ASHE19-1057 A01 CCEB.xls
XLS spreadsheet 182 KB Posted
- Solicitation number
- FA568220R0024
About this file
This is a construction cost estimate breakdown and federal contract opportunity notice for enclosing and renovating a tactical vehicle boat overhang facility at Aviano Air Base in Italy. The cost estimate breakdown provides line item details for demolition, architectural, structural, civil, mechanical, electrical, fire prevention and addendum work. It includes estimates for materials, labor, and direct costs. The federal contract opportunity is a pre-solicitation notice for the project work tentatively scheduled for solicitation issuance in August 2020. Offerors must have an active System for Award Management registration and adequate Statement of Capabilities certification in construction category OG01 covering their proposed amount. The project scope is to enclose and renovate the tactical vehicle boat overhang facility for a lump sum price between $250,000 and $500,000.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| ASHE191057 ADD02 CCEB.xls | XLS spreadsheet | |
| ASHE191057 ADD02 SOW.pdf | ||
| Solicitation Amendment FA568220R00240001 SF 30.pdf | ||
| Solicitation - FA568220R0024.pdf | ||
| AVIANO MASTERSPECS 2020.pdf | ||
| ASHE 19-1057 Safety Plan.pdf | ||
| ASHE19-1057 ADDENDUM 01.pdf | ||
| ASHE19-1057 ADDENDUM 01Attch 01.pdf | ||
| ASHE 19-1057 Tech Spec Eng.pdf | ||
| ASHE 19-1057 Drawings.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ASHE 19-1057
| CONSTRUCTION COST ESTIMATE BREAKDOWN | |||||||||||||
| CONTRACTOR | ADDRESS | ||||||||||||
| CONTRACT FOR (Work to be performed) | PROPOSED TOTAL CONTRACT PRICE | ||||||||||||
| ENCLOSE RENOVATE TACTICAL VEHICLE BOAT OVERHANG, B.73003 A#01 | |||||||||||||
| PURCHASE REQUEST NUMBER | PROJECT NUMBER | WORK LOCATION | |||||||||||
| ASHE 19-1057 | AREA F, AVIANO AIR BASE, ITALY | ||||||||||||
| MATERIAL COSTS | LABOR COSTS | ||||||||||||
| LINE NO. | ITEM | UNIT OF MEASURE | QUANTITY | UNIT | TOTAL | MANHOURS MANDAYS | AVERAGE RATE | TOTAL | OTHER DIRECT COSTS | LINE TOTAL | |||
| (1) | (2) | (3) | (4) | (5) | (6) | (7) | (8) | (9) | (10) | ||||
| PART I - DEMOLITIONS, EXCAVATIONS AND REMOVALS / Parte I - Demolizioni, Scavi e Rimozioni | |||||||||||||
| Ia Architectural Demolition - Ia Demolizioni Architettoniche | |||||||||||||
| 1 | REMOVAL OF METAL DOWNSPOUTS | ||||||||||||
| Rimozione di pluviali metallici | IT. No. Art. n. | 1 | EA/NO | 10.00 | |||||||||
| 2 | REMOVAL OF METAL GUTTER | ||||||||||||
| Rimozione di gronda metallica | IT. No. Art. n. | 2 | LM/ML | 92.00 | |||||||||
| 3 | REMOVAL OF STEEL BOLLARDS | ||||||||||||
| Rimozione di bitte in acciaio | IT. No. Art. n. | 3 | EA/NO | 5.00 | |||||||||
| 4 | REMOVAL OF ANTI-PIGEON NET | ||||||||||||
| Rimozione di rete anti piccioni | IT. No. Art. n. | 4 | SM/MQ | 900.00 | |||||||||
| Total Architectural - Totale Architettura | |||||||||||||
