Approved Drawings
9 MB Posted
- Attached to
- PROPANE INFRASTRUCTURE
- Solicitation number
- 23-038
- Issued by
- Fulton County, Georgia
About this file
Summary
This document is a set of approved construction drawings and specifications for the City of Sandy Springs, Georgia, for the Long Island Streambank Stabilization Project located at 5375 Long Island Drive, Sandy Springs, GA 30327. The project involves stabilizing approximately 130 linear feet of eroded streambank along Long Island Creek through removal of excess debris and unsuitable soils, re-grading of the right stream bank slope, and installation of FlexaMat Plus erosion protection material. Additional work includes installation of curb and gutter (370 linear feet of 24-inch curb and gutter with 117 linear feet of replacement), guardrail installation (approximately 337 linear feet total), coir logs along the water edge, and rip-rap placement at the slope toe. The project encompasses a total disturbed area of 0.23 acres within the Long Island Drive right-of-way, a permanent 10-foot slope easement, and a temporary construction easement. A non-mandatory pre-bid conference was scheduled for October 19, 2022, at 11:00 AM via Zoom, with questions due by October 26, 2022, at 5:00 PM and bids due November 14, 2022, at 2:00 PM EST through the Bonfire Portal. The building permit was approved on September 22, 2022.
The construction drawings indicate earthwork quantities of 110.11 cubic yards of cut and 2.03 cubic yards of fill, though the contractor is required to verify all quantities independently and cannot rely on plan quantities. All work shall comply with Georgia Department of Transportation Standard Specifications and current editions, with the contractor responsible for utility coordination using the 811 call-before-you-dig system. Key utility facilities identified in the project area include Atlanta Gas Light (4-inch steel gas main), Fulton County Water and Sewer, Georgia Power Company, FiberLight, and Zayo. The contractor must provide independent geotechnical testing to verify soil compaction meets City of Sandy Springs standards, maintain traffic control per MUTCD requirements with at least one lane open at all times, install erosion control measures prior to land disturbance, and furnish as-built drawings signed and sealed by a registered land surveyor. All project communications and submissions must be directed to the Procurement Agent, Edward McAdoo, at purchasing@sandyspringsga.gov, and all bids must be submitted exclusively through the Bonfire Portal.
Text of this file
SHEET INDEX
SHEET NO. SHEET NAME
C0.00 COVER SHEET
C0.01 STANDARD SPECIFICATIONS
SURV BOUNDARY AND TOPOGRAPHIC SURVEY
C2.00 GRADING PLAN
C2.10 CURBING & GUARDRAIL PLAN
C2.20 PROFILES
C3.10 EROSION CONTROL PLANS
C3.41 - C3.42 EROSION CONTROL DETAILS
C4.00 - C4.01 CONSTRUCTION DETAILS
LONG ISLAND DRIVE
STREAMBANK STABILIZATION
5375 LONG ISLAND DRIVE
SANDY SPRINGS, GA 30327
FOR
CITY OF SANDY SPRINGS
1 GALAMBOS WAY
SANDY SPRINGS, GA 30328
PHONE: (770) 730-5600
PREPARED BY:
SITE LOCATION MAP
NOT TO SCALE
FEMA FIRM MAP
FEMA FIRM PANEL NO.: 13121C0144F
NOT TO SCALE
N
SITE LOCATION
SITE LOCATION
C0.00
COVER SHEET
N/A
Planners & Engineers Collaborative+
LAND PLANNING + LANDSCAPE ARCHITECTURE + CIVIL ENGINEERING
ARBORISTS + SURVEYING & CONSTRUCTION + WATER RESOURCES
350 RESEARCH COURT STE 200 PEACHTREE CORNERS, GA 30092 P: (770) �51-27�1
21318.00 02/04/2022
J:
\2
1\
0\
D e\
_P la ns he et s\
C 0.
C O
V E
R S
H E
E T
- 2
.d w g
- C
Te st a
- 8
/1 /2
:1
A
M
AT
P: (770) 451-2741
350 RESEARCH COURT STE 200
PEACHTREE CORNERS, GA 30092
F: (770) 451-3915
WWW.PEC.PLUS
Planners & Engineers Collaborative+
LAND PLANNING
SURVEYING & CONSTRUCTION
CIVIL ENGINEERING
ARBORISTS
LANDSCAPE ARCHITECTURE
WATER RESOURCES+ +
2 3 4 5 6 7 8 9 10 11 12 13 14 151
K
J
I
H
G
F
E
D
C
B
A
2 3 4 5 6 7 8 9 10 11 12 13 14 151
SCALE:
DATE:
PROJECT:
DESCRIPTIONNO. BYDATE
GEORGIA WEST ZONE
GRID NORTH
SHEET
REVISIONS
c Th is d ra w in g is th e pr op er ty o f P la nn er s an d En gi ne er s
C ol la bo ra tiv e an d is n ot to b e co pi ed in w ho le o r i n pa rt.
It is n ot to b e us ed o n an y ot he r p ro je ct a nd is to b e re tu rn ed u po n re qu es t.
P la nn er s an d En gi ne er s
C ol la bo ra tiv e.
FOR
PROJECT
CITY COMMENTS1 CT05-06-22
CITY OF SANDY SPRINGS
1 GALAMBOS WAY
SANDY SPRINGS, GA 30328
P: (770) 730-5600
LONG ISLAND DRIVE
STREAMBANK
STABILIZATION
WR#21-030596
5375 LONG ISLAND DRIVE
SANDY SPRINGS, GA 30327
CITY COMMENTS2 CT05-24-22
GSWCC LEVEL II DESIGN PROFESSIONAL
CERTIFICATION # 0000067548 EXP. 12/21/2024
THIS SEAL IS ONLY VALID IF COUNTER SIGNED
AND DATED WITH AN ORIGINAL SIGNATURE.
7/29/2022
CITY COMMENTS3 CT05-27-22
CITY COMMENTS4 CT06-16-22
CITY COMMENTS5 CT07-29-22
CONTACT INFORMATION:
ENGINEER: NEIL SCHAAP, P.E.
PLANNERS AND ENGINEERS
COLLABORATIVE
ADDRESS: 350 RESEARCH COURT
PEACHTREE CORNERS,
GEORGIA 30092
PHONE: 770.451.2741
EMAIL: NSCHAAP@PEC.PLUS
OWNER: CITY OF SANDY SPRINGS
ADDRESS: 1 GALAMBOS WAY
SANDY SPRINGS, GA 30328
PHONE: (770) 730-5600
1. TOTAL DISTURBED AREA: 0.23 ACRES.
2. BOUNDARY & TOPOGRAPHIC INFORMATION PROVIDED BY GEOSURVEY DATED 12/17/2021.
3. THE FEDERAL EMERGENCY MANAGEMENT AGENCY FLOOD INSURANCE RATE MAP FOR FULTON COUNTY, GEORGIA AND INCORPORATED AREAS, COMMUNITY PANEL NUMBER(S) 13121C0144F, EFFECTIVE DATE 09/18/2013 WAS EXAMINED AND NO PORTION OF THE PROPERTY SHOWN HEREIN WAS FOUND TO FALL WITHIN A DESIGNATED FLOOD ZONE "A" (AREAS OF 100-YEAR FLOOD) OR SPECIAL FLOOD HAZARD ZONE (AREAS OF 500-YEAR FLOOD).
4. THERE ARE STATE WATERS LOCATED ON THE PROJECT SITE
5. THERE ARE NO KNOWN WETLANDS ON THIS SITE
24 HOUR CONTACT:
CITY OF SANDY SPRINGS
770-730-5600
ADDRESS: 5375 LONG ISLAND DRIVE
SANDY SPRINGS, GA 30327
SITE INFORMATION
SITE DATA
THIS PROJECT INVOLVES STABILIZING APPROXIMATELY 130 LF OF ERODED STREAM BANK ALONG LONG ISLAND CREEK IN SANDY SPRINGS, GA. WORK ASSOCIATED WITH THE PROJECT WILL INCLUDE UTILITY LINE COORDINATION, REMOVING EXCESS DEBRIS AND UNSUITABLE SOILS FROM THE RIGHT STREAMBANK SLOPE, RE-GRADING THE RIGHT STREAM BANK SLOPE, AND INSTALLING FLEXAMAT PLUS ALONG THE RE-GRADED SLOPE TO PROVIDE EROSION PROTECTION. CURB AND GUTTER AND GUARDRAIL WILL ALSO BE INSTALLED AS PART OF THE PROJECT. ACCESS WILL BE PROVIDED IN THE LONG ISLAND DRIVE RIGHT OF WAY AND PROJECT WORK WILL OCCUR IN THE RIGHT OF WAY, THE PERMANENT 10 FOOT SLOPE EASEMENT ADJACENT, AND IN A TEMPORARY CONSTRUCTION EASEMENT. THIS
WORK IS INTENDED TO STABILIZE THE STREAMBANK AND PREVENT FUTURE HEAVY EROSION.
PROJECT SCOPE:
NO SPECIMEN TREES ARE PROPOSED TO BE REMOVED FOR THIS PROJECT.
TREE / VEGETATION REMOVAL
P W
-0
-5
LO
N G
IS
LA
N D
D R
N W
W
-0
R
PERMITTED
09/22/2022
BUILDING PERMIT
SANDY SPRINGS, GA. COMMUNITY DEVELOPMENT DEPARTMENT
THESE PLANS WERE REVIEWED WITH RESPECT TO BUILDING CODES ONLY. NO EFFORT WAS MADE TO
CHECK THE ELECTRICAL, PLUMBING, MECHANICAL OR STRUCTURAL DESIGN OTHER THAN TO
COMPARE THE SUBMITTED PLANS WITH THE APPLICABLE BUILDING CODES. STRUCTURAL REVIEW ALSO CONSIDERED APPLICABILITY OF A SPECIAL INSPECTIONS PROGRAM. STRUCTURAL INTEGRITY IS THE TOTAL RESPONSIBILITY OF THE OWNER AND THE OWNER'S AGENTS. THIS BUILDING PERMIT IS
SUBJECT TO ALL SANDY SPRINGS ORDINANCES AND GEORGIA STATE LAWS.
BY:_____________________________________________Natalie G Adkisson
ALL WORK SHALL BE DONE IN ACCORDANCE WITH GEORGIA
DEPARTMENT OF TRANSPORTATION STANDARD SPECIFICATIONS
CONSTRUCTION OF TRANSPORTATION SYSTEMS, APPROVED
APRIL 18, 2013; AND GDOT CONSTRUCTIONS STANDARDS AND
DETAILS, LATEST VERSIONS. SPECIFICATIONS USED ARE NOT
LIMITED TO THE SPECIFICATIONS LISTED ON THE FOLLOWING
PAGES.
