Appendix F is a comprehensive safety requirements and deliverables document for the Ames National Laboratory Fire Alarm Replacement Phase 2 project. The document outlines critical safety protocols and expectations for contractors and subcontractors, including specific requirements for managing potential hazardous material exposures such as mercury, asbestos, beryllium, lead, and radiation, with mandatory notification procedures if unidentified materials are discovered during work.
Key safety provisions include compliance with DOE Worker Protection Plan, industrial hygiene monitoring, documentation requirements, personal protective equipment (PPE) standards, electrical work guidelines, and specific exposure limits for crystalline silica and noise levels. Contractors must complete a Subcontractor Affirmation Form, adhere to strict safety practices for wall/ceiling/floor penetrations, use proper lockout/tagout procedures, and ensure daily equipment inspections. The document emphasizes the subcontractor's responsibility to communicate and enforce safety regulations across all tiers of work personnel.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Ames National Laboratory Fire Alarm Replacement Phase 2
Appendix F - Safety Requirements and Deliverables
This appendix is not intended to be a comprehensive list. Additional documentation and requirements may arise as the project progresses.
1. Per DOE policy, CFR 851 Worker Protection Plan, Ames Laboratory contractors and subcontractors must demonstrate compliance with ACGIH TLVs, typically by industrial hygiene monitoring or objective third-party data.
2. All documentation must be available to Ames Laboratory upon request including, but not limited to: training records, medical clearance, SOPs, and SDSs shall be provided in conjunction with the hazard evaluation and hazard management statements.
3. Copies of SDS for all chemicals, compounds, coatings, paints, etc. which will be brought on-site must be submitted in conjunction with the hazard evaluation documentation, or as soon as it is determined it will be used.
4. Contractors may encounter mercury compounds while working in laboratory space, elemental mercury when removing drain traps, or mercury vapor via broken fluorescent lamps.
5. Subcontractors are not to access interstitial spaces due to potential contamination unless approved by Ames
National Laboratory ESH. (Beryllium, Radiological, Asbestos, etc. concerns)
6. Asbestos hazards or Potential Asbestos Containing Materials (PACM) will be identified by Ames National
Laboratory. If asbestos is positively identified, or is a PACM that could not be tested, a mitigation plan will be developed by subcontractor and Ames National Laboratory.
a. If unidentified material is discovered while work is being performed, Ames National Laboratory ESH should be notified immediately.
7. Beryllium hazards will be identified by Ames National Laboratory. If Beryllium contamination is positively identified, a mitigation plan will be developed by subcontractor and Ames National Laboratory.
a. If unidentified material is discovered while work is being performed, Ames National Laboratory ESH should be notified immediately.
8. Lead hazards will be identified by Ames National Laboratory. If Lead contamination is positively identified, a mitigation plan will be developed by subcontractor and Ames National Laboratory.
a. If unidentified material is discovered while work is being performed, Ames National Laboratory ESH should be notified immediately.
9. Radiation hazards will be identified by Ames National