekly virtual (Microsoft Teams) conference calls with the Government and other project team members during the Construction Phase to update them on the following agenda items:
• Approval of minutes of previous meetings.
• Submittal status.
• Review of off-site fabrication and delivery (as applicable).
• Requests for Information (RFIs) and issues.
• Modifications.
• Work in progress and work projected over the next six (6) weeks.
• Schedule update (provide updated Critical Path Method schedule every two months).
• Status of As-Constructed Drawings and O&M Manuals.
• Other business related to the project.
Meeting Participation:
Participation at scheduled meetings on the part of this DBC shall include the design disciplines and consultants along with subcontractors as appropriate to the project milestones and current issues.
Participants shall be responsible professionals with direct knowledge of the work components.
The DBC shall take the lead in the coordination and facilitation of all meetings and ensure the attendance of the necessary team members. DBC shall provide meeting minutes and written responses to review comments within one week of the meeting conclusion or receipt of comments.
2.1.5 Project Schedule
The Project Schedule shall be managed by the DBC as follows:
General:
The Contractor shall furnish the project schedule to the Government and provide digital copies after award and at the Kickoff Meeting. The Schedule shall include a detailed design phase with design deliverable submission dates and review periods, as well as a summary construction schedule, with important milestones included.
The Contractor shall fully develop the construction portion of the schedule and submit it to the Government before the Preconstruction Meeting or any construction begins. The project schedule shall
Design-Build Statement of Work February 2026 be updated every month throughout the entire contract period until project substantial completion. The status date of each schedule update shall be 10 days before the progress payment request date.
Purpose:
The purpose of the project schedule is to ensure adequate planning, coordination, scheduling, and reporting during execution of design and construction activities of the DBC. The project schedule will assist the DBC and the Government in monitoring the progress of the work, evaluating proposed changes, and processing the DBC’s monthly progress payment requests.
Software:
Scheduling software shall be the latest version of Microsoft Project or approved equal.
Schedule Development:
The project schedule shall cover the entire contract period. The late finish date of the project schedule shall be the same date as the established completion date of the contract.
The DBC shall use the Critical Path Method (CPM) with limited use of lead or lag durations between scheduled activities. The DBC’s project schedule shall consist of procurement activities (including permits, mobilization, submittals, and the fabrication and delivery of key and long-lead procurement items) and construction activities.
In developing the project schedule, the DBC shall be responsible for ensuring that subcontractor work at all tiers, as well as its own work, is included in the project schedule.
Project Schedule Updates
Monthly Updates:
The monthly updating of the project schedule shall be an integral part and basic element of the estimate upon which progress payments shall be made under this contract. If, in the judgement of the Government, the DBC fails or refuses to provide a schedule of values and a complete schedule update or revision as specified hereinafter, the DBC shall be deemed to have not provided the required information upon which the progress payment may be made and shall be subject to retainage of a portion of the payment.
Progress Report:
The report shall include a brief description of the actual progress made during the update period;
actual and potential delaying activities; any impediments to progress; issues related to inclement weather; progress toward established milestones and project float. The report shall include a brief description of the work anticipated to be performed in the next month. Any minor revisions to the schedule should be identified so they can be evaluated and accepted or rejected.
As the project progresses, indicate Actual Completion percentage for each activity. If the schedule update shows a late finish date after the contract completion date, at a minimum, include the following in the progress report submission:
• Any known delays.
• Actions that will be taken to get back on schedule.
• Pending modifications.
• Impediments or constraints affecting progress.
Progress Payments:
The monthly updating of the currently accepted construction schedule shall be an integral part of the process upon which progress payments will be made under this contract. If the Contractor fails to provide schedule updates or revisions, then a portion of the monthly payment may be retained until such corrections have been made.
Time Impact Analysis for Contract Modifications, Changes, Delays, and Contractor Requests Requirements:
Design-Build Statement of Work February 2026
When contract modifications or changes are initiated, delays are experienced, or the DBC desires to revise the project schedule, the DBC shall submit to the Government a written time impact analysis illustrating the influence of each modification, change, delay, or DBC request on the contract time.
Time Extensions:
Activity delays shall not automatically mean that an extension of the contract time is warranted or due the DBC. It is possible that a modification, change, or delay will not affect existing critical activities or cause non-critical activities to become critical. Time extensions will be granted in accordance with the terms of the contract.