CLEARING AND GRADING
1. ALL WORK TO BE DONE IN ACCORDANCE WITH THE GEORGIA DEPARTMENT OF
TRANSPORTATION STANDARD SPECIFICATIONS FOR THE CONSTRUCTION OF TRANSPORTATION
(GDOT) SYSTEMS, CURRENT EDITION, AND SUPPLEMENTS THERETO, AS APPROVED BY THE
FEDERAL HIGHWAY ADMINISTRATION.
2. ALL KNOWN UTILITY FACILITIES ARE SHOWN SCHEMATICALLY ON PLANS AND ARE NOT
NECESSARILY ACCURATE IN LOCATION AS TO PLAN OR ELEVATION. UTILITY FACILITIES SUCH AS
SERVICE LINES OR UNKNOWN FACILITIES NOT SHOWN ON PLANS WILL NOT RELIEVE THE
CONTRACTOR OF HIS OR HER RESPONSIBILITY UNDER THIS REQUIREMENT. "EXISTING UTILITY FACILITIES" MEANS ANY UTILITY THAT EXISTS ON THE PROJECT IN ITS ORIGINAL, RELOCATED OR
NEWLY INSTALLED POSITION. ALL SPECIFIC ITEMS IN THE DETAILED ESTIMATE ARE TO BE
REMOVED OR RELOCATED TO CLEAR CONSTRUCTION IN ADVANCE O F THE WORK. DISRUPTION
TO SERVICES OUTSIDE THE HOURS OF 9:00 AM AND 4:00 PM REQUIRE PRIOR APPROVAL BY THE
CITY OF SANDY SPRINGS.
3. UTILITY WORK COORDINATION WILL BE REQUIRED AS PART OF THIS CONTRACT. THE
CONTRACTOR WILL BE REQUIRED TO USE THE ONE-CALL CENTER TELEPHONE NUMBER 811, FOR
THE PURPOSE OF COORDINATING THE MARKING OF UNDERGROUND UTILITIES. THE
CONTRACTOR'S ATTENTION IS CALL TO SUBSECTION 105.06 OF THE GDOT STANDARD
SPECIFICATIONS "COOPERATION WITH UTILITIES."
4. THE FOLLOWING UTILITIES HAVE FACILITIES IN THE PROJECT AREA:
ATLANTA GAS LIGHT (SOUTHERN COMPANY GAS)
CONTACT: GINNNY MAULDIN-KINNEY (404) 584-3176
FULTON COUNTY WATER AND SEWER
CONTACT: ABDUL AKBAR (404) 612-7518
GEORGIA POWER COMPANY
CONTACT: LAMONTE WASLIEN (404) 947-0729
FIBERLIGHT
CONTACT: EVAN MOSHONISIOTIS (443) 807-1340
ZAYO
CONTACT: RUSTY PERDIEU (706) 889-6967
5. THE EARTHWORKS QUANTITY SHOWN ON THE PLANS IS TO BE VERIFIED BY THE CONTRACTOR.
THE CONTRACTOR SHALL NOTIFY THE CITY IF EARTHWORKS QUANTITIES ARE FOUND TO BE
DIFFERENT THAN WHAT IS IN THE BID DOCUMENTS. THE CITY OF SANDY SPRINGS PUBLIC
WORKS DEPARTMENT ASSUMES NO RESPONSIBILITY FOR ITS ACCURACY, AND INCLUDE
GRADING WORK AS PART OF THE BID PRICE FOR GRADING COMPLETE AND IT SHALL BE HIS OR
HER RESPONSIBILITY TO DETERMINE THE ACTUAL EARTHWORK QUANTITY TO BE GRADED. NO
CLAIMS WILL BE CONSIDERED FOR EXTRA COMPENSATION IF THE CONTRACTOR RELIES ON THE
QUANTITY SHOWN ON THE PLANS. GRADING ON THIS PROJECT IS LIMITED TO THE ACTUAL
CONSTRUCTION LIMITS UNLESS DIRECTED BY THE ENGINEER. COST FOR GRADING SHALL BE
INCLUDED IN THE BID PRICE FOR GRADING COMPLETE.
6. THE CONTRACTOR SHALL STRICTLY ADHERE TO DUST CONTROL REGULATIONS. ALL AREAS
SUBJECTED TO DUST FORMATION MUST BE PERIODICALLY WATERED SUFFICIENT TO RETARD
DUST, NO SEPARATE PAYMENT WILL BE MADE FOR ANY COST INCURRED TO COMPLY WITH THIS
REQUIREMENT.
7. THE TOTAL AREA SHOWN ON THE PLANS FOR GRASSING IS FOR INFORMATION ONLY. THE CITY
OF SANDY SPRINGS ASSUMES NO RESPONSIBILITY FOR ITS ACCURACY. THE CONTRACTOR
SHALL INCLUDE IN THE BID PRICE FOR GRASSING, AND IT SHALL BE HIS RESPONSIBILITY TO
DETERMINE THE ACTUAL AREA TO BE GRASSED. NO CLAIMS WILL BE CONSIDERED FOR
COMPENSATION IF THE CONTRACTOR RELIES ON THE AREA SHOWN ON THE PLANS.
8. THE TYPE OF GRASS OR SOD USED ON THIS PROJECT WILL BE REQUIRED TO MATCH ANY TYPE
OF GRASS OR SOD WHICH MAY BE PLANTED AND GROWING ON THE ADJACENT LAWN. I.E.
BERMUDA SOD FOR BERMUDA SOD, ZOYSIA FOR ZOYSIA, ETC. NO SEPARATE PAYMENT SHALL
BE MADE FOR ANY COST INCURRED TO COMPLY WITH THIS REQUIREMENT.
9. INGRESS AND EGRESS SHALL BE MAINTAINED AT ALL TIMES TO ADJACENT PROPERTIES. REFER
TO SUB-SECTION 107.07 OF THE GDOT STANDARD SPECIFICATIONS.
10. IT SHALL BE THE CONTRACTOR'S RESPONSIBILITY TO FURNISH SUITABLE BORROW MATERIAL
FOR THE PROJECT AND DISPOSE OF ANY UNSUITABLE OR WASTE MATERIAL.
11. HORIZONTAL CONTROL IS BASED UPON GEORGIA STATE PLANE COORDINATE SYSTEM.
12. IN THE EVENT A DRIVEWAY IS DAMAGED DUE TO CONSTRUCTION, THE DRIVEWAY SHALL BE
REPLACED, IN KIND, I.E. ASPHALT FOR ASPHALT, CONCRETE FOR CONCRETE, AND BRICK
PAVERS FOR BRICK PAVERS. EXCEPT EARTH AND GRAVEL DRIVEWAYS SHALL BE REPLACED
WITH ASPHALT TO THE CONSTRUCTION LIMITS. DRIVEWAYS CONTAINING BRICK PAVERS SHALL
BE CONSTRUCTED USING GDOT SPECIFICATIONS. THE DRIVEWAY LOCATIONS INDICATED ON
THE PLANS ARE FROM THE BEST AVAILABLE DATA. THE CONTRACTOR SHALL CONSTRUCT NEW
DRIVEWAYS TO MATCH ACTUAL FIELD LOCATIONS OF EXISTING DRIVEWAYS WHERE THEY ARE
NOT IN CONFLICT WITH RULES AND REGULATIONS. THE CONTRACTOR SHALL OBTAIN THE
APPROVAL OF THE ENGINEER PRIOR TO MAKING ANY REVISIONS SUCH AS TO LOCATION, WIDTH
AND/OR NUMBER OF DRIVES TO BE CONSTRUCTED. WHERE REQUIRED, THE DRIVEWAY SHALL BE
PAVED AS FOLLOWS:
ASPHALTIC DRIVES
RESIDENTIAL:
1.5" RECY. ASPHALTIC CONCRETE, 9.5mm SUPERPAVE, GP 2 ONLY, INCLUDING BITUM. MAT'L & H. LIME
6" GRADED AGGREGATE BASE
COMMERCIAL:
1.5" RECY. ASPHALTIC CONCRETE, 9.5mm SUPERPAVE, GP 2 ONLY, INCLUDING BITUM. MAT'L AND H. LIME
2" RECY. ASPHALTIC CONC. 19mm SUPERPAVE, GP 1 OR 2, INCLUDING BITUM. MAT'L AND H.LIME
8" GRADED AGGREGATE BASE
CONCRETE DRIVES
RESIDENTIAL: 6" CONCRETE VALLEY GUTTER
6" CONCRETE DRIVEWAY
COMMERCIAL: 8" CONCRETE VALLEY GUTTER
8" CONCRETE DRIVEWAY
ALL DRIVEWAYS SHALL BE PAVED TO THE LIMITS OF CONSTRUCTION. EXISTING
DRIVEWAYS SHALL NOT BE USED FOR PROJECT ACCESS.
13. WHERE WET SUBGRADE IS ENCOUNTERED AND WATER IDENTIFIED BY THE ENGINEER, AN
UNDERDRAIN PIPE WITH DRAINAGE AGGREGATE SHALL BE PLACED AS DIRECTED BY THE
ENGINEER TO AID IN DEWATERING THE SUBGRADE.
14. THE CONTRACTOR SHALL OBSERVE ALL APPLICABLE LOCAL, STATE, AND FEDERAL SAFETY
REGULATIONS REGARDING PIPE INSTALLATION IN TRENCHES. NO SEPARATE PAYMENT WILL BE
MADE FOR ANY COST INCURRED TO COMPLY WITH THIS REQUIREMENT.
15. ALL EXISTING STORMWATER PIPE SHALL BE REMOVED UNLESS OTHERWISE NOTED ON PLANS OR AS DIRECTED BY THE ENGINEER. ALL COST FOR REMOVAL SHALL BE INCLUDED IN THE LUMP
SUM BID PRICE FOR GRADING COMPLETE.
16. IN AREAS WHERE TYPE 2 CURB IS USED, DRAINAGE STRUCTURES 1033D AND 1034D WILL BE
REQUIRED. IN AREAS WHERE TYPE 7 CURB IS USED, DRAINAGE STRUCTURES 1033G AD 1034G
WILL BE REQUIRED.
17. AT LOCATIONS WHERE NEW PAVEMENT IS TO BE PLACED ADJACENT TO EXISTING PAVEMENT
WITHOUT AN OVERLAY OR WHERE CURBING IS TO BE PLACED ACROSS A PAVED AREA, A JOINT
SHALL BE SAWED ON A LINE ESTABLISHED BY THE ENGINEER TO ENSURE PAVEMENT REMOVAL
TO A NEAT LINE. THE COST FOR ASPHALT SAWED JOINTS, WHEN REQUIRED, SHALL BE INCLUDED
IN THE BID PRICE FOR GRADING COMPLETE.
