Appendix G - Points of Demarcation.docx
DOCX document 26 KB Posted
- Attached to
- Navy Nuclear Power Training Command (NNPTC) Facility Preventative Maintenance, Inspection, & Repairs
- Solicitation number
- Not on record
About this file
This document is an Appendix G that outlines the points of demarcation for maintenance and repairs of water lines, sewage mains, and low voltage lines at the Navy Nuclear Power Training Command (NNPTC) facility located on Joint Base Charleston-Weapon Station (JBC-WS) in Goose Creek, South Carolina.
The contractor is responsible for maintenance and repairs of exterior water supply lines from the shutoff valve to the building or five feet from the building if no valve exists. The Base Civil Engineer (BCE) is responsible for water supply from the shutoff valve or five feet from the building to the source main. The contractor is responsible for maintenance and repairs of sewage mains from the building clean-out to the building or five feet from the building if no clean-out exists, while the BCE is responsible from the clean-out to the sewer main or five feet from the building. The contractor is responsible for the main distribution breaker(s) and all components downstream of the high voltage lines.
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Appendix G – Points of Demarcation
The Contractor shall be responsible for maintenance and repairs of exterior water lines as follows:
· Water supply lines from the shutoff valve to the building or five feet from the building if no valve exist, will be the responsibility of the Contractor.
· Water supply from the shut off valve or five feet from the building to the source main will be the responsibility of the Base Civil Engineer (BCE).
· If no shut off valve exist, the BCE will assist with isolation and the five foot rule will take effect.
Responsibility for maintenance and repairs of sewage mains are as follows:
· From the building clean-out to the building or five feet from the building if no clean-out exist, will be the responsibility of the contractor.
· From the clean-out to the sewer main or five feet from the building if no clean-out exist, will the responsibility of the BCE
Responsibility for maintenance and repairs of Low Voltage Lines are as follows:
· High Voltage Lines will end at the primary side of the main distribution breaker(s).
· The contractor shall be responsible for the main distribution breaker(s) and all components downstream.