| Ib Structural Demolition - Ib Demolizioni Strutturali | |||||||||||||
| Not Applicable / Non Applicabile | |||||||||||||
| Ic Civil Demolition - Ic Demolizioni Civili | |||||||||||||
| 5 | PARTIAL DEMOLITION OF REINFORCED CNC PAVEMENT | ||||||||||||
| Demolizione parziale di pavimentazione in cls armato | IT. No. Art. n. | 5 | SM/MQ | 22.00 | |||||||||
| 6 | TRENCH EXCAVATION ON BITUMINOUS CONCRETE PAVEMENT - COLUMN FOUNDATIONS | ||||||||||||
| Scavo in trincea su pavimentazione in conglomerato bituminoso - Fondazioni pilastri | IT. No. Art. n. | 6a | CU.M/MC | 68.00 | |||||||||
| 7 | TRENCH EXCAVATION ON BITUMINOUS CONCRETE PAVEMENT - PIPELINES | ||||||||||||
| Scavo in trincea su pavimentazione in conglomerato bituminoso - TUBAZIONI | IT. No. Art. n. | 6b | CU.M/MC | 90.00 | |||||||||
| 8 | DEMOLITION OF BITUMINOUS CONCRETE PAVEMENT | ||||||||||||
| Demolizone di pavimentazione in conglomerato bituminoso | IT. No. Art. n. | 7 | CU.M/MC | 16.00 | |||||||||
| 9 | MILLING OF EXISTING BITUMINOUS CONCRETE WEARING COURSE | ||||||||||||
| Scarifica dello strato di usura in conglomerato bituminoso | IT. No. Art. n. | 8 | SM/MQ | 865.00 | |||||||||
| Total Civil - Totale Civile | |||||||||||||
| Id Mechanical Demolitions - Id Demolizioni Meccaniche | |||||||||||||
| Not Applicable / Non Applicabile | |||||||||||||
| Ie Electrical Demolitions - Ie Demolizioni Elettriche | |||||||||||||
| 10 | REMOVE LIGHTING SYSTEM | ||||||||||||
| Rimozione Impianto Illuminazione | IT. No. Art. n. | 9 | LS/AC | 0.00 | |||||||||
| 11 | REMOVE REINSTALLATION OF LPS DOWN CONDUCTORS | ||||||||||||
| Rimozione e rimontaggio calatre LPS | IT. No. Art. n. | 10 | LS/AC | 0.00 | |||||||||
| Total Electrical - Totale Elettrico | |||||||||||||
| TOTAL PART I / Totale Parte I | |||||||||||||
| PART II - ARCHITECTURAL, STRUCTURAL AND CIVIL WORK / Parte II - Lavori Architettonici, Strutturali e Civili | |||||||||||||
| IIa Architectural - IIa Architettonico | |||||||||||||
| 12 | SANDWICH PANEL ENCLOSURE Rivestimento in pannelli sandwich | IT. No. Art. n. | 1 | SM/MQ | 470.00 | ||||||||
| 13 | MOTORIZED FOLDING- UP DOOR, D1 TYPE | ||||||||||||
| Portone motorizzato a impaccettamento, tipo D1 | IT. No. Art. n. | 2 | EA/NO | 17.00 | |||||||||
| 14 | EXTERIOR STEEL DOOR, 90x210cm, D2 Type | ||||||||||||
| Porta in acciaio per esterni, 90x210cm, tipo D2 | IT. No. Art. n. | 3 | EA/NO | 3.00 | |||||||||
| 15 | PREFINISHED GALVANIZED STEEL LOUVERS | ||||||||||||
| Griglie in acciaio zincato preverniciato | IT. No. Art. n. | 4 | SM/MQ | 17.20 | |||||||||
| 16 | PREFINISHED GALVANIZED STEEL FLASHING | ||||||||||||
| Scossaline in acciaio zincato preverniciato | IT. No. Art. n. | 5 | KG | 236.00 | |||||||||
| 17 | PREFINISHED GALVANIZED STEEL DOWNSPOUT | ||||||||||||
| Pluviali in acciaio zincato preverniciato | IT. No. Art. n. | 6 | LM/ML | 53.00 | |||||||||
| 18 | PREFINISHED GALVANIZED STEEL GUTTER | ||||||||||||
| Gronda in acciaio zincato preverniciato | IT. No. Art. n. | 7 | LM/ML | 92.00 | |||||||||