18. WHERE EXISTING PAVEMENT MARKINGS AND LINES ARE IN CONFLICT WITH THE TRAFFIC
PATTERN BEING USED ON CONSTRUCTION, THE THE CONTRACTOR SHALL REMOVE OR OVERLAY
LINES TO THE SATISFACTION OF THE ENGINEER SUCH THAT THE LINES DO NOT CONFUSE THE
TRAVELING PUBLIC. ALL REMAINING LINES OR MARKINGS SHALL BE IN ACCORDANCE WITH THE
'MANUAL ON UNIFORM TRAFFIC CONTROL DEVICES', OR AS DIRECTED BY THE ENGINEER.
TRAFFIC SHALL NOT BE ALLOWED ON ANY PAVEMENT NOT PROPERTY STRIPED.
19. THE CONTRACTOR'S ATTENTION IS DIRECTED TO ARTICLES 104.05 AND 107.07 OF THE STANDARD
SPECIFICATIONS AND THE SPECIAL PROVISIONS FOR TRAFFIC CONTROL AND SEQUENCE OF
OPERATIONS IN REGARDS TO MAINTENANCE OF TRAFFIC DURING CONSTRUCTION.
20. THE BID PRICE FOR TRAFFIC CONTROL SHALL INCLUDE, BUT IS NOT LIMITED TO CONSTRUCTION, MAINTENANCE , AND REMOVAL OF TEMPORARY SIGNAGE AND PAVEMENT MARKINGS, BARRICADES, CHANNELIZING DEVICES, ETC, REQUIRED FOR MAINTENANCE OF TRAFFIC DURING
CONSTRUCTION. ALL TEMPORARY SIGNAGE AND PAVEMENT MARKINGS SHALL BE IN
ACCORDANCE WIT THE 'MANUAL OF UNIFORM TRAFFIC CONTROL DEVICES', CURRENT EDITION
AND/OR AS DIRECTED BY THE ENGINEER.
21. ALL CUT AND FILL SLOPES SHALL BE GRASSED AS DIRECTED BY THE ENGINEER IMMEDIATELY
AFTER THE SLOPES ARE ESTABLISHED IN ORDER TO REDUCE EROSION. IF THE SEASON DOES
NOT PERMIT GRASSING, TEMPORARY MULCH SHALL BE USED AS DIRECTED BY THE ENGINEER.
22. THE CONTRACTOR SHALL ENSURE THAT POSITIVE AND ADEQUATE DRAINAGE IS MAINTAINED AT
ALL TIMES WITHIN THE PROJECT LIMITS. THIS MAY INCLUDE, BUT NOT LIMITED TO,
REPLACEMENT OR RECONSTRUCTION OF EXISTING DRAINAGE STRUCTURES THAT HAVE BEEN
DAMAGED, REMOVED OR REGRADED AS REQUIRED BY THE ENGINEER, EXCEPT FOR THOSE
DRAINAGE ITEMS SHOWN AT SPECIFIC LOCATIONS ON THE PLANS. NO SEPARATE PAYMENT WILL
BE MADE FOR ANY COSTS INCURRED TO COMPLY WITH THIS REQUIREMENT.
23. QUANTITIES SHOWN ON THE PLANS ARE FOR ESTIMATION PURPOSES ONLY. CONTRACTOR IS TO
VERIFY ALL QUANTITIES TO BE INCLUDED IN THE BID PRICE.
24. EROSION CONTROL MEASURES SHALL BE INSTALLED PRIOR TO OR CONCURRENT WITH LAND
DISTURBANCE ACTIVITIES AND SHALL BE MAINTAINED AT ALL TIMES. ADDITIONAL EROSION AND
SEDIMENT CONTROL DEVICES SHALL BE INSTALLED IF DEEMED NECESSARY BY THE ON-SITE
INSPECTOR OR AS DIRECTED BY THE ENGINEER.
25. ALL SILT FENCES MUST BE PLACED AS ACCESS IS OBTAINED DURING CLEARING. NO GRADING
SHALL BE DONE UNTIL SILT FENCE INSTALLATION IS COMPLETE. IT IS THE CONTRACTOR'S
RESPONSIBILITY TO MAINTAIN ALL SILT FENCES AND TO REPAIR OR REPLACE ANY SILT FENCE
THAT IS NOT SATISFACTORY. EROSION CONTROL MEASURES SHALL BE PLACED IMMEDIATELY
AFTER DRAINAGE STRUCTURES ARE IN PLACE. ALL EROSION CONTROL DEVICES SHALL BE
PLACED ACCORDING TO THE PLANS AND AS DIRECTED BY THE ENGINEER. SEE THE GEORGIA
STANDARD SPECIFICATIONS AND THE 'MANUAL FOR EROSION AND SEDIMENT CONTROL IN
GEORGIA', CURRENT EDITION REGARDING EROSION CONTROL. THE CONTRACTOR SHALL BE
RESPONSIBLE TO KEEP WETLAND AREAS FREE FROM SILTATION. THE CONTRACTOR SHALL
OBTAIN AND ABIDE BY ALL UNITED STATES ARMY CORPS OF ENGINEERS (USACE) RULES AND
REGULATIONS CONCERNING CONSTRUCTION ADJACENT TO WATERS OF THE UNITED STATES
(WOTUS) AND MAINTAIN WATER QUALITY.
26. THIS PROJECT HAS A TOTAL DISTURBED AREA OF 0.23 ACRES. THE DISTURBED AREA
ENCOMPASSES THE THE AREA ASSOCIATED WITH CLEARING, GRADING, EXCAVATING, FILLING
OF LAND, OR OTHER SIMILAR ACTIVITIES WHICH MAY RESULT IN SOIL EROSION, AS DEFINED
UNDER 'CONSTRUCTION ACTIVITIES' IN THE STATE OF GEORGIA NATURAL POLLUTANT
DISCHARGE ELIMINATION SYSTEM (NPDES) GENERAL PERMIT NO. GAR100002.
27. AGGREGATE SURFACE COURSE FOR TEMPORARY, DRIVEWAYS, INCLUDING MATERIAL, HAUL
AND PLACEMENT SHALL BE USED AT THE ENGINEER'S DIRECTION TO FACILITATE THE
MOVEMENT OF LOCAL TRAFFIC THROUGH THE CONSTRUCTION AREA DURING INCLEMENT
WEATHER. WHEN USED FOR THIS PURPOSE, SECTION 318 OF THE GDOT STANDARD
SPECIFICATIONS IS MODIFIED TO PERMIT TRUCK DUMPING ON UNPREPARED WET, MUDDY
SUBGRADE. SECTION 318 IS FURTHER MODIFIED TO PERT THE USE OF CRUSHER STONE AS
DESCRIBED IN SECTION 318.02.
28. THE CONTRACTOR WILL HAVE THE USE OF THE FOLLOWING MATERIALS:
A. GRADED AGGREGATE, ARTICLE 815.2.01
B. COURSE GRADED AGGREGATE, SIZE 467, ARTICLE 800.2.01
C. STABILIZED AGGREGATE, TYPE I OR II, SECTION 803.2 OR 803.2.02
D. CRUSHED STONE, ARTICLE 806.2.01
29. CONSTRUCTION LAYOUT AND STAGING PLAN WILL BE REQUIRED BY THE CONTRACTOR. ALL
COST FOR THIS ITEM WILL BE INCLUDED IN THE BID PRICE.
30. CITY OF SANDY SPRINGS PUBLIC WORKS DEPARTMENT SHALL BE NOTIFIED A MINIMUM OF 72
HOURS IN ADVANCE OF ALL CONSTRUCTION ACTIVITIES. THE CONTRACTOR SHALL COORDINATE
THIS ACTION WITH THE LEAD INSPECTOR.
31. THE GDOT STANDARDS AND CONSTRUCTION DETAILS REQUIRED FOR THIS PROJECT ARE LISTED IN THIS PLAN SET WITH THE LAST KNOWN REVISION DATE, HOWEVER THE CONTRACTOR WILL BE
RESPONSIBLE FOR OBTAINING AND MAINTAINING ON THE PROJECT SITE THE CURRENT GDOT
STANDARD DRAWINGS AND CONSTRUCTION DETAILS REQUIRED FOR THIS PROJECT.
32. ANY ADJUSTMENTS OR RELOCATIONS OF CITY OF SANDY SPRINGS PUBLIC WORKS DEPARTMENT FACILITIES SHALL BE IN ACCORDANCE WITH THE CITY OF SANDY SPRINGS ORDINANCE NUMBER 2008-09-48. THIS DOCUMENT IS AVAILABLE AT THE DEPARTMENT OFFICE AT 1 GALAMBOS WAY, CITY OF SANDY SPRINGS. TELEPHONE (770) 730-5600 AND THE 24 HR EMERGENCY CONTACT
NUMBER FOR THE CITY OF SANDY SPRINGS IS (770) 730-5600.
33. THE SURVEY FOR THIS PROJECT WAS PREPARED BY GEOSURVEY AND SUPPLEMENTED USING
FULTON COUNTY AND CITY OF SANDY SPRINGS GIS DATA.
34. STORM DRAINAGE FOR THE ROADWAY MUST BE MAINTAINED DURING CONSTRUCTION.
35. UNLESS OTHERWISE SPECIFIED, ANY IRRIGATION SYSTEM ENCOUNTERED WITHIN THE LIMITS OF
CONSTRUCTION IS TO BE RE-ESTABLISHED (INCLUDING TESTING) BY THE CONTRACTOR.
PROJECT CONTRACTOR IS TO CUT AND CAP IRRIGATION SYSTEM OUTSIDE OF LIMITS OF
CONSTRUCTION DURING CONSTRUCTION.
36. PRIOR TO PROCEEDING WITH CONSTRUCTION, ANY DEBRIS REMAINING AFTER THE REMOVAL OF
OF THE EXISTING STORM SEWER PIPES/STRUCTURES AND OTHER DELETERIOUS NON-SOIL
MATERIALS SHOULD BE STRIPPED FROM PROPOSED CONSTRICTION AREAS.
37. EXCAVATION BRACING (SHORING) DESIGN AND INSTALLATION IS THE RESPONSIBILITY OF THE
GENERAL CONTRACTOR. ANY SHORING (INCLUDING TRENCH BOXES) GREATER THAN FOUR (4)
FEET MUST BE SIGNED AND SEALED BY A STRUCTURAL ENGINEER CURRENTLY REGISTERED IN
THE STATE OF GEORGIA.
38. FILL MATERIAL SHOULD BE LOW PLASTICITY SOIL (PLASTICITY INDEX LESS THAN 30), FREE OF
NON-SOIL MATERIALS AND ROCK FRAGMENTS LARGER THAN 2 INCHES IN ANY ONE DIMENSION.
39. SOIL MOISTURE CONTENT SHOULD BE MAINTAINED WITHIN 3% OF THE OPTIMUM MOISTURE
CONTENT.
