This is an asphalt adjustment pricing spreadsheet for Kentucky state and local contract opportunities, specifically related to Bridge Maintenance & Repair for State Projects D 1-8 & 10-11 under Master Agreements effective March 1, 2026. The spreadsheet is designed to track monthly asphalt deliveries and calculate price adjustments based on fluctuating asphalt costs. The document provides a template for recording delivery order information, including the month placed, quantity of tons, asphalt content percentages, and threshold determinations across all twelve months of the contract year. The spreadsheet is configured to calculate total asphalt adjustment quantities automatically using the specified formula.

The asphalt adjustment is calculated using the formula: Asphalt Adjustment Quantity = (Q x 5.6)/100 x (PC - PL), where Q represents tons of material or mixture used, PL represents the KAPI (Kentucky Asphalt Price Index) for the month the contract was bid, and PC represents the KAPI for the month of pickup or delivery. The adjustment percentage is determined by comparing the current month's KAPI price (PC) against the base month KAPI price from February 2026 (PL), with a threshold determination included to trigger adjustments only when specified conditions are met. The spreadsheet references the Kentucky Transportation Cabinet's Fuel and Asphalt Adjustments page for obtaining current KAPI pricing data, enabling contractors to accurately calculate cost adjustments throughout the contract period.

View the file

Other files

File Type Posted
Bid Tab Sheet (STATE) (2).xlsx XLSX spreadsheet
Final_RFB_605_2700000074_1_SO_FORM.PDF PDF
Drawings and Notes -2026.pdf PDF
District Map.pdf PDF
How to Submit an Online Response - March 2023.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

In Place

For Master Agreements effective March 1, 2026Delivery Order Number
Type Delivery Order Here
Month PlacedItemTons (Q)Asphalt ContentPL
(Feb 2026)PC (KAPI)Threshold Met
(1=Yes, 0=No)AdjustmentpercentDate
5.6January
5.6February
5.6March
5.6April
5.6May
5.6June
5.6July
5.6August
5.6September
5.6October
5.6November
5.6December
Total Asphalt Adjustment Quantity$0.00

To get the PC (KAPI), click HERE

Contract Formula for Calculating Asphalt Adjustment:

Asphalt Adjustment Quantity = (Q x 5.6)/100 x (PC - PL)

Where:
Q = Tons of material or mixture used
PL = KAPI for the month that the contract is bid
PC = KAPI for the month of pick up or delivery

https://transportation.ky.gov/Construction/Pages/Fuel-and-Asphalt-Adjustments.aspx