| Total Architectural - Totale Architettura | |||||||||||||
| IIb Structural - IIb Strutturale | |||||||||||||
| 19 | B450C STEEL BARS DRILLING | ||||||||||||
| Inghisaggio barre in acciaio tipo B450C | IT. No. Art. n. | 8a | LM/ML | 126.00 | |||||||||
| 20 | 10cm THICK LEAN CONCRETE BASE | ||||||||||||
| Sottofondo in calcestruzzo magro, Sp=10cm | IT. No. Art. n. | 8b | CU.M/MC | 2.00 | |||||||||
| 21 | FORMWORKS | ||||||||||||
| Casseforme | IT. No. Art. n. | 8c | SM/MQ | 73.00 | |||||||||
| 22 | B450 STEEL REINFORCEMENT | ||||||||||||
| Armatura in acciaio tipo B450C | IT. No. Art. n. | 8d | KG | 1,600.00 | |||||||||
| 23 | C30/37 CONCRETE | ||||||||||||
| Calcestruzzo classe C30/37 | IT. No. Art. n. | 8e | CU.M/MC | 20.00 | |||||||||
| 24 | C30/37 CONCRETE CURB | ||||||||||||
| Cordolo in Calcestruzzo classe C30/37 | IT. No. Art. n. | 9 | LS/AC | 1.00 | |||||||||
| 25 | S355JR GLVD STEEL STRUCTURE | ||||||||||||
| Struttura portante in acciaio zincato S355JR | IT. No. Art. n. | 10 | KG | 16,500.00 | |||||||||
| 26 | TESTING OF THE STRUCTURES IAW DM 17.01.2018 | ||||||||||||
| Collaudo delle strutture ai sensi del DM 17.01.2018 | IT. No. Art. n. | 11 | LS/AC | 1.00 | |||||||||
| Total Structural - Totale Strutturale | |||||||||||||
| IIc Civil - IIc Civile | |||||||||||||
| 27 | RESTORATION OF REINFORCED CNC PAVEMENT | ||||||||||||
| Ripristino di pavimentazione in calcestruzzo armato | IT. No. Art. n. | 12 | SM/MQ | 22.00 | |||||||||
| 28 | RESTORATION OF BITUMINOUS CONCRETE PAVEMENT | ||||||||||||
| Ripristino di pavimentazione in conglomerato bituminoso | IT. No. Art. n. | 13 | SM/MQ | 188.00 | |||||||||
| 29 | CONSTRUCTION OF CONCRETE RAMP | ||||||||||||
| Costruzione di rampa in calcestruzzo | IT. No. Art. n. | 14 | LS/AC | 1.00 | |||||||||
| 30 | CONSTRUCTION OF REINFORCED CNC PAVEMENT | ||||||||||||
| Costruzione di pavimentazione in cls armato | IT. No. Art. n. | 15 | SM/MQ | 30.00 | |||||||||
| 31 | 3cm THICK WEARING COURSE | ||||||||||||
| Strado di usura, Sp=3cm | IT. No. Art. n. | 16 | SM/MQ | 865.00 | |||||||||
| 32 | PIPE BEDDING WITH GRAVEL AND SAND MATERIAL | ||||||||||||
| Allettamento tubazioni in misto granulare e sabbia | IT. No. Art. n. | 17 | CU.M/MC | 33.50 | |||||||||
| 33 | SN4 PVC PIPES FOR DRAINAGE SYSTEM - DN110 | ||||||||||||
| Tubi in PVC classe SN4 impianto di drenaggio - DN110 | IT. No. Art. n. | 18a | LM/ML | 30.00 | |||||||||
| 34 | SN4 PVC PIPES FOR DRAINAGE SYSTEM - DN160 | ||||||||||||
| Tubi in PVC classe SN4 impianto di drenaggio - DN160 | IT. No. Art. n. | 18b | LM/ML | 44.00 | |||||||||
| 35 | SN4 PVC PIPES FOR DRAINAGE SYSTEM - DN200 | ||||||||||||
| Tubi in PVC classe SN4 impianto di drenaggio - DN200 | IT. No. Art. n. | 18c | LM/ML | 44.00 | |||||||||
| 36 | SN4 PVC PIPES FOR DRAINAGE SYSTEM - DN250 | ||||||||||||
| Tubi in PVC classe SN4 impianto di drenaggio - DN250 | IT. No. Art. n. | 18d | LM/ML | 15.00 | |||||||||