40. ORGANIC AND/OR DEBRIS LADEN MATERIAL (>3% ORGANICS BY WEIGHT) IS NOT SUITABLE FOR
RE-USE AS STRUCTURAL FILL.
41. FILL SHOULD BE PLACED IN THIN, HORIZONTAL LOOSE LIFTS (MAXIMUM 8-INCH) AND COMPACTED
TO AT LEAST 100% OF THE STANDARD PROCTOR MAXIMUM DRY DENSITY (ASTM D 698) UNDER
ROADWAYS, 98% OF THE STANDARD PROCTOR IN THE RIGHT OF WAY AND AROUND UTILITIES,
AND 95% OF THE STANDARD PROCTOR ELSEWHERE.
42. CONTRACTOR SHALL PROVIDE INDEPENDENT GEOTECHNICAL TESTING TO VERIFY SOIL
COMPACTION MEETS THE CITY OF SANDY SPRINGS STANDARDS.
43. FILL MATERIALS USED IN STRUCTURAL AREAS SHOULD HAVE A TARGET MAXIMUM DRY DENSITY
OF AT LEAST 95 POUNDS PER CUBIC FOOT (PCF).
44. OPEN-GRADED CRUSHED STONE SHOULD BE PLACED IN RELATIVELY THIN LIFTS OF 12 INCHES
OR LESS AND COMPACTED WITH VIBRATORY COMPACTION EQUIPMENT.
45. WATER LEVELS SHALL BE MAINTAINED AT LEAST ONE FOOT BELOW WORKING SUBGRADE
SURFACES TO AVOID DEGRADING SUBGRADE.
46. THE SUBGRADE SHOULD BE WELL-DRAINED TO PREVENT THE ACCUMULATION OF WATER.
47. GRADING COMPLETE - LUMP SUM SHALL INCLUDE ALL UNCLASSIFIED EXCAVATION, BORROW
EXCAVATION, CHANNEL EXCAVATION, FOUNDATION BACKFILL MATERIAL, TYPE I, ROCK
EXCAVATION, ASPHALT CUTS, CLEARING AND GRUBBING, TREE REMOVAL, DEBRIS/SOLD WASTE
REMOVAL, AND REMOVAL OF ALL ITEMS NOT SHOWN AS SEPARATE PAY ITEM. THIS SHALL ALSO
INCLUDE ALL COMPACTION EFFORTS NECESSARY TO ACHIEVE THE COMPACTION REQUIREMENT
SPECIFIED IN THE PLANS.
48. PLANNERS & ENGINEERS COLLABORATIVE (PEC) SHALL FURNISH "AS-BUILT" DRAWINGS THAT
ARE SIGNED AND SEALED BY A REGISTERED LAND SURVEYOR (R.L.S.). CONTRACTOR SHALL
NOTIFY PEC OF ALL CHANGES AND DEVIATIONS FROM CONTRACT DRAWINGS.
DRAWING LEGEND
FFE XX.XX FINISHED FLOOR ELEVATION
BFE XX.XX BASEMENT FLOOR ELEVATION
SPOT ELEVATION
EXISTING CONTOURS
PROPOSED CONTOURS
PROPOSED WATER LINE
PROPOSED WATER METER
PROPOSED VALVE & END CAP
PROPOSED FIRE HYDRANT & FDC
PROPOSED TEE, BEND & INTERSECTION
PROPOSED SANITARY SEWER LINE
PROPOSED SANITARY MANHOLE
PROPOSED SANITARY CLEANOUT
PROPOSED GREASE TRAP
PROPOSED STORM LINE
PROPOSED JUNCTION BOX
PROPOSED DROP INLET
PROPOSED YARD INLET
PROPOSED CURB INLET
PROPOSED WEIR INLET
PROPOSED CATCH BASIN
PROPOSED HEADWALL
PROPOSED OUTLET CONTROL STRUCTURE
TYPICAL WALL LABELS
TW = TOP OF WALL
TFG = TOP FINISHED GRADE
BFG = BOTTOM FINISHED GRADE
TF = TOP OF FOOTING
BF = BOTTOM OF FOOTING
W
10.72
TW
TF
BF
BFG
TFG
GDOT DETAILS USED IN PROJECT
GDOT DETAIL NUMBER GDOT DETAIL TITLE
9032B CONCRETE CURB & GUTTER
4380 "W" BEAM GUARDRAIL
4381 POSTS & OFFSET BLOCKS FOR "W" & "T"
BEAM GUARDRAIL
C0.01
STANDARD
SPECIFICATIONS
N/A
21318.00 02/04/2022
J:
\2
1\
0\
D e\
_P la ns he et s\
C 0.
C O
V E
R S
H E
E T
- 2
.d w g
- C
Te st a
- 8
/1 /2
:1
A
M
AT
P: (770) 451-2741
350 RESEARCH COURT STE 200
PEACHTREE CORNERS, GA 30092
F: (770) 451-3915
WWW.PEC.PLUS
Planners & Engineers Collaborative+
LAND PLANNING
SURVEYING & CONSTRUCTION
CIVIL ENGINEERING
ARBORISTS
LANDSCAPE ARCHITECTURE
WATER RESOURCES+ +
2 3 4 5 6 7 8 9 10 11 12 13 14 151
K
J
I
H
G
F
E
D
C
B
A
2 3 4 5 6 7 8 9 10 11 12 13 14 151
SCALE:
DATE:
PROJECT:
DESCRIPTIONNO. BYDATE
GEORGIA WEST ZONE
GRID NORTH
SHEET
REVISIONS
c Th is d ra w in g is th e pr op er ty o f P la nn er s an d En gi ne er s
C ol la bo ra tiv e an d is n ot to b e co pi ed in w ho le o r i n pa rt.
It is n ot to b e us ed o n an y ot he r p ro je ct a nd is to b e re tu rn ed u po n re qu nn er s an d En gi ne er s
C ol la bo ra tiv e.
FOR
PROJECT
CITY COMMENTS1 CT05-06-22
CITY OF SANDY SPRINGS
1 GALAMBOS WAY
SANDY SPRINGS, GA 30328
P: (770) 730-5600
LONG ISLAND DRIVE
STREAMBANK
STABILIZATION
WR#21-030596
5375 LONG ISLAND DRIVE
SANDY SPRINGS, GA 30327
CITY COMMENTS2 CT05-24-22
GSWCC LEVEL II DESIGN PROFESSIONAL
CERTIFICATION # 0000067548 EXP. 12/21/2024
THIS SEAL IS ONLY VALID IF COUNTER SIGNED
AND DATED WITH AN ORIGINAL SIGNATURE.
7/29/2022
CITY COMMENTS3 CT05-27-22
CITY COMMENTS4 CT06-16-22
CITY COMMENTS5 CT07-29-22
TRANSPORTATION NOTES
1. ALL TRAFFIC CONTROL AND WARNING DEVICES MUST BE SHOWN AND PLACED
PER THE MUTCD. THE TRAFFIC CONTROL PLAN IS SUBJECT TO CHANGE BY THE
SANDY SPRINGS TRAFFIC ENGINEER.
2. TEMPORARY TRAFFIC CONTROL AND WARNING DEVICES SHALL BE PLACED
PRIOR TO THE COMMENCEMENT OF ANY WORK AND SHALL REMAIN IN PLACE
UNTIL THE CONCLUSION OF ALL SIGNING AND STRIPING WORK.
3. ALL SIGNS SHALL CONFORM TO THE MUTCD STANDARDS AND SANDY SPRINGS
STANDARDS FOR COLOR, SIZE, REFLECTIVITY, HEIGHT, AND PLACEMENT.
4. CONTACT THE SANDY SPRINGS TRAFFIC ENGINEER (770-730-5600) ONE WEEK
PRIOR TO COMMENCEMENT OF ANY STRIPING WORK.
5. A CITY OF SANDY SPRINGS UTILITY PERMIT IS REQUIRED FOR ANY
CONSTRUCTION WITHIN THE RIGHT OF WAY. REFER TO THE CITY'S UTILITY
PERMIT POLICY FOR REQUIREMENTS.
6. SAWCUT MUST BE USED IN ANY AREA WHERE NEW PAVEMENT WILL ABUT
EXISTING PAVEMENT.
7. NO CLOSURES OF OR ENCROACHMENTS INTO THE PEDESTRIAN, BICYCLE, OR
VEHICULAR TRAVEL AREAS SHALL BE DONE WITHOUT PRIOR APPROVAL FROM
THE SANDY SPRINGS TRAFFIC ENGINEER. ALL PROPOSED PLANS FOR
CLOSURES AND ENCROACHMENTS SHALL BE SUBMITTED AT LEAST TWO WEEKS
PRIOR TO INTENDED BEGINNING AND MUST BE APPROVED PRIOR TO
COMMENCEMENT.
8. CONTRACTOR TO VERIFY ALL CONDITIONS, ELEVATIONS AND DIMENSIONS
BEFORE BEGINNING CONSTRUCTION. ANY DISCREPANCIES SHALL BE REPORTED
TO THE ENGINEER FOR JUSTIFICATION AND/OR CORRECTION BEFORE
PROCEEDING WITH THE WORK. CONTRACTOR TO ASSUME RESPONSIBILITY FOR
DISCREPANCIES WHICH ARE NOT REPORTED. ALL DIMENSIONS SHOULD BE
READ OR CALCULATED.
9. CONTRACTOR TO HAVE ALL UTILITIES FILED LOCATION AND CLEARLY MARKED
PRIOR TO THE START OF AN CONSTRUCTION ACTIVITY.
10. CONTRACTOR SHALL PROVIDE ADEQUATE ON-SITE RESTROOM FAICILITIES FOR
WORK CREW FOR THE DURATION OF THE PROJECT. THE FACILITIES SHALL BE
REMOVED PROMPTLY ONCE THE PROJECT IS ACCEPTED.
PERMITTED
09/22/2022
BUILDING PERMIT
SANDY SPRINGS, GA. COMMUNITY DEVELOPMENT DEPARTMENT
THESE PLANS WERE REVIEWED WITH RESPECT TO BUILDING CODES ONLY. NO EFFORT WAS MADE TO
CHECK THE ELECTRICAL, PLUMBING, MECHANICAL OR STRUCTURAL DESIGN OTHER THAN TO
COMPARE THE SUBMITTED PLANS WITH THE APPLICABLE BUILDING CODES. STRUCTURAL REVIEW ALSO CONSIDERED APPLICABILITY OF A SPECIAL INSPECTIONS PROGRAM. STRUCTURAL INTEGRITY IS THE TOTAL RESPONSIBILITY OF THE OWNER AND THE OWNER'S AGENTS. THIS BUILDING PERMIT IS
(VARIABLE R/W)
LONG ISLAND DRIVE
2.6'
2:
1.
