ARFQ 0608 DCR2400000049 - SWRJ Addendum No. 1.pdf

PDF 369 KB Posted

Attached to
Equipment and Systems Maintenance and Repairs SWRJCF
Solicitation number
ARFQ 0608 DCR2400000049 2
Issued by
Lewis County, West Virginia

About this file

This addendum addresses clarifications and modifications to Request for Quotation 0608 DCR2400000049 for equipment and systems maintenance and repair services at the Southwestern Regional Jail and Correctional Facility. The contract encompasses corrective maintenance services including the provision and replacement of air filters, with labor charged at hourly rates and materials subject to a percentage markup as specified in the contract documents. The bid closing date has been established for 10:30 AM E.S.T. on October 23, 2023, with the public bid opening scheduled for 11:00 AM E.S.T. on the same date. A non-mandatory pre-bid sign-in sheet is available for prospective bidders.

Regarding pricing and contract requirements, filter provision and replacement will be billed through corrective maintenance hourly labor rates plus applicable material markups, with the contractor responsible for sourcing and installing replacement air filters at the facility. A bid bond is not required for this procurement. The addendum does not specify contract duration, renewal options, or other detailed pricing terms beyond the maintenance labor and material markup structure outlined for filter services.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ARFQ 0608 DCR2400000049

REQUEST FOR QUOTATION

EQUIPMENT AND SYSTEMS MAINTENANCE AND REPAIRS CONTRACT

SOUTHWESTERN REGIONAL JAIL AND CORRECTIONAL FACILITY

Addendum No. 1

Questions:

Q1: Are filters included in the contract price?

A1: If the facility wants the contractor to provide and replace the filters, it is done as a corrective maintenance hourly labor rate cost and a material percentage markup as stated in the specifications. The contractor would be responsible for providing and installing new air filters at the facility.

Clarifications:

C1: Please see attached non-mandatory pre-bid sign-in sheet.

C2: A bid bond will not be required on this contract.

C2: The bid closing date has changed: 10:30 AM E.S.T. on October 23, 2023

C3: The public bid opening date has changed: 11:00 AM E.S.T. on October 23, 2023