| 37 | HDPE PIPES FOR WASTEWATER SYSTEM - DN 50 | ||||||||||||
| Tubazioni in PEAD impianto scarico lavaocchi - DN 50 | IT. No. Art. n. | 19 | LM/ML | 8.00 | |||||||||
| 38 | DETECTABLE WARNING TAPE | ||||||||||||
| Nastro di segnalamento rilevabile | IT. No. Art. n. | 20 | LM/ML | 186.00 | |||||||||
| 39 | TRENCH BACKFILLING WITH SELECTED RESULTING MATERIAL | ||||||||||||
| Rinterro delle trincee con materiale di risulta selezionato | IT. No. Art. n. | 21 | CU.M/MC | 98.00 | |||||||||
| 39 | 30x30 cm CONCRETE PIT INCL. D400 CAST IRON COVER | ||||||||||||
| Pozzetto di cls 30x30 cm incluso chiusino in ghisa D400 | IT. No. Art. n. | 22a | EA/NO | 11.00 | |||||||||
| 40 | 50x50 cm CONCRETE PIT INCL. D400 CAST IRON COVER | ||||||||||||
| Pozzetto di cls 50x50 cm incluso chiusino in ghisa D400 | IT. No. Art. n. | 22b | EA/NO | 11.00 | |||||||||
| 41 | HDPE PIPES FOR W/FP SYSTEM - DN160 | ||||||||||||
| Tubazioni in PEAD impianto idrico antincendio - DN 160 | IT. No. Art. n. | 23 | LM/ML | 72.00 | |||||||||
| 42 | 120x120 CM REINF. CONCRETE WATER PIT INCLUDING D400 COVER | ||||||||||||
| Pozzetto di calcestruzzo armato 120x120cm per rete idrica incluso chiusino D400 | IT. No. Art. n. | 24 | EA/NO | 1.00 | |||||||||
| 43 | PN 16, DN160 BRONZE VALVE AND CAST-IRON VALVE BOX | ||||||||||||
| Valvola PN 16, DN160 in bronzo e box valvola in ghisa | IT. No. Art. n. | 25 | EA/NO | 1.00 | |||||||||
| Total Civil - Totale Civile | |||||||||||||
| TOTAL PART II / Totale Parte II | |||||||||||||
| PART III - MECHANICAL WORK / Parte III - Lavori Meccanici | |||||||||||||
| IIIa HVAC - IIIa HVAC | |||||||||||||
| 44 | AIR RENOVATION SYSTEM COMPLETE OF CONTROLS, CONTAMINANT SENSORS AND FITTINGS | ||||||||||||
| Sistema di rinnovo dell'aria completo di controlli, sensori di contaminanti ed accessori | IT. No. Art. n. | 1 | LS/AC | 1.00 | |||||||||
| 45 | TEST AND BALANCING HVAC AND VENTILATION SYSTEMS | ||||||||||||
| Prove e bilaciamento dei sistemi HVAC e ventilazione | IT. No. Art. n. | 2 | LS/AC | 1.00 | |||||||||
| Total HVAC - Totale HVAC | |||||||||||||
| IIIb Plumbing - IIIb Idrico sanitario | |||||||||||||
| 46 | DOMESTIC COLD AND HOT WATER PIPEWORK. | ||||||||||||
| Rete di distribuzione acqua calda e fredda potabile | IT. No. Art. n. | 3 | LS/AC | 1.00 | |||||||||
| 47 | PN16 BALL VALVE - DN20 | ||||||||||||
| Valvola a sfera PN16 - DN20 | IT. No. Art. n. | 4 | EA/NO | 3.00 | |||||||||
| 48 | Y FILTER - DN20 | ||||||||||||
| Filtro ad Y - DN20 | IT. No. Art. n. | 5 | EA/NO | 1.00 | |||||||||
| 49 | EYE WASH STATION COMPLIANT WITH EN 15154 | ||||||||||||
| Postazione lava occhi conforme alla EN 15154 | IT. No. Art. n. | 6 | EA/NO | 1.00 | |||||||||
| 50 | TEST AND CLEANING PUMBING SYSTEMS | ||||||||||||
| Prove e pulizia impianto idricosanitario | IT. No. Art. n. | 7 | LS/AC | 1.00 | |||||||||
| Total Plumbing - Totale Idrico sanitario | |||||||||||||
| IIIc Fire Suppression - IIIc Spegnimento incendi | |||||||||||||