5:
4.5'
0+32
0+
0+
0+
0+
0+27
0+
0+
0+
0+31
0+
0+
0+
0+
0+33
0+
0+
0+
0+
1.5'
855855
LOD / TPF
LOD / TPF
LOD / TPF
LOD / TPF
LOD
LOD
LOD
LODLOD
LOD
LOD
LODLODLOD
LODLOD
LOD
LODLODLODLOD
LOD
LOD
LOD
LOD LOD LOD LOD LOD LOD LOD LOD LOD LOD LOD LOD LOD LOD LOD LOD LOD LOD
2:
1.
5:
A- A-
B- B-
D- D-
C- C-
FLEXAMAT PLUSÒ STEEP
SLOPE STABILIZATION
(SEE DETAIL SHEET C4.00)
FLEXAMAT UPSTREAM TRANSITION
(24"x 24" TRENCH FOR FLEXAMAT
ANCHORING, FILLED WITH #3 STONE)
SLOPE EASEMENT
COMMUNICATIONS LINE TO BE FIELD LOCATED PRIOR
TO CONSTRUCTION (SEE NOTE THIS SHEET)
FLEXAMAT DOWNSTREAM TRANSITION
(SEE UPSTREAM NOTE)
TEMPORARY CONSTRUCTION
EASEMENT
EQUIPMENT/ STAGING AREA
12" MINIMUM DIAMETER RIP RAP
STONE ALONG TOE OF SLOPE (SEE
NOTE SHEET C4.00)
FLEXAMAT SLOPE TOE ANCHOR TRENCH
(18"x18" TRENCH FOR FLEXAMAT ANCHORING, FILLED WITH #3 STONE)
EQUIPMENT/
STAGING AREA
EXISTING RIGHT OF WAY
APPROX. LOCATION PER AGL RECORDS. CONTRACTOR TO FIELD
LOCATE PRIOR TO CONSTRUCTION. SEE NOTE THIS SHEET.
PROPOSED GUARDRAIL 1.5'
FROM EDGE OF PAVEMENT
R
Knowwhat'sbelow.
Callbefore you dig.
www.Georgia811.com
GRADING NOTES:
1. DISTURBED AREAS LEFT IDLE FOR FOURTEEN DAYS, AND NOT TO FINAL GRADE,
SHALL BE ESTABLISHED TO TEMPORARY VEGETATION (Ds2). DISTURBED AREAS
LEFT IDLE FOUR WEEKS OR MORE WILL BE ESTABLISHED TO PERMANENT
VEGETATION (Ds3). ALL AREAS TO FINAL GRADE SHALL BE ESTABLISHED TO
PERMANENT VEGETATION WITHIN TWO WEEKS.
2. WHEN HAND PLANTING, MULCH (HAY OR STRAW) SHALL BE UNIFORMLY SPREAD
OVER SEEDED AREA WITHIN 24 HOURS OF SEEDING.
3. DURING UNSUITABLE GROWING SEASONS, MULCH SHALL BE USED AS A TEMPORARY
COVER (Ds1). ON SLOPES THAT ARE 4:1 OR STEEPER, MULCH SHALL BE ANCHORED.
4. CITY OF SANDY SPRINGS LAND DISTURBANCE PERMIT MUST BE DISPLAYED ON THE
SITE AT ALL TIMES DURING CONSTRUCTION AND IN PLAIN VIEW FROM A COUNTY
ROAD OR STREET.
5. SEDIMENT/EROSION CONTROL DEVICES MUST BE CHECKED AFTER EACH STORM
EVENT. EACH DEVICE SHALL BE MAINTAINED OR REPLACED IF SEDIMENT
ACCUMULATION HAS REACHED ON HALF THE CAPACITY OF THE DEVICE.
6. ALL WORK AND MATERIALS SHALL COMPLY WITH THE CITY OF SANDY SPRINGS
GEORGIA REGULATIONS AND CODES AND O.S.H.A. STANDARDS.
7. EXISTING STRUCTURES WITHIN CONSTRUCTION LIMITS ARE TO BE ABANDONED
REMOVED, OR RELOCATED AS NECESSARY.
8. PLANNERS & ENGINEERS COLLABORATIVE (PEC) SHALL FURNISH "AS-BUILT"
DRAWINGS. CONTRACTOR SHALL NOTIFY PEC OF ALL CHANGES AND DEVIATIONS
FROM CONTRACT DRAWINGS.
9. CONTRACTOR SHALL BE RESPONSIBLE FOR ALL RELOCATION INCLUDING BUT NOT
LIMITED TO, ALL UTILITIES, STORM DRAINAGE, SIGNS, TRAFFIC SIGNALS AND POLES,
ETC., GOVERNING AUTHORITIES SPECIFICATIONS AND SHALL BE APPROVED BY
SUCH. ALL COST SHALL BE INCLUDED IN BASE BID.
10. OPEN BURNING OR BURY PITS ARE NOT ALLOWED.
11. THERE ARE NO KNOWN WETLANDS ON SITE PER THE NATIONAL WETLANDS
INVENTORY MAP.
DIRT STATEMENT:
FILL
2.03 C.Y.
CONTRACTOR SHALL PERFORM AND CONCLUDE EARTHWORK
CALCULATIONS INDEPENDENTLY AND SHALL NOT RELY ON THESE
OPINION OF VOLUMES. VOLUMES STATED ARE USED TO SECURE A
HAUL ROUTE PERMIT ONLY.
CUT
110.11 C.Y.
C2.00
GRADING PLAN
1" = 10'
5 10 20 300
21318.00 02/04/2022
J:
\2
1\
0\
D e\
_P la ns he et s\
C 2.
G R
A D
IN
G
P
LA
N
0.
dw g
- C Te st a
- 8 /1
/2
:1
A M
AT
P: (770) 451-2741
350 RESEARCH COURT STE 200
PEACHTREE CORNERS, GA 30092
F: (770) 451-3915
WWW.PEC.PLUS
Planners & Engineers Collaborative+
LAND PLANNING
SURVEYING & CONSTRUCTION
CIVIL ENGINEERING
ARBORISTS
LANDSCAPE ARCHITECTURE
WATER RESOURCES+ +
2 3 4 5 6 7 8 9 10 11 12 13 14 151
K
J
I
H
G
F
E
D
C
B
A
2 3 4 5 6 7 8 9 10 11 12 13 14 151
SCALE:
DATE:
PROJECT:
DESCRIPTIONNO. BYDATE
GEORGIA WEST ZONE
GRID NORTH
SHEET
REVISIONS
c Th is d ra w in g is th e pr op er ty o f P la nn er s an d En gi ne er s
C ol la bo ra tiv e an d is n ot to b e co pi ed in w ho le o r i n pa rt.
It is n ot to b e us ed o n an y ot he r p ro je ct a nd is to b e re tu rn ed u po n re qu nn er s an d En gi ne er s
C ol la bo ra tiv e.
FOR
PROJECT
CITY COMMENTS1 CT05-06-22
CITY OF SANDY SPRINGS
1 GALAMBOS WAY
SANDY SPRINGS, GA 30328
P: (770) 730-5600
LONG ISLAND DRIVE
STREAMBANK
STABILIZATION
WR#21-030596
5375 LONG ISLAND DRIVE
SANDY SPRINGS, GA 30327
CITY COMMENTS2 CT05-24-22
GSWCC LEVEL II DESIGN PROFESSIONAL
CERTIFICATION # 0000067548 EXP. 12/21/2024
THIS SEAL IS ONLY VALID IF COUNTER SIGNED
AND DATED WITH AN ORIGINAL SIGNATURE.
7/29/2022
CITY COMMENTS3 CT05-27-22
CITY COMMENTS4 CT06-16-22
CITY COMMENTS5 CT07-29-22
LONG ISLAND CREEK 1.5:1 GRADED SLOPE WITH
FLEXAMAT PLUS PERMANENT STABILIZATION
PLAN VIEW
SCALE: 1" = 10'
TELECOM UTILITY NOTES:
1. ALL UTILITIES, INCLUDING ALL TELECOM LINES, MUST BE FIELD LOCATED PRIOR TO
START OF WORK. MULTIPLE TELECOM FACILITIES ARE IN THE PROJECT AREA; IF
PROJECT WORK IS FOUND TO BE IN CONFLICT WITH THESE FACILITIES, THE
CONTACTS BELOW MUST BE NOTIFIED.
FIBERLIGHT
CONTACT: EVAN MOSHONISIOTIS (443) 807-1340
ZAYO
CONTACT: RUSTY PERDIEU (706) 889-6967
ATLANTA GAS LINE (AGL) NOTES:
1. AGL GAS LINE SHOWN NORTH OF TEE IS PER AGL RECORDS AND IS NOT SHOWN ON
SURVEY. LOCATION IS APPROXIMATE AND MUST BE FIELD LOCATED.
2. AGL GAS LINE PER AGL RECORDS IS A 4" STEEL GAS MAIN, AND AT TEE, IS
RECORDED TO CROSS UNDERNEATH LONG ISLAND DRIVE. CROSSING IS NOT SHOWN
ON SURVEY AND MUST BE FIELD LOCATED.
3. AFTER FIELD LOCATING AGL 4" GAS LINE, IF WORK IS FOUND TO BE WITHIN A 2.0'
RADIUS OF LINE, AGL MUST BE CONTACTED IMMEDIATELY.
ATLANTA GAS LIGHT (SOUTHERN COMPANY GAS)
CONTACT: JOSHUA CRAWFORD (470) 451-2366
GINNY MAULDIN (470) 316-6836
PERMITTED
09/22/2022
BUILDING PERMIT
SANDY SPRINGS, GA. COMMUNITY DEVELOPMENT DEPARTMENT
THESE PLANS WERE REVIEWED WITH RESPECT TO BUILDING CODES ONLY. NO EFFORT WAS MADE TO
CHECK THE ELECTRICAL, PLUMBING, MECHANICAL OR STRUCTURAL DESIGN OTHER THAN TO
COMPARE THE SUBMITTED PLANS WITH THE APPLICABLE BUILDING CODES. STRUCTURAL REVIEW ALSO CONSIDERED APPLICABILITY OF A SPECIAL INSPECTIONS PROGRAM. STRUCTURAL INTEGRITY IS THE TOTAL RESPONSIBILITY OF THE OWNER AND THE OWNER'S AGENTS. THIS BUILDING PERMIT IS
855855
LO
D
/ TPF
LOD / TPF
LOD / TPF
LOD
LOD
LOD
LOD
LOD
LOD
LODLOD
LOD
LODLODLODLODLODLOD
LO
D
LOD LOD LOD LOD
LOD
LOD
LOD LOD LOD LOD LOD LOD LOD LOD LOD LOD LOD LOD LOD
END 370 LF OF GDOT 24" CURB
& GUTTER. CURB & GUTTER
TO TIE INTO EXISTING
GUARDRAIL END
INSTALL APPROX. 124 LF OF
GUARDRAIL 1.5' FROM BACK
OF CURB (SEE SHEET C4.01)
INSTALL APPROX. 50 LF OF
GUARDRAIL 1.5' FROM BACK
OF CURB (SEE SHEET C4.01)
INSTALL APPROX. 110 LF OF
GUARDRAIL 1.5' FROM BACK
OF CURB (SEE SHEET C4.01)
CONTRACTOR TO SUBMIT A LANE
CLOSURE PLAN TO THE CITY
PRIOR TO START OF WORK
EXISTING
RIGHT OF WAY
END GUARDRAIL APPROX. 3.5' ON
EITHER SIDE OF SEWER MAIN &
DOUBLE WING CATCH BASIN
END OF EXISTING 6" CURB (TO BE REPLACED);
INSTALL 370 LF OF 24" CURB & GUTTER
(SEE DETAIL SHEET C4.01)
INSTALL APPROX. 53 LF
OF GUARDRAIL (SEE
SHEET C4.01)
EXISTING ROAD
STRIPING
EXISTING ROAD
STRIPING
APPROX. LOCATION PER AGL RECORDS.
