This Request for Qualifications (RFQ) is issued by the City of Phoenix, Arizona Office of the City Engineer for Construction Manager at Risk (CMAR) services on the Arizona Science Center Stormwater and Sewer Pipe Replacement project located at 600 E. Washington Street. The project seeks a qualified CMAR firm to provide preconstruction services and complete construction services for the replacement and remediation of all existing drain, waste, vent (DWV), and storm drainage systems serving the Arizona Science Center facility. The estimated construction cost is $8.2 million. The preconstruction phase services include detailed cost estimating, design collaboration, constructability reviews, project planning and scheduling, value engineering, long-lead procurement studies, permitting assistance, and local and Small Business Enterprise (SBE) participation coordination. Construction phase services encompass all work necessary to complete the project, including subcontractor management, quality control, safety oversight, schedule management, two Guaranteed Maximum Price (GMP) proposals, 24-hour emergency response coverage, and warranty period services through project closeout. A mandatory pre-submittal meeting is scheduled for 11:00 a.m. on Tuesday, December 1, 2026, at Phoenix City Hall or via Microsoft Teams. Statements of Qualifications must be submitted electronically through the City's Procurement Portal by 12:00 p.m. on Friday, December 11, 2026, with a maximum of 12 pages permitted. Selection notification is anticipated for mid-January 2027, with a scope meeting scheduled for end of January 2027.
The evaluation process is qualifications-based, with scoring distributed across five criteria: General Information (150 points), Experience and Qualifications of the Firm (250 points), Experience of Key Personnel (250 points), Understanding of the Project and Approach (350 points), and Reference Checks (21 points), totaling 1,021 points. Prospective firms must hold appropriate Arizona contractor licenses and be registered in the City's Vendor Management System prior to submittal. Firms must provide current Experience Modification Rate (EMR), a bonding capacity statement from an A- rated or better Surety Company, and three project references. Only firms with physical business locations within Maricopa County are eligible to meet SBE subcontracting goals, which will be established prior to construction based on SBE subcontractor availability. The CMAR will be required to maintain all project records in electronic format using UNIFIER, the City's web-based project management database. The City reserves the right to reject any or all Statements of Qualifications, conduct due diligence reviews, and disqualifies proposers who violate the contact with City employees policy or fail to provide required documentation.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CITY OF PHOENIX, ARIZONA
OFFICE OF THE CITY ENGINEER
DESIGN AND CONSTRUCTION PROCUREMENT
REQUEST FOR QUALIFICATIONS
ARIZONA SCIENCE CENTER STORMWATER AND SEWER PIPE
REPLACEMENT
CONSTRUCTION MANAGER AT RISK SERVICES
OPENGOV ID NO. PW26740069
RFQ Rev. 1/25 Page | 2
The City of Phoenix is seeking a qualified Construction Manager at Risk (CMAR) to provide preconstruction services and complete construction services for the ARIZONA SCIENCE
CENTER STORMWATER AND SEWER PIPE REPLACEMENT CONSTRUCTION MANAGER
AT RISK SERVICES project. The selected CMAR will work as a team with the designer of record and City staff to ensure an efficient design approach for the project. The project site is located at
600 E. Washington Street. The estimated construction cost is $8.2 million.
Project Description
The purpose of this project is to provide Construction Manager at Risk (CMAR) services for the replacement, and/or other remedy methods approved by the design engineer, of all existing drain, waste, vent (DWV), and storm drainage systems serving the Arizona Science Center. The project will address aging and deteriorated plumbing infrastructure throughout the facility to improve system reliability, maintain operational continuity, and support the long-term functionality of the building.
The selected CMAR will provide comprehensive services throughout all phases of the project, including preconstruction, Guaranteed Maximum Price (GMP) development and contract transition, construction, project closeout, and warranty period services.
Scope of Work
The Construction Manager at Risk will begin with the firm in an agency support role for preconstruction services. The CMAR will assume the risk of delivering the project through a Guaranteed Maximum
Price (GMP) contract. The CMAR will be responsible for construction means and methods, and will be required to solicit bids from prequalified subcontractors to perform the work using the City’s subcontractor selection process. The CMAR may also compete to self-perform limited amounts of work. The GMP must be submitted in MAG or CSI format or it will not be accepted.