| 51 | NEW COMPLETE SPRINKLER FIRE CABINET | ||||||||||||
| Nuova stazione sprinkler completa | IT. No. Art. n. | 8 | LS/AC | 1.00 | |||||||||
| 52 | FIRE DEPARTMENT CONNECTION - FDC DN80 UNI70 DOUBLE. | ||||||||||||
| Gruppo attacco VVF - FDC DN80 UNI70 doppio | IT. No. Art. n. | 9 | EA/NO | 1.00 | |||||||||
| 53 | NEW DRY SPRINKLER SYSTEM W/PIPES, SPRINKLERS, SEISMIC BRACING, SUPPORTS AND FITTINGS Nuovo sistema sprinkler a secco con tubazione, staffaggio antisismico, supporti e accessori | IT. No. Art. n. | 10 | LS/AC | 1.00 | ||||||||
| 54 | SEISMIC PIPE JOINT- JUST DN125 | ||||||||||||
| Giunto antisistmico per tubazioni - fino DN125 | IT. No. Art. n. | 11 | EA/NO | 7.00 | |||||||||
| 55 | HYDRAULIC CALCULATION - SPRINKLER NFPA 13 | ||||||||||||
| Calcoli idraulici sprinkler - NFPA 13 | IT. No. Art. n. | 12 | LS/AC | 1.00 | |||||||||
| 56 | SPRINKLER SYSTEM TEST AND CERTIFICATION | ||||||||||||
| Prove e certificazioni sull'impianto sprinkler | IT. No. Art. n. | 13 | LS/AC | 1.00 | |||||||||
| Total Fire suppression - Totale Spegnimento incendi | |||||||||||||
| TOTAL PART III - Totale Parte III | |||||||||||||
| PART IV- ELECTRICAL WORK / Parte VI - Lavori Elettrici | |||||||||||||
| IVa Power System - Impianto Forza Motrice | |||||||||||||
| 57 | NEW DB11A ELECTRICAL PANEL | ||||||||||||
| Nuovo quadro elettrico DB11A | IT. No. Art. n. | 1 | EA/NO | 1.00 | |||||||||
| 58 | FG16OR16 5G2,5 Sqmm ELECTRICAL CABLE | ||||||||||||
| Cavo elettrico FG16OR16 5G2,5 mmq | IT. No. Art. n. | 2a | LM/ML | 960.00 | |||||||||
| 59 | FG16R16 5G2,5 Sqmm ELECTRICAL CABLE | ||||||||||||
| Cavo elettrico FG16R16 5G2,5 mmq | IT. No. Art. n. | 2b | LM/ML | 650.00 | |||||||||
| 60 | 500x50 GALVANIZED STEEL CABLE TRAY | ||||||||||||
| Canale portacavi in acciaio 500x50 | IT. No. Art. n. | 3a | LM/ML | 10.00 | |||||||||
| 61 | 300x50 GALVANIZED STEEL CABLE TRAY | ||||||||||||
| Canale portacavi in acciaio 300x50 | IT. No. Art. n. | 3b | LM/ML | 15.00 | |||||||||
| 62 | 150x50 GALVANIZED STEEL CABLE TRAY | ||||||||||||
| Canale portacavi in acciaio 150x50 | IT. No. Art. n. | 3c | LM/ML | 80.00 | |||||||||
| 63 | PVC CONDUIT DIAM. 32 MM | ||||||||||||
| Cavidotto in PVC diam. 32 mm | IT. No. Art. n. | 4 | LM/ML | 60.00 | |||||||||
| 64 | ITALIAN STYLE RECEPTACLE OUTLETS 16A | ||||||||||||
| Prese tipo italiano 16 A | IT. No. Art. n. | 5 | EA/NO | 16.00 | |||||||||
| 65 | OUTLETS FEEDING POINT 16A | ||||||||||||
| Alimentazione Punto Presa 16 A | IT. No. Art. n. | 6 | EA/NO | 16.00 | |||||||||
| 66 | EMERGENCY SHUT-OFF CIRCUIT | ||||||||||||
| Circuito elettrico pulsante di emergenza | IT. No. Art. n. | 7 | LS/AC | 1.00 | |||||||||
| 67 | EMERGENCY LIGHTS CIRCUIT TEST | ||||||||||||
| Circuito test luci emergenza | IT. No. Art. n. | 8 | LS/AC | 1.00 | |||||||||
| Total Power System - Totale Impianto Forza Motrice | |||||||||||||
| IVb Lighting System - Impianto Illuminazione | |||||||||||||
| 68 | INSTALLATION OF LIGHTING POINT SWITCH | ||||||||||||