CONTRACTOR TO FIELD LOCATE PRIOR TO
CONSTRUCTION. SEE NOTE THIS SHEET.
CONTRACTOR TO FIELD LOCATE
EXISTING 4" AGL GAS MAIN
PRIOR TO CONSTRUCTION
END GUARDRAIL APPROX.
5.0' ON EITHER SIDE OF
POWER POLE
AGL VALVE & TEE LOCATION
END GUARDRAIL APPROX.
5.0' ON EITHER SIDE OF
BRACE POLE
DEMO & REPLACE EXISTING
117 LF OF 6" CURB (SEE
NOTE THIS SHEET)
CONTRACTOR TO REPLACE ALL
EXISTING CONFLICTING ROAD SIGNAGE
TAPER GUARDRAIL AND END
AT EXISTING BRIDGE WALL
R
Knowwhat'sbelow.
Callbefore you dig.
www.Georgia811.com
GUARDRAIL NOTES:
1. ALL UTILITIES MUST BE FIELD LOCATED PRIOR TO START OF
GUARDRAIL INSTALLATION. GUARDRAIL POST LOCATION PLAN
MUST BE SUBMITTED TO CITY PRIOR TO START OF WORK SHOWING
AVOIDANCE OF GAS, TELECOM, STORM, SEWER, AND WATER
UTILITY LINES.
0 7.5 15 30 45
1" = 15'
21318.00 02/04/2022
J:
\2
1\
0\
D e\
_P la ns he et s\
C 2.
G R
A D
IN
G
P
LA
N
0.
dw g
- C Te st a
- 8 /1
/2
:1
A M
AT
P: (770) 451-2741
350 RESEARCH COURT STE 200
PEACHTREE CORNERS, GA 30092
F: (770) 451-3915
WWW.PEC.PLUS
Planners & Engineers Collaborative+
LAND PLANNING
SURVEYING & CONSTRUCTION
CIVIL ENGINEERING
ARBORISTS
LANDSCAPE ARCHITECTURE
WATER RESOURCES+ +
2 3 4 5 6 7 8 9 10 11 12 13 14 151
K
J
I
H
G
F
E
D
C
B
A
2 3 4 5 6 7 8 9 10 11 12 13 14 151
SCALE:
DATE:
PROJECT:
DESCRIPTIONNO. BYDATE
GEORGIA WEST ZONE
GRID NORTH
SHEET
REVISIONS
c Th is d ra w in g is th e pr op er ty o f P la nn er s an d En gi ne er s
C ol la bo ra tiv e an d is n ot to b e co pi ed in w ho le o r i n pa rt.
It is n ot to b e us ed o n an y ot he r p ro je ct a nd is to b e re tu rn ed u po n re qu nn er s an d En gi ne er s
C ol la bo ra tiv e.
FOR
PROJECT
CITY COMMENTS1 CT05-06-22
CITY OF SANDY SPRINGS
1 GALAMBOS WAY
SANDY SPRINGS, GA 30328
P: (770) 730-5600
LONG ISLAND DRIVE
STREAMBANK
STABILIZATION
WR#21-030596
5375 LONG ISLAND DRIVE
SANDY SPRINGS, GA 30327
CITY COMMENTS2 CT05-24-22
GSWCC LEVEL II DESIGN PROFESSIONAL
CERTIFICATION # 0000067548 EXP. 12/21/2024
THIS SEAL IS ONLY VALID IF COUNTER SIGNED
AND DATED WITH AN ORIGINAL SIGNATURE.
7/29/2022
CITY COMMENTS3 CT05-27-22
CITY COMMENTS4 CT06-16-22
CITY COMMENTS5 CT07-29-22
1.5' 1.5'
1. CONTRACTOR SHALL PROVIDE TRAFFIC CONTROL IN
ACCORDANCE WITH MUTCD REQUIREMENTS.
2. IF A ROAD CLOSURE IS NECESSARY, CONTRACTOR SHALL
PROVIDE A DETOUR PLAN.
3. DURING CONSTRUCTION, ONE LANE OF ROAD SHALL REMAIN
OPEN AT ALL TIMES UNLESS OTHERWISE APPROVED.
TRAFFIC CONTROL NOTES:
C2.10
CURBING &
GUARDRAIL PLAN
ATLANTA GAS LINE (AGL) NOTES:
1. AGL GAS LINE SHOWN NORTH OF TEE IS PER AGL RECORDS AND IS
NOT SHOWN ON SURVEY. LOCATION IS APPROXIMATE AND MUST
BE FIELD LOCATED.
2. AGL GAS LINE PER AGL RECORDS IS A 4" STEEL GAS MAIN, AND AT
TEE, IS RECORDED TO CROSS UNDERNEATH LONG ISLAND DRIVE.
CROSSING IS NOT SHOWN ON SURVEY AND MUST BE FIELD
LOCATED.
3. AFTER FIELD LOCATING AGL 4" GAS LINE, IF WORK IS FOUND TO BE
WITHIN A 2.0' RADIUS OF LINE, AGL MUST BE CONTACTED
IMMEDIATELY.
ATLANTA GAS LIGHT (SOUTHERN COMPANY GAS)
CONTACT: JOSHUA CRAWFORD (470) 451-2366
GINNY MAULDIN (470) 316-6836
2.25'
2.50'
23.44'
PERMITTED
09/22/2022
BUILDING PERMIT
SANDY SPRINGS, GA. COMMUNITY DEVELOPMENT DEPARTMENT
THESE PLANS WERE REVIEWED WITH RESPECT TO BUILDING CODES ONLY. NO EFFORT WAS MADE TO
CHECK THE ELECTRICAL, PLUMBING, MECHANICAL OR STRUCTURAL DESIGN OTHER THAN TO
COMPARE THE SUBMITTED PLANS WITH THE APPLICABLE BUILDING CODES. STRUCTURAL REVIEW ALSO CONSIDERED APPLICABILITY OF A SPECIAL INSPECTIONS PROGRAM. STRUCTURAL INTEGRITY IS THE TOTAL RESPONSIBILITY OF THE OWNER AND THE OWNER'S AGENTS. THIS BUILDING PERMIT IS
A-A
HORIZONTAL SCALE: 1" = 5'
VERTICAL SCALE: 1" = 5'
EXISTING
POWER POLE
0+00
3.
3.
0+05
3.
3.
0+10
3.
3.
0+15
1.
1.
0+20
5.
5.
0+25
2.
2.
0+30
1.
1.
0+35
BACK OF
CURB
EXISTING RIGHT OF WAY/ BEGINNING
OF 10' SLOPE EASEMENT
END OF 10' SLOPE
EASEMENT
2.71'
5.41'
EDGE OF WATER
1.5'
1.5
EXISTING 4" STEEL
GAS LINE (APPROX.
3.0' DEPTH; TO BE
CONFIRMED PRIOR
TO CONSTRUCTION)
12" MINIMUM DIAMETER RIP RAP ALONG
TOE OF SLOPE (SEE SHEET C4.00)
FLEXAMAT PLUSÒ STEEP
SLOPE STABILIZATION
4.5'
18"x18" ANCHOR TRENCH
C-C
HORIZONTAL SCALE: 1" = 5'
VERTICAL SCALE: 1" = 5'
0+00
3.
3.
0+05
3.
3.
0+10
3.
3.
0+15
1.
1.
0+20
7.
7.
0+25
3.
3.
0+30
1.
1.
0+35
BACK OF
CURB
END OF 10' SLOPE
EASEMENT
EXISTING RIGHT OF WAY/ BEGINNING
OF 10' SLOPE EASEMENT
1.5
7.08'
EDGE OF WATER
1.5'
FLEXAMAT PLUSÒ STEEP
SLOPE STABILIZATION
4.5'
12" MINIMUM DIAMETER RIP RAP
ALONG TOE OF SLOPE (SEE SHEET
C4.00)
18"x18" ANCHOR TRENCH
EXISTING 4" STEEL GAS
LINE (APPROX. DEPTH
& LOCATION; TO BE
CONFIRMED PRIOR TO
CONSTRUCTION)
B-B
HORIZONTAL SCALE: 1" = 5'
VERTICAL SCALE: 1" = 5'
0+00
3.
3.
0+05
3.
3.
0+10
3.
3.
0+15
9.
9.
0+20
5.
5.
0+25
3.
3.
0+30
1.
1.
0+35
BACK OF
CURB
END OF 10' SLOPE
EASEMENT
EXISTING RIGHT OF WAY/ BEGINNING
OF 10' SLOPE EASEMENT
7.38'
1.5
EDGE OF WATER
1.5'
2.74'
FLEXAMAT PLUSÒ STEEP
SLOPE STABILIZATION
12" MINIMUM DIAMETER RIP RAP
ALONG TOE OF SLOPE (SEE SHEET
C4.00)
4.5'
18"x18" ANCHOR TRENCH
EXISTING 4" STEEL
GAS LINE (APPROX.
3.0' DEPTH; TO BE
CONFIRMED PRIOR
TO CONSTRUCTION)
D-D
HORIZONTAL SCALE: 1" = 5'
VERTICAL SCALE: 1" = 5'
0+00
3.
3.
0+05
3.
3.
0+10
2.
2.
0+15
0.
0.
0+20
7.
7.
0+25
3.
3.