A. Preconstruction phase services by the CMAR may include the following:
o Provide detailed cost estimating and knowledge of marketplace conditions and budget validation at designated design milestones o Design-phase collaboration and constructability reviews, including procurement and subcontractor selection recommendations o During the preconstruction phase, the CMAR will collaborate closely with the Owner and design team to evaluate design alternatives, identify constructability issues, develop value engineering recommendations, and establish procurement strategies for long-lead and critical materials o Provide project planning and scheduling o Provide for construction phasing and scheduling that will minimize interruption to City operations and allow for facility to remain open and operational during construction activities o Logistics and phasing plans to support ongoing facility operations o Site utilization and access planning o Pipe camera exploration and locating as needed to assist design process o Include pot holing as needed to identify system connections at building exterior o Provide add alternate for ADA upgrades, including adult changing stations
Page | 3 o Provide alternate systems evaluation and constructability studies o Value engineering and cost-saving analyses o Advise City on ways to gain efficiencies in project delivery o Risk identification and mitigation planning o Provide long-lead procurement studies and initiate procurement of long-lead items o Assist in the permitting processes o Participate with the City in a process to set a goal for local and SBE participation and implement the local and SBE process o Protect the City’s sensitivity to quality, safety, and environmental factors
B. Construction phase services by the CMAR may include:
o Following GMP acceptance, the CMAR will provide all construction services necessary to complete the work, including subcontractor management, quality control, safety oversight, schedule management, coordination with facility operations, and overall project delivery o Construction services shall include the replacement, and/or other remedy methods approved by design engineer, of all existing drain, waste, vent (DWV), and storm drainage systems serving facility. Remedy methods aside from replacement, may include: HDPE split casting sleeves, cured in place pipe (CIPP) lining, or other alternatives methods accepted by EOR o Select subcontractors/suppliers for this project o Prepare two (2) Guaranteed Maximum Price (GMP) proposals that each meet the approval of the City. Each GMP proposal will not exceed budget capacity for specified fiscal years.
o Coordinate with various City of Phoenix departments, other agencies, utility companies, etc.
o Arrange for procurement of materials and equipment o Schedule and manage site operations, with a focus on safety and security o Bid, award, and manage all construction related contracts while meeting City bid requirements including the local and SBE participation goal o Provide quality controls o Bond and insure the construction o Address all federal, state and local permitting requirements o Maintain a safe work site for all project participants o The CMAR shall prepare and maintain an emergency response plan that identifies designated points of contact and escalation procedures. During the construction phase, the CMAR shall provide 24-hour, 7-day emergency response coverage and respond in person to emergency situations on-site within two (2) hours of notification.
o Include temporary restrooms as designed by EOR o Comply with COP building standards o The CMAR's services will continue through project closeout and warranty, including systems verification, punch-list completion, as-built documentation, operation and maintenance manual coordination, staff training support, warranty management, and resolution of post-construction issues to ensure successful project completion and Owner satisfaction.
Page | 4
• Use of UNIFIER, an Application Service Provider (ASP) web-based project management database, may be required. The following information provides a guideline for utilization. Any questions related to the requirements of UNIFIER should be directed to the Project Manager.
• The CMAR will be required to maintain all project records in electronic format.
• The City provides an ASP web-based project management database which the CMAR will be required to utilize in the fulfillment of the contract requirements.
• The CMAR shall provide a computerized networked office platform with broadband internet connectivity.
• UNIFIER training will be provided through the City of Phoenix to firms under contract.
Small Business Enterprise (SBE) Requirements
Only firms whose physical business is located within Maricopa County are eligible to meet the
SBE subcontracting goal, which will be set prior to construction of this project. The final goal will be based on SBE subcontractor availability.
Pre-Submittal Meeting
A pre-submittal meeting will be held at 11:00 am, Phoenix time on Tuesday, December 1, 2026, at Phoenix City Hall, 200 West Washington Street, 6th Floor, Conference Room 6 West AND via
Teams. At this meeting, City staff will discuss the scope of work, general project requirements, and respond to questions from the attendees. It is strongly recommended that interested firms attend the pre-submittal meeting. Inquiries regarding the project scope outside of this pre-submittal meeting must be directed to the Contracts Specialist.
Pre-Submittal Meeting Teams Information:
https://teams.microsoft.com/meet/2198868857943990?p=1hUaChk4PwXfRglAnj
Meeting ID: 219 886 885 794 399 0
Passcode: tE9B65c7
Statement of Qualifications Evaluation Criteria
A firm will be selected through a qualifications-based selection process based on the criteria below. Subcriteria are listed in order of importance in relation to project services. City of Phoenix project experience is not required.