| Installazione di interruttore per punto luce | IT. No. Art. n. | 9 | EA/NO | 6.00 | |||||||||
| 69 | INSTALLATION OF LIGHTING POINT | ||||||||||||
| Installazione punto luce | IT. No. Art. n. | 10 | EA/NO | 60.00 | |||||||||
| 70 | PVC CONDUIT DIAM. 40 MM | ||||||||||||
| Cavidotto in PVC diam. 40 mm | IT. No. Art. n. | 11 | LM/ML | 60.00 | |||||||||
| 71 | ZUMTOBEL CRAFT LUMINAIRE OR EQUAL APPROVED | ||||||||||||
| Apparecchio illuminanate Zumtobel Craft o eq. Approvato | IT. No. Art. n. | 12 | EA/NO | 31.00 | |||||||||
| 72 | ZUMTOBEL RESCLITE ANT. OR EQUAL APPROVED | ||||||||||||
| Zumtobel Resclite Ant o equivalente approvato | IT. No. Art. n. | 13 | EA/NO | 10.00 | |||||||||
| 73 | ZUMTOBEL RESCLITE ESC. OR EQUAL PRROVED | ||||||||||||
| Zumtobel Resclite Esc o equivalente approvato | IT. No. Art. n. | 14 | EA/NO | 10.00 | |||||||||
| 74 | ZUMTOBEL MULTIFUNCTION CONTROLLER OR EQ. APPROV. | ||||||||||||
| Controllo multifunzione Zuntobel o eq. approvato | IT. No. Art. n. | 15 | EA/NO | 1.00 | |||||||||
| 75 | ZUMTOBEL CIRCLE CONTROL OR EQ. APPROV. | ||||||||||||
| Comando Circle Zumtobel o eq. Approvato | IT. No. Art. n. | 16 | EA/NO | 1.00 | |||||||||
| 76 | PICTOGRAM FOR CEILING MOUNTED EXIT LIGHTS | ||||||||||||
| Pittogrammi per luci uscite di emergenza a soffitto | IT. No. Art. n. | 17 | EA/NO | 3.00 | |||||||||
| 77 | MAINTAINED EMERGENCY LIGHTING FIXTURE | ||||||||||||
| Corpo illuminante di emergenza funz. Permanente | IT. No. Art. n. | 18 | EA/NO | 3.00 | |||||||||
| 78 | EXTERIOR FLOODLIGHT DISANO MINI RODIO OR EQ. APP. | ||||||||||||
| Proiettore Per Esterno Disano Mini Rodio o eq. Appr. | IT. No. Art. n. | 19 | EA/NO | 6.00 | |||||||||
| Total Ligting System System - Totale Impianto Illuminazione | |||||||||||||
| IVc Communication System - Impianto Comunicazioni | |||||||||||||
| 79 | CAT 6 RJ45 OUTLETS | ||||||||||||
| Prese CAT 6 RJ45 | IT. No. Art. n. | 20 | LS/AC | 1.00 | |||||||||
| Total Communication System - Totale Impianto Comunicazioni | |||||||||||||
| IVd Fire Alarm System systems - Impianto Allarme Incedio | |||||||||||||
| 80 | SMOKE DETECTORS | ||||||||||||
| Rilevatori di fumo | IT. No. Art. n. | 21 | EA/NO | 11 | |||||||||
| 81 | HEAT DETECTORS | ||||||||||||
| Rilevatori di calore | IT. No. Art. n. | 22 | EA/NO | 1 | |||||||||
| 82 | PULL STATIONS | ||||||||||||
| Stazioni manuali | IT. No. Art. n. | 23 | EA/NO | 4 | |||||||||
| 83 | AUDIO/VISUAL DEVICE | ||||||||||||
| Dispositivo audio/video | IT. No. Art. n. | 24 | EA/NO | 5 | |||||||||
| 84 | FIRE ALARM CONTR. PANEL NOTIFIER AM-8200 OR EQ. APP. | ||||||||||||
| Centrale allarme incendio | IT. No. Art. n. | 25 | EA/NO | 1 | |||||||||
| 85 | LEAD BATTERY 12V 17-18 Ah | ||||||||||||
| Batteria al Piombo 12V 17-18 Ah | IT. No. Art. n. | 26 | EA/NO | 2 | |||||||||
| 86 | METAL SIGN | ||||||||||||
| Cartello indicatore in metallo | IT. No. Art. n. | 27 | EA/NO | 4 | |||||||||