0+30 0+35
BACK OF
CURB
END OF 10' SLOPE
EASEMENT
EXISTING RIGHT OF WAY/ BEGINNING
OF 10' SLOPE EASEMENT
1.5
EDGE OF WATER
8.62'
1.5'
FLEXAMAT PLUSÒ STEEP
SLOPE STABILIZATION
12" MINIMUM DIAMETER RIP RAP
ALONG TOE OF SLOPE (SEE SHEET
C4.00)
4.5'
18"x18" ANCHOR TRENCH
EXISTING 4" STEEL GAS
LINE (APPROX. DEPTH
& LOCATION; TO BE
CONFIRMED PRIOR TO
CONSTRUCTION)
R
Knowwhat'sbelow.
Callbefore you dig.
www.Georgia811.com
N/A
21318.00 02/04/2022
J:
\2
1\
0\
D e\
_P la ns he et s\
C 2.
G R
A D
IN
G
P
LA
N
0.
dw g
- C Te st a
- 8 /1
/2
:1
A M
AT
P: (770) 451-2741
350 RESEARCH COURT STE 200
PEACHTREE CORNERS, GA 30092
F: (770) 451-3915
WWW.PEC.PLUS
Planners & Engineers Collaborative+
LAND PLANNING
SURVEYING & CONSTRUCTION
CIVIL ENGINEERING
ARBORISTS
LANDSCAPE ARCHITECTURE
WATER RESOURCES+ +
2 3 4 5 6 7 8 9 10 11 12 13 14 151
K
J
I
H
G
F
E
D
C
B
A
2 3 4 5 6 7 8 9 10 11 12 13 14 151
SCALE:
DATE:
PROJECT:
DESCRIPTIONNO. BYDATE
GEORGIA WEST ZONE
GRID NORTH
SHEET
REVISIONS
c Th is d ra w in g is th e pr op er ty o f P la nn er s an d En gi ne er s
C ol la bo ra tiv e an d is n ot to b e co pi ed in w ho le o r i n pa rt.
It is n ot to b e us ed o n an y ot he r p ro je ct a nd is to b e re tu rn ed u po n re qu nn er s an d En gi ne er s
C ol la bo ra tiv e.
FOR
PROJECT
CITY COMMENTS1 CT05-06-22
CITY OF SANDY SPRINGS
1 GALAMBOS WAY
SANDY SPRINGS, GA 30328
P: (770) 730-5600
LONG ISLAND DRIVE
STREAMBANK
STABILIZATION
WR#21-030596
5375 LONG ISLAND DRIVE
SANDY SPRINGS, GA 30327
CITY COMMENTS2 CT05-24-22
GSWCC LEVEL II DESIGN PROFESSIONAL
CERTIFICATION # 0000067548 EXP. 12/21/2024
THIS SEAL IS ONLY VALID IF COUNTER SIGNED
AND DATED WITH AN ORIGINAL SIGNATURE.
7/29/2022
CITY COMMENTS3 CT05-27-22
CITY COMMENTS4 CT06-16-22
CITY COMMENTS5 CT07-29-22
C2.20
PROFILES
EXISTING GRADE
PROPOSED GRADE
LEGEND:
PERMITTED
09/22/2022
BUILDING PERMIT
SANDY SPRINGS, GA. COMMUNITY DEVELOPMENT DEPARTMENT
THESE PLANS WERE REVIEWED WITH RESPECT TO BUILDING CODES ONLY. NO EFFORT WAS MADE TO
CHECK THE ELECTRICAL, PLUMBING, MECHANICAL OR STRUCTURAL DESIGN OTHER THAN TO
COMPARE THE SUBMITTED PLANS WITH THE APPLICABLE BUILDING CODES. STRUCTURAL REVIEW ALSO CONSIDERED APPLICABILITY OF A SPECIAL INSPECTIONS PROGRAM. STRUCTURAL INTEGRITY IS THE TOTAL RESPONSIBILITY OF THE OWNER AND THE OWNER'S AGENTS. THIS BUILDING PERMIT IS
GL
EN
E
RR
OL
RO
AD
N W
(VARIABLE R/W)
LONG ISLAND DRIVE
TEMPORARY CONSTRUCTION
EASEMENT
Sd2-PSd2-P
Co
Ds1 Du
Ds2
SLOPE EASEMENT
X
X X X X X X X
Skd1
COIR LOGS TO BE PLACED
ALONG EDGE OF WATER
COIR LOGS
LO
D
/ TPF
LOD / TPF
LOD / TPF
LOD
LODLODLODLOD
LOD
LO
D
LODLODLODLOD
LO
D
LOD LOD LOD
LOD
LOD LOD LOD LOD LOD LOD LOD LOD LOD LOD
SILT FENCE TYPE S
CONSTRUCTION
ENTRANCE/EXIT
LAT: N33.902293
LONG: W84.396502
EXISTING RIGHT
OF WAY
EXISTING ROAD
STRIPING
GL
EN
E
RR
OL
RO
AD
N W
(VARIABLE R/W)
LONG ISLAND DRIVE
TEMPORARY CONSTRUCTION
EASEMENT
Sd2-PSd2-P
Co
Ds1 Du
Ds2
Ss Ss
SLOPE EASEMENT
X
X X X X X X X
Skd1
COIR LOGS TO BE PLACED
ALONG EDGE OF WATER
COIR LOGS
LO
D
/ TPF
LOD / TPF
LOD / TPF
LOD
LODLODLODLOD
LOD
LO
D
LODLODLODLOD
LO
D
LOD LOD LOD
LOD
LOD LOD LOD LOD LOD LOD LOD LOD LOD LOD
SILT FENCE TYPE S
CONSTRUCTION
ENTRANCE/EXIT
LAT: N33.902293
LONG: W84.396502
EXISTING RIGHT
OF WAY
EXISTING ROAD
STRIPING
GL
EN
E
RR
OL
(VARIABLE R/W)
LONG ISLAND DRIVE
SLOPE EASEMENT
Ds3Ds3
Sb
FLEXAMAT PLUSÒ STEEP SLOPE STABILIZATION
(SEE DETAIL SHEET C4.00)
EXISTING RIGHT
OF WAY
EXISTING ROAD
STRIPING
Sb STREAMBANK STABILIZATION (WITH
PERMANENT VEGETATION)
THE EXISTING SOILS ON SITE CONSIST OF:
CaA - Cartecay-Toccoa complex, 0-2% slopes, occasionally flooded
SOILS INFORMATION
THERE ARE KNOWN STATE WATERS ON THE PROPERTY
THERE ARE IMPAIRED STREAMS WITHIN ONE MILE DOWNSTREAM
AND WITHIN THE SAME WATERSHED AS THE PROJECT SITE
THERE ARE NO KNOWN WETLANDS ON THE PROJECT SITE
24 HOUR CONTACT:
CITY OF SANDY
SPRINGS
770-730-5600
Sd1
R
Knowwhat'sbelow.
Callbefore you dig.
www.Georgia811.com
1" = 20'
10 20 40 600
C3.10
EROSION CONTROL
PLANS
Ss
DISTURBED AREA STABILIZATION
(WITH MULCHING ONLY)
DUST CONTROL ON
DISTURBED AREADu
Ds1
ES&PC LEGEND
DISTURBED AREA STABILIZATION
(WITH PERMANENT VEGETATION)Ds3
VEGETATIVE BEST MANAGEMENT PRACTICES
STRUCTURAL BEST MANAGEMENT PRACTICES
SLOPE STABILIZATION
CURB INLET
SEDIMENT
FILTER
DISTURBED AREA STABILIZATION
(WITH TEMPORARY SEEDING)Ds2
Sd2-P
LIMITS OF DISTURBANCE
SILT FENCEX
LOD
Sd1-S
TRAFFIC CONTROL NOTES:
1. CONTRACTOR SHALL PROVIDE TRAFFIC CONTROL IN
ACCORDANCE WITH MUTCD REQUIREMENTS.
2. IF A ROAD CLOSURE IS NECESSARY, CONTRACTOR SHALL
PROVIDE A DETOUR PLAN.
3. DURING CONSTRUCTION, ONE LANE OF ROAD SHALL REMAIN
OPEN AT ALL TIMES UNLESS OTHERWISE APPROVED.
4. THE CONTRACTOR SHALL FURNISH AND MAINTAIN ALL
NECESSARY BARRICADES WHILE ROADWAY FRONTAGE
IMPROVEMENTS ARE BEING MADE.
EROSION CONTROL NOTES:
1. ALL SILT FENCE AND/OR TREE PROTECTION FENCE SHALL BE
REMOVED FOLLOWING FINAL STABILIZATION.
2. NO EQUIPMENT SHALL BE STAGED OUTSIDE OF ROAD
SHOULDER OR IN RIGHT-OF-WAY WITHOUT THE REQUIRED
TRAFFIC CONTROL MEASURES IN PLACE.
3. PRIOR TO ANY OTHER CONSTRUCTION, A STABILIZED
CONSTRUCTION ENTRANCE SHALL BE CONSTRUCTED AT
EACH ENTRY TO OR EXIT FROM THE SITE.
4. THE CONSTRUCTION EXITS SHALL BE MAINTAINED IN A
CONDITION WHICH WILL PREVENT TRACKING OR FLOW OF
MUD ONTO PUBLIC RIGHT-OF-WAY. THIS MAY REQUIRE
PERIODIC TOP DRESSING WITH STONE, AS CONDITIONS
DEMAND, AND REPAIR AND/OR CLEANOUT OF ANY
STRUCTURES USED TO TRAP SEDIMENT. ALL MATERIALS
SPILLED, DROPPED, WASHED, OR TRACKED FROM VEHICLE
ONTO PUBLIC ROADWAY OR INTO STORM DRAIN MUST BE
REMOVED.
5. PRIOR TO COMMENCING LAND DISTURBANCE ACTIVITY THE
LIMITS OF LAND DISTURBANCE SHALL BE CLEARLY AND
ACCURATELY DEMARCATED WITH STAKES, RIBBONS, OR
OTHER APPROPRIATE MEANS. THE LOCATION AND EXTENT
OF ALL AUTHORIZED LAND DISTURBANCE SHALL OCCUR
WITHIN THE APPROVED LIMITS INDICATED ON THE
APPROVED PLANS.
6. THE CONSTRUCTION OF THE SITE WILL INITIATE WITH THE
INSTALLATION OF EROSION CONTROL MEASURES
SUFFICIENT TO CONTROL SEDIMENT DEPOSITS AND
EROSION. ALL SEDIMENT CONTROL WILL BE MAINTAINED
UNTIL ALL UP STREAM GROUND WITHIN THE CONSTRUCTION
AREA HAS BEEN COMPLETELY STABILIZED WITH PERMANENT
VEGETATION AND ALL ROADS/DRIVEWAYS HAVE BEEN
PAVED.
7. FAILURE TO INSTALL, OPERATE OR MAINTAIN ALL EROSION
CONTROL MEASURES WILL RESULT IN ALL CONSTRUCTION
BEING STOPPED ON THE JOB SITE UNTIL SUCH MEASURES
ARE CORRECTED BACK TO CITY OF SANDY SPRINGS
STANDARDS.