2.2 Design Requirements
The campground design effort will comply with environmental regulations as well as requirements of the local reviewers. Design will also include utilities such as water distribution, and site drainage system. The contractor shall review existing utility routes and research tie-in locations. Possible capacity issues shall be brought to the BLM’s attention.
The following requirements will be considered supplementary to the basic professional requirements to comply with applicable regulations, codes, and standards. The requirements serve to identify specific items the Government wants accomplished in the design effort.
2.2.1 Conceptual Site Design
The intent of the conceptual design phase is to present the initial ideas and data to the Government providing various options for site layouts and manufactured materials. The conceptual site design shall include at least three alternative site plans. At a minimum, these alternatives should incorporate different site access points, campsite layouts, pavilion types, and any other items the DBC would like more information on the preferences from the Government.
Include the following:
• Existing conditions and Topographical Site Survey documents, including:
o Control points.
o Existing physical features.
o Field notes and observations.
o Site photos.
o Utilities, above and below ground.
o Topographic contours.
• Schematic Site Design o Including ADA accessible routes and campsites o Proposed locations and orientation for all major items include but not limited to: tent pads, fire rings, picnic tables, pavilions, parking, RV pads o Landscaping and irrigation site plan
• Typical drawings for proposed tent pads, pavilions, picnic tables, gas stove-stand, fences, and any other furnished items
• Preliminary stormwater and drainage plans
• Preliminary water distribution plans
• Geotechnical report including soils and seismic analysis and recommendations for excavations, foundations, roadway typical sections, and import fill, et al, to assess the existing soils conditions for the project.
• Required peak water demands, and storm water flow calculations.
Design-Build Statement of Work February 2026
2.2.2 65% Construction Documents The 65% Construction Documents phase shall consist of the continued development and expansion of the Conceptual Site Design based on the preferred options chosen from the Government during the Conceptual Site Design Review. The DBC is responsible for providing, in writing, responses to the BLM’s review comments of the Conceptual Site Design submission.
The following items shall be provided / completed by the DBC in the submission of the 65% Construction Document package (in addition to the items outlined in the Section 2.2.1 Conceptual Site Design):
• Construction Drawing Set to include:
o Overall phased site development plans.
o Demolition plans o Drainage and stormwater management plans.
o Erosion and sediment control plans.
o Landscaping and irrigation site plans.
o Grading plans.
o Water supply and distribution plans o Additional utilities and infrastructure plans.
• Technical Specification Package organized in accordance with industry standards (MasterFormat).
2.2.3 95% Construction Documents The 95% Construction Documents phase shall consist of the continued development and expansion of 65% Construction Documents. The DBC is responsible for providing, in writing, responses to the BLM’s review comments of the 65% Construction Documents.
The following items shall be provided / completed by the DBC in the submission of the 95% Construction Document package (in addition to the items outlined in the Section 2.2.2 65% Construction Documents):
o Demolition plans o Drainage and stormwater management plans.
o Erosion and sediment control plans.
o Landscaping and irrigation site plans.
o Grading plans.
o Water supply and distribution plans o Additional utilities and infrastructure plans.
• Construction schedule
2.2.4 100% Construction Documents The 100% Construction Documents phase shall consist of the continued development and expansion of 95% Construction Documents. The DBC is responsible for providing, in writing, responses to the BLM’s review comments of the 95% Construction Documents.
The following items shall be provided / completed by the DBC in the submission of the 100% Construction Document package (in addition to the items outlined in the Section 2.2.3 95% Construction Documents):
o Demolition plans o Drainage and stormwater management plans.
o Erosion and sediment control plans.
o Landscaping and irrigation site plans.
o Grading plans.
Design-Build Statement of Work February 2026 o Water supply and distribution plans o Additional utilities and infrastructure plans.
• Construction schedule
2.2.5 Complete Stamped and Signed Construction Documents
Upon approval of the 100% Construction Documents by BLM the Complete Stamped and Signed Construction Documents submission shall be considered the final document package, which shall be approved, stamped, and signed by the official Design Professional of Record. Professional landscape architects and engineers stamping the record drawings shall be licensed in the State of Utah.
The following documents shall be included in the Complete Stamped and Signed Construction Documents, and shall be used for Construction, BLM archiving, and general use:
• Construction Drawings
• Divisions 2 through 49 Construction Specifications.
o All Structural Tests and Special Inspections (as applicable) should be included in the specifications.