No. Evaluation Criteria Scoring Method Weight (Points) https://teams.microsoft.com/meet/2198868857943990?p=1hUaChk4PwXfRglAnj
Page | 5
1. General Information
Provide a general description of the firm that is proposing to provide construction management services and general construction services.
Explain the legal organization of the proposed firm or team. Provide an organization chart showing key personnel.
A. Provide the following information:
1. List the Arizona contractor licenses held by the firm and the key personnel who will be assigned to this project.
Provide the contractor license number.
Reference the appropriate licenses held, if needed. In order to be considered for this project, the contractor must hold the correct license as deemed appropriate by the
Arizona Registrar of
Contractors prior to submitting a Statement of Qualifications (SOQ) for this project in accordance with
Arizona Revised Statute
§32-1151.
2. Identify the location of the firm’s principal office and the home office location of key staff on this project.
Points Based 150
(14.7% of Total)
Page | 6
3. Identify any contract or subcontract held by the firm or officers of the firm, which has been terminated within the last five years. Identify any claims arising from a contract which resulted in litigation or arbitration within the last three years. Briefly describe the circumstances and the outcomes.
Page | 7
2. Experience and Qualifications of the Firm
A. Identify at least three comparable projects in which the firm served as either CMAR, agency
Construction Manager during design and construction phases
(without providing construction services), or
General Contractor. Special consideration will be given to firms that have provided
Construction Manager at
Risk services on similar successful projects. For each project identified, provide the following:
1. Description of the project
2. Role of the firm (specify whether Construction
Manager at Risk, Construction Manager or General Contractor. If
CMAR or General
Contractor, identify the percent of work self-performed. Also specify services provided during design phase, i.e. cost estimating, scheduling, value engineering, etc.)
3. Project’s original contracted construction cost and final construction cost
4. Construction dates
Points Based 250
(24.5% of Total)
Page | 8
5. Project owner
3. Experience of Key Personnel to be Assigned to This Project
For each key person identified, list their length of time with the firm and at least two comparable projects in which they have played a primary role. If a project selected for a key person is the same as one selected for the firm, provide just the project name and the role of the key person. For other projects provide the following:
1. Description of project
2. Role of the person
3. Project’s original construction cost and final construction cost
4. Construction dates
5. Project owner
A. List any proposed consultants, including key staff names and the experience and qualifications of these individuals.
Points Based 250
(24.5% of Total)
Page | 9
4. Understanding of the Project and Approach to Performing the
Required Services
A. Discuss the major issues your team has identified on this project and how you intend to address those issues.
B. Attached to this Request for
Qualifications is the City of
Phoenix general subcontractor selection plan
(see Exhibit A). Describe how you intend to implement this subcontractor selection plan including your recommendations for subcontractor trades to be selected by qualifications only vs. qualifications and bids; and discuss the benefit that your subcontractor selection plan provides to the project.
C. Describe your team’s project management approach and team organization during design and construction phase services. Describe systems used for planning, scheduling, estimating, and managing construction.
Briefly describe the firm’s experience on quality control, dispute resolution, and safety management.
Points Based 350
(34.3% of Total)
Page | 10
5. Reference Checks
Use the form provided in the
Attachments section to obtain at least three references. It is preferred no more than one be a
City of Phoenix project. If your firm has not completed prior projects with other agencies, you will not be penalized. It is recommended there be references outside the City of
Phoenix.
*These points are in addition to the
1,000 points for the SOQ.
Points Based 21
(2.1% of Total)
Submittal Requirements
Electronic Submittal Process: Firms interested in this project must submit a Statement of
Qualifications (SOQ) electronically through the City's Procurement Portal at https://procurement.opengov.com/portal/phoenix.
Submittal requirements are as follows:
Vendor Information: All firms must be registered in the City’s Vendor Management System prior to submitting a proposal. The vendor number should be included on the cover of the
SOQ. Information on how to register with the City is available at:
https://www.phoenix.gov/financesite/Pages/EProc-help.aspx
If your firm is already registered with the City of Phoenix’s Procurement system, visit https://procurement.opengov.com/portal/phoenix to login and access the electronic solicitation.