| 87 | STANDARD BASE | ||||||||||||
| Base standard | IT. No. Art. n. | 28 | EA/NO | 12 | |||||||||
| 89 | 1 INPUT ADDRESSABLE MODULE | ||||||||||||
| Modulo indirizzato 1 input | IT. No. Art. n. | 29 | EA/NO | 5 | |||||||||
| 88 | FG40HM1 2x1 mm2 cable | ||||||||||||
| Cavo FG40HM1 2x1 mm2 | IT. No. Art. n. | 30 | LM/ML | 150 | |||||||||
| 90 | 100x50 GALVANIZED STEEL CABLE TRAY | ||||||||||||
| Canale portacavi in acciaio 100x50 | IT. No. Art. n. | 30 | LM/ML | 90 | |||||||||
| 91 | F/A programmation | ||||||||||||
| Programmazione quadro F/A | IT. No. Art. n. | 31 | LS/AC | ||||||||||
| Total Fire Alarm System - Totale Impianto Allarme Incendio | |||||||||||||
| TOTAL PART IV - Totale Parte IV | |||||||||||||
| PART V - FIRE PREVENTION/ Parte V - Prevenzione Incendi | |||||||||||||
| 92 | CPI PROCUREMENTS | ||||||||||||
| Ottenimento Certificato Prevenzioen incendi | IT. No. Art. n. | 1 | LS/AC | 1.00 | |||||||||
| 93 | FIRE ESTINGUISHER | ||||||||||||
| Estintori | IT. No. Art. n. | 2 | EA/NO | 4.00 | |||||||||
| 94 | FIRE PREVENTION SIGNS | ||||||||||||
| Segnaletica antincendio | IT. No. Art. n. | 3 | LS/AC | 1.00 | |||||||||
| Total Fire Prevention - Totale Prevenzione Incendi | |||||||||||||
| TOTAL PART V - Totale Parte V | |||||||||||||
| ADDENDUM #01 / Modifica n°01 | |||||||||||||
| 1 | WALL MOUNT RACK | ||||||||||||
| Rastrelliera comunicazioni a muro | IT. No. Art. n. | 1 | LS/AC | 1.00 | |||||||||
| Total Addendum #01 - Totale Modifica n°01 | |||||||||||||
| TOTAL ADDENDUM #01 - Totale modifica n°01 | |||||||||||||
| SUMMARY / Riepilogo | |||||||||||||
| PART I - DEMOLITIONS, EXCAVATIONS AND REMOVALS | |||||||||||||
| PART II - ARCHITECTURAL, STRUCTURAL AND CIVIL WORK | |||||||||||||
| PART III - MECHANICAL WORK | |||||||||||||
| PART IV - ELECTRICAL WORK | |||||||||||||
| PART V - FIRE PREVENTION | |||||||||||||
| ADDENDUM #01 | |||||||||||||
| TOTAL PRICE / Costo Totale | |||||||||||||
| OR US DOLLARS (RATE 1$ = 0,8587€) |
&C&"Arial,Grassetto"&12FOR OFFICIAL USE ONLY &C&"Arial,Grassetto"&12FOR OFFICIAL USE ONLY&RSheet &P of &N
GRAND TOTAL
| ASHE 19-1057- ENCLOSE RENOVATE TACTICAL VEHICLE BOAT OVERHANG, B.73003 | ||||
| INSTRUCTIONS FOR COMPLETING AF FORM 3052 | ||||
| TOTAL MATERIAL COSTS | € | |||
| TOTAL LABOR COSTS | € | |||
| TOTAL OTHER DIRECT COSTS | € | |||
| TOTAL DIRECT COSTS | € | |||
| OVERHEAD | % | € | ||
| SUBTOTAL | € | |||
| PROFIT | % | € | ||
| TOTAL PRICE | € | |||
| DATE | FIRM NAME | |||
| TITLE | BY | |||
| INSTRUCTIONS TO OFFERORS |
&C&"Arial,Grassetto"&12FOR OFFICIAL USE ONLY &C&"Arial,Grassetto"&12FOR OFFICIAL USE ONLY Col 1 Item. Description of materials required, work to be done, special equipment needed, etc. Breakdown should be in sufficient detail to permit itemizing of all direct costs.
Col 2 Unit of Measure. Description of the unit in which each item is to be estimated (examples - square yards-SY, cubic yards-CY, square feet- SF, linear feet-LF, board feet-BF, each-EA,, pound-LB).