• Design Calculations.
• Written responses to the 100% Construction Documents review comments.
All items in the Complete Stamped and Signed Construction Documents package shall be submitted digitally in both PDF and their respective native file types (AutoCAD, Revit, MS-Word, MS-Excel, etc.).
2.3 Construction Requirements
2.3.1 Environmental and Sustainability Requirements
Minimize Construction Impacts:
The following mitigation measures shall be implemented to minimize the impacts of construction activities:
• Site Disturbance: Minimize the construction limits of the project to reduce the project’s impact on the site.
• Toxic Chemicals: Avoid materials that can leach toxic chemicals into the ground water. Do not allow toxic chemicals to enter sewers or storm drains or contaminate land or any body of water.
• Soil Erosion: Protect against erosion and topsoil depletion in accordance with a site-specific Stormwater Pollution Prevention Plan after obtaining a UPDES Construction Storm Water Permit.
Before starting construction, the Contractor shall implement the approved SWPPP.
• Noise: Minimize noise generation during construction. Operate power equipment in accordance with local noise restrictions.
• Exotic Vegetation and Noxious Weeds: Prevent the introduction and minimize the spread of exotic vegetation and noxious weeds. Incorporate the following procedures:
o Any fill, rock, or additional topsoil needed shall be obtained from a Government approved source.
o All areas disturbed by construction shall be re-vegetated using approved native seed and/or plants.
o Begin project demolition, construction, and maintenance activities in weed-free areas before operating in weed-infested areas o Clean equipment (remove mud, dirt, and plant parts) before entering campground for demolition, construction, and maintenance activities. Before leaving the campground, clean all equipment if operating in areas infested with weeds. Workers need to inspect, remove, and properly dispose of weed seed and plant parts found on their clothing and equipment. Proper disposal means bagging the seeds and plant parts and incinerating them.
Design-Build Statement of Work February 2026 o Ensure the use of certified weed-free seed when seeding native perennial grass and forbs.
o Migratory Birds: If construction occurs in the Spring, BLM Biologist will complete a survey for nesting birds 7-10 days prior to construction/installation activities. A report of the survey results will be provided to the DBC at the completion of the survey.
If no migratory birds are found nesting in the project area, then project activities may proceed as planned.
• If migratory birds are present and nesting in the project area, BLM Biologist may request an avoidance buffer or may be on site for observation during work depending on species. Active raptor nests shall be avoided by the spatial and temporal buffers specified in the U.S. Fish and Wildlife Utah Field Office’s Guidelines for Raptor Protection from Human and Land Use Disturbances (Romin & Muck, 2002).
• Sensitive Species: Existing structures will be surveyed for bat use prior to demolition/removal. If bats are using structures, then exclusion of the bats (if the site is not being used as a maternity colony or winter roost) from the structure should be performed by a qualified wildlife biologist prior to demolition/removal.
If the site is being used as a maternity colony or winter roost, then demolition/removal will be delayed until bats are no longer using the structure.
o New developments/facilities will not be located within 100 meters (330 feet) of active pygmy rabbit or kit fox burrows. Surveys will be performed in suitable habitat no more than 30 days prior to installation of new facilities.
• General Wildlife:
o All excavated steep-walled holes or trenches more than 2-feet deep will be covered at the close of each working day. If trenches cannot be closed, one or more escape ramps constructed of earthen fill or wooden planks should be installed. Before holes or trenches are filled, they will be thoroughly inspected for trapped animals.
o All construction pipes, culverts, or similar structures accessible to wildlife and stored at the construction site for one or more nights will be inspected for wildlife before the pipe is subsequently buried, capped, or otherwise used or moved in any way. Any wildlife found inside the structure will be allowed to leave before the structure is buried, capped, or moved.
Air and Water Pollution Control:
Air quality impacts are expected to be temporary and localized. To minimize these impacts, the following actions shall be taken:
• To reduce tailpipe emissions, construction equipment shall not be left idling any longer than is necessary for safety and mechanical reasons.
• To reduce construction dust, water shall be applied to problem areas. Equipment shall be limited to the fenced project area to minimize soil disturbance and dust generation.
• Take all necessary reasonable measures to reduce air and water pollution by any material or…