8. A COPY OF THE APPROVED LAND DISTURBANCE PLAN &
PERMIT SHALL BE PRESENT ON THE SITE WHENEVER LAND
DISTURBANCE ACTIVITY IS IN PROGRESS.
9. ALL SEWER EASEMENTS DISTURBED MUST BE DRESSED
AND GRASSED TO CONTROL EROSION.
LIMITS OF DISTURBANCE /
TREE PROTECTION FENCELOD / TPF
TOTAL DISTURBED AREA: 0.23 ACRES
21318.00 02/04/2022
J:
\2
1\
0\
D e\
_P la ns he et s\
C 3.
E R
O S
IO
N
C O
N
TR
O L
P
LA
N
0.
dw g
- C Te st a
- 8 /1
/2
:1
A M
AT
P: (770) 451-2741
350 RESEARCH COURT STE 200
PEACHTREE CORNERS, GA 30092
F: (770) 451-3915
WWW.PEC.PLUS
Planners & Engineers Collaborative+
LAND PLANNING
SURVEYING & CONSTRUCTION
CIVIL ENGINEERING
ARBORISTS
LANDSCAPE ARCHITECTURE
WATER RESOURCES+ +
2 3 4 5 6 7 8 9 10 11 12 13 14 151
K
J
I
H
G
F
E
D
C
B
A
2 3 4 5 6 7 8 9 10 11 12 13 14 151
SCALE:
DATE:
PROJECT:
DESCRIPTIONNO. BYDATE
GEORGIA WEST ZONE
GRID NORTH
SHEET
REVISIONS
c Th is d ra w in g is th e pr op er ty o f P la nn er s an d En gi ne er s
C ol la bo ra tiv e an d is n ot to b e co pi ed in w ho le o r i n pa rt.
It is n ot to b e us ed o n an y ot he r p ro je ct a nd is to b e re tu rn ed u po n re qu nn er s an d En gi ne er s
C ol la bo ra tiv e.
FOR
PROJECT
CITY COMMENTS1 CT05-06-22
CITY OF SANDY SPRINGS
1 GALAMBOS WAY
SANDY SPRINGS, GA 30328
P: (770) 730-5600
LONG ISLAND DRIVE
STREAMBANK
STABILIZATION
WR#21-030596
5375 LONG ISLAND DRIVE
SANDY SPRINGS, GA 30327
CITY COMMENTS2 CT05-24-22
GSWCC LEVEL II DESIGN PROFESSIONAL
CERTIFICATION # 0000067548 EXP. 12/21/2024
THIS SEAL IS ONLY VALID IF COUNTER SIGNED
AND DATED WITH AN ORIGINAL SIGNATURE.
7/29/2022
CITY COMMENTS3 CT05-27-22
CITY COMMENTS4 CT06-16-22
CITY COMMENTS5 CT07-29-22
INITIAL EROSION & SEDIMENT CONTROL PLAN
SCALE: 1" = 20'
FINAL EROSION & SEDIMENT CONTROL PLAN
SCALE: 1" = 20'
INTERMEDIATE EROSION & SEDIMENT CONTROL PLAN
SCALE: 1" = 20'
COIR LOG
C4.00
C4.00
PERMITTED
09/22/2022
BUILDING PERMIT
SANDY SPRINGS, GA. COMMUNITY DEVELOPMENT DEPARTMENT
THESE PLANS WERE REVIEWED WITH RESPECT TO BUILDING CODES ONLY. NO EFFORT WAS MADE TO
CHECK THE ELECTRICAL, PLUMBING, MECHANICAL OR STRUCTURAL DESIGN OTHER THAN TO
COMPARE THE SUBMITTED PLANS WITH THE APPLICABLE BUILDING CODES. STRUCTURAL REVIEW ALSO CONSIDERED APPLICABILITY OF A SPECIAL INSPECTIONS PROGRAM. STRUCTURAL INTEGRITY IS THE TOTAL RESPONSIBILITY OF THE OWNER AND THE OWNER'S AGENTS. THIS BUILDING PERMIT IS
DEFINITION
The establishment of temporary vegetative cover with fast growing seedings for seasonal protection on disturbed or denuded areas.
CONDITIONS
Temporary grassing, instead of mulch, can be applied to rough graded areas that will be exposed for less than six months. Temporary vegetative measures should be coordinated with permanent measures to assure economical and effective stabilization. Most types of temporary vegetation are ideal to use as companion crops until the permanent vegetation is established.
SEEDING RATES FOR
TEMPORARY SEEDING
* Unusual site conditions may require heavier seeding rates.
** Seeding dates may need to be altered to fit temperature variations and conditions.
SPECIFICATIONS
GRADING AND SHAPING
Excessive water run-off shall be reduced by properly designed and installed erosion control practices such as closed drains, ditches, dikes, diversions, sediment barriers and others.
SEEDBED PREPARATION
When a hydraulic seeder is used, seedbed preparation is not required. When using conventional or handseeding, seedbed preparation is not required if the soil material is loose and not sealed by rainfall.
When soil has been sealed by rainfall or consists of smooth cut slopes, the soil shall be pitted, trenched or otherwise scarified to provide a place for seed to lodge and germinate.
LIME AND FERTILIZER
Agricultural lime is required unless soil tests indicate otherwise. Apply agricultural lime at a rate of one ton per acre. Graded areas require lime application. Soils can be tested to determine if fertilizer is needed. On reasonably fertile soils or soil material, fertilizer is not required. For soils with very low fertility, 500 to 700 pounds of 10-10-10 fertilizer or the equivalent per acre (12-16 lbs./1,000 sq. ft.)
shall be applied. Fertilizer should be applied before land preparation and incorporated with a disk, ripper or chisel.
SEEDING
Select a grass or grass-legume mixture suitable to the area and season of the year. Seed shall be applied uniformly by hand, cyclone seeder, drill, cultipacker seeder, or hydraulic seeder (slurry including seed and fertilizer). Drill or cultipacker seeders should normally place seed one-quarter to one-half inch deep. Appropriate depth of planting is ten times the seed diameter. Soil should be "raked" lightly to cover seed with soil if seeded by hand.
MULCHING
Temporary vegetation can, in most places, be established without the use of mulch. Mulch without seeding should be considered for short term protection.
Refer to Ds1 - Disturbed Area Stabilization (With Mulching Only).
IRRIGATION
During times of drought, water shall be applied at a rate not causing runoff and erosion. The soil shall be thoroughly wetted to a depth that will ensure germination of the seed. Subsequent applications should be made when needed.
Ds2 DISTURBED AREA STABILIZATION
(WITH TEMPORARY SEEDING)
SPECIES
RATE Per 1,000 sq.ft.
RATE Per Acre*
PLANTING
DATES**
Rye 3.9 pounds 3 bu. 9/15-11/30
Ryegrass 0.9 pounds 40 lbs. 9/1-12/15
Annual Lespedeza
0.9 pounds 40 lbs. 3/1-3/31
Weeping Lovegrass
0.1 pounds 4 lbs. 4/1-5/31
Sudangrass 1.4 pounds 60 lbs. 5/1-7/31
Browntop Millet
0.9 pounds 40 lbs. 4/15-6/30
Wheat 4.1 pounds 3bu. 10/1-12/15
DEFINITION
The planting of perennial vegetation such as trees, shrubs, vines, grasses, or legumes on exposed areas for final permanent stabilization. Permanent perennial vegetation shall be used to achieve final stabilization.
CONDITIONS
Permanent perennial vegetation is used to provide a protective cover for exposed areas including cuts, fills, dams, and other denuded areas.
SPECIFICATIONS
GRADING AND SHAPING
Grading and shaping may not be required where hydraulic seeding and fertilizing equipment is to be used. Vertical banks shall be sloped to enable plant establishment.
When conventional seeding and fertilizing are to be done, grade and shape where feasible and practical, so that equipment can be used safely and efficiently during seedbed preparation, seeding, mulching and maintenance of the vegetation.
Concentrations of water that will cause excessive soil erosion shall be diverted to a safe outlet. Diversions and other treatment practices shall conform with the appropriate standards and specifications.
LIME APPLICATION RATES
Agricultural lime is required at the rate of one to two tons per acre unless soil tests indicate otherwise. Graded areas require lime application. If lime is applied within six months of planting permanent perennial vegetation, additional lime is not required. Agricultural lime shall be within the specifications of the Georgia Department of Agriculture.
SEEDBED PREPARATION
Seedbed preparation may not be required where hydraulic seeding and fertilizing equipment is to be used. When conventional seeding is to be used, seedbed preparation will be done as follows:
I. Broadcast plantings
1. Tillage at a minimum, shall adequately loosen the soil to a depth of 4 to 6 inches; alleviate compaction; incorporate lime and fertilizer; smooth and firm the anchoring of soil; allow for the proper placement of seed, sprigs, or plants; and allow for the anchoring of straw or hay mulch if a disk is to be used.
2. Tillage may be done with any suitable equipment.
3. Tillage should be done on the contour where feasible.
4. On slopes too steep for the safe operations of tillage equipment, the soil surface shall be pitter or trenched across the slope with appropriate hand tools to provide two places 6 to 8 inches apart in which seed may lodge and germinate. Hydraulic seeding may also be used.
II. Individual Plants
1. Where individual plants are to be set, the soil shall be prepared by excavating holes, opening furrows, or dibble planting.
2. For nursery stock plants, holes shall be large enough to accommodate roots without crowding.
3. Where pine seedlings are to be planted, subsoil under the row 36 inches deep on the contour four to six months prior to planting. Subsoiling should be done when the soil is dry, preferably in August or September
PLANTING
I. Hydraulic Seeding
Mix the seed (innoculated if needed), fertilizer, and wood cellulose or wood pulp fiber mulch with water and apply in a slurry uniformly over the area to be treated.
Apply within one hour after the mixture is made.
II. Conventional Seeding
Seeding will be done on a freshly prepared and firmed seedbed. For broadcast planting, use a cultipacker seeder, drill, rotary seeder, other mechanical seeder, or hand seeding to distribute the seed uniformly over the area to be treated.
Cover the seed lightly with 1/8 to 1/4 inch of soil for small seed and 1/2 to 1 inch for large seed when using a…
This is the start of the file's text. The full file is on GovTribe.
Other files
| File | Type | Posted |
|---|---|---|
| 23-038 PROPANE | — | |
| Award Information | — | |
| Award Information | — | |
| RFP #23-038 Scope & Specs. | — | |
| 23-038 DO CO Scale Invitation | — | |
| RFP #23-038 Plans | — | |
| ITB 23-038 | — |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
File details come from the government source that posted it. Updated .