Col 3 Quantity. Contractor's estimated of quantity required in terms of unit of measure (column 2). Item and units of measure will be furnished by the Government. Quantity estimates will be furnished by the Government only when it is anticipated that a unit price contract will be issued. Otherwise, the contractor is responsible for determining quantity estimates.
Col 4 and 5 Material Costs. Enter unit cost (Col 4) of material to be supplied and total cost (Col 5) for item listed in column 1.
Col 6, 7 and 8 Labor Costs. Enter in col 6 the estimated number of manhours or mandays needed to perform the work listed in column 1. Enter in col 7 the average rate per manhour (manday) and in col 8 the total labor cost.
Col 9 Other Direct Costs. Enter estimated costs of special equipment and other items (listed in column 1), which are special to the contract and of significant dollar value.
Col 10 Line. Self-explanatory.
Note: In addition to other totals entered on various pages, the grand total of column 10, plus overhead and profit will be shown on the last page as follows:
1. The purpose of this form is to provide a standard format by which the offeror submits to the Government a summary of incurred and estimated costs, (and attached supporting information) suitable for detailed review and analysis. Prior to the award of a contract resulting from this proposal, the offeror shall, under the conditions stated in ASPR 3-807.3, be required to submit a certificate of current cost or pricing data (see ASPR 3-807.3 and 3-807.4).
2. In addition to the specific information required by this form, the offeror is experted, in good faith, to incorporate in and submit with this form any additional data, supporting schedules, or substation which are reasonably required for the conduct of an appropriate review and analysis in the light of the specific facts of this procurement. For effective negotiations, it is essential that there be a clean understanding of:
a. The existing, verifiable data.
b. The judgmental factors applied in projecting from know data to the estimate, and
c. The contingencies used by the offeror in his proposed price.
In short, the offeror's estimating process itself needs to be disclosed.
3. When attachment of supporting cost or pricing data to this form is impracticable, the data will be described (with schedules as appropriate) and made available to the contracting officer or his authorized representative upon request.
4. By submission of this proposal the offeror grants to the contracting officer, or his authorized representative, the right to examine, for the purpose of verifying the cost or pricing data submitted, those books, records, documents and other supporting data which will permit adequate evaluation of such cost or pricing data, along with the computations and projections used therein. This right may be exercised in connection with any negotiations prior to contract award.