Submittals:
• Experience Modification Rate (EMR) – provide current rating; the awarded company will be asked to provide verification upon contract execution.
• Submit only one SOQ electronically, in .PDF format only, addressing all evaluation criteria. No hard copies will be accepted.
• Clearly display the firm legal name, vendor number, project title, and project number on the cover of the SOQ.
• A maximum of 12 pages is permitted to address all content in the SOQ submittal.
(Maximum page limit includes evaluation criteria and all additional content. It does not include information sheet.)
• Submit electronically the Statement of Qualifications by 12:00 pm, Phoenix time, on
Friday, December 11, 2026.
https://procurement.opengov.com/portal/phoenix https://www.phoenix.gov/financesite/Pages/EProc-help.aspx https://procurement.opengov.com/portal/phoenix
Page | 11
• Page size must meet requirements of 8½” x 11”.
• Font size must not be less than 10 point.
• Content count:
o Each side of a page containing evaluation criteria and additional content will be counted toward the maximum page limit noted above.
o Pages that have project photos, charts and/or graphs will be counted towards the maximum page limit noted above.
o Front and back covers, information sheet, Table of Contents pages, and divider (tab) pages will NOT be counted toward the maximum page limit noted above, unless they include evaluation criteria and additional content that could be considered by the selection panel.
Information Sheet: Provide an information sheet that includes project title, OpenGov ID number, legal firm name (not a trade name), address, phone number, vendor number, and the name, title, email address and signature of your contact person for the project. Do not include any additional information.
Evaluation Criteria: Address the SOQ evaluation criteria.
Bonding Statement: As a separate PDF attachment, include a statement of the firm’s bonding capacity from a Surety Company (A- or better for the prior four quarters). This bond statement will not be counted towards the maximum number of pages.
Additional Content: Resumes and other information may be included (content shall be included within the permitted maximum page limit).
Note: All pages exceeding the specified maximum page limit will be removed from the submittal and not considered in evaluating a submitted SOQ.
Grounds for Disqualification
Please be advised that the following will be grounds for disqualification, and will be strictly enforced:
• Submitting a Statement of Qualifications for a different project
• Violating the “Contact with City Employees” policy contained in this RFQ
• Failure to provide additional documents due at time of submittal
• Failure to provide bonding statement
Selection Process and Schedule
The successful firm will be selected through a qualifications-based selection process. Interested firms will submit a Statement of Qualifications (SOQ). A Selection Panel will evaluate each SOQ according to the criteria set forth in Statement of Qualifications Evaluation Criteria above. The https://procurement.opengov.com/portal/phoenix/projects/325206/document?section=3075406
Page | 12
City will select a firm based on the SOQs received; no formal interviews will be conducted. The
City may conduct a due diligence review on the firm receiving the highest evaluation.
The City expects to create a final list of at least one, but not more than three firms for this project.
The City will enter into negotiations with the selected firm and execute a contract upon completion of negotiation of contract terms for City Council approval.
The following tentative schedule has been prepared for this project. The Pre-submittal meeting is not mandatory.
Pre-submittal Meeting 11:00 am on Tuesday, December 1, 2026
SOQs Due 12:00 pm on Friday, December
11, 2026
Selection Notification Mid-January 2027
Scope Meeting End of January 2027
If the City is unsuccessful in negotiating a contract with the best-qualified firm, the City may then negotiate with the next most qualified firm until a contract is executed, or the City may decide to terminate the selection process. Once a contract is executed with the successful firm, the procurement is complete.
The firm selected for this project will be notified directly by the City. Notification to all other firms on the status of a short list for this project will be posted on the City of Phoenix’s Procurement
Portal:
https://procurement.opengov.com/portal/phoenix
General Information
Citywide Capital Improvement Projects. Consulting and contractor services supporting the
City’s Capital Improvement Projects are procured under the authority of the City Engineer, currently located within the Street Transportation Department. Design and Construction
Procurement coordinates the citywide consulting and construction contracting procurement processes.
Changes to Request for Qualifications. Any changes to this Request for Qualifications
(RFQ) will be in the form of a Notification. The City of Phoenix shall not be held responsible for any oral instructions. Notifications are available on both the Current Opportunities and City's eProcurement Portal at https://procurement.opengov.com/portal/phoenix.
It shall be the responsibility of the registered RFQ holder to determine, prior to the submittal of the Statement of Qualifications, if a Notification has been issued. Registered
RFQ holders may refer to the web page or call the Contracts Specialist (listed below) to ascertain if a Notification has been issued for this project.
Page | 13
Alternate Format. For more information or a copy of this publication in an alternate format, contact O'cie Hendricks at (602) 534-1423 - Voice or TTY 711. Requests will only be honored if made within the first week of the advertising period.
Release of Project Information/Public Records Request. The City shall provide the release of all public information concerning the project, including selection announcements and contract awards. Those desiring to release information to the public must receive prior written approval from the City. To submit a Public Records Request, visit phoenix.gov/prr.
City Rights. The City of Phoenix reserves the right to reject any or all Statements of
Qualifications, to waive any informality or irregularity in any Statement of Qualifications received, and to be the sole judge of the merits of the respective Statements of Qualifications received.
Contact with City Employees. This policy is intended to create a level playing field for all
Proposers, assure that contracts are awarded in public, and protect the integrity of the selection process. OFFERORS THAT VIOLATE THIS POLICY WILL BE DISQUALIFIED.
Beginning on the date the RFQ is issued and until the date the contract is awarded or the RFQ withdrawn, all persons or entities that respond to the RFQ, including their authorized employees, agents, representatives, proposed partner(s), subcontractor(s), joint venture(s), member(s), or any of their lobbyists or attorneys (collectively the Proposer), will refrain from any direct or indirect contact with any person (other than the designated Contract Specialist) who may play a part in the selection process, including members of the evaluation panel, the City Manager, Assistant
City Manager, Deputy City Managers, Department heads, the Mayor and other members of the
Phoenix City Council. As long as the RFQ solicitation is not discussed, Proposers may continue to conduct business with the City and discuss business that is unrelated to this RFQ solicitation with City staff.
Commencing on the date and time a solicitation is published, potential or actual proposers
(including their representatives) will only discuss matters associated with the solicitation with the
Mayor, any members of City Council, the City Manager, any Deputy City Manager, or any department director directly associated with the solicitation (including in each case their assigned staff, except for the designated procurement officer) at a public meeting, posted under the Arizona
Revised Statutes, until the resulting contract(s) are awarded or all offers or responses are rejected and the solicitation is cancelled without any announcement by the procurement officer of the City’s intent to reissue the same or a similar solicitation.
Proposers may discuss their proposal or the RFQ solicitation with the Mayor or one or more members of the Phoenix City Council, provided such meetings are scheduled through the
Contract Specialist (listed above), conducted in person at 200 W. Washington, Phoenix, Arizona
85003, and are posted as open meetings with the City Clerk at least twenty-four (24) hours prior to the scheduled meetings. The City Clerk will be responsible for posting the meetings. The posted notice shall identify the participants and the subject matter, as well as invite the public to participate.
Conflict of Interest. The City reserves the right to disqualify any Proposer on the basis of any real or apparent conflict of interest that is disclosed by the proposal submitted or any other data available to the City. This disqualification is at the sole discretion of the City. Any Proposer submitting a proposal herein waves any right to object now or at any future time, before any body or agency, including but not limited to, the City Council of the City of Phoenix or any court.
https://phoenix.gov/prr
Page | 14
Protest Procedures. Firms responding to disqualification or a procurement outcome are referred to the Code of the City of Phoenix Chapter 2, Article XII, Section 2-187 to 2-190.4, which governs protest procedures utilized throughout the selection process. The procedures may be reviewed through the City of Phoenix website at:
http://www.codepublishing.com/az/phoenix/
A copy of the Protest Policy is also available online at:
https://www.phoenix.gov/administration/departments/streets/careers/business-opportunities.html
Questions - Questions pertaining to this selection process or contract issues should be submitted via the Procurement Portal.
Vendor Questionnaire
*Response required
*Response required http://www.codepublishing.com/az/phoenix/ https://www.phoenix.gov/administration/departments/streets/careers/business-opportunities.html
| REQUEST FOR QUALIFICATIONS |
| Project Description |
| Scope of Work |
| Small Business Enterprise (SBE) Requirements |
| Pre-Submittal Meeting |
| Statement of Qualifications Evaluation Criteria |
| Submittal Requirements |
| Grounds for Disqualification |
| Selection Process and Schedule |
| General Information |
| Vendor Questionnaire |
File details come from the government source that posted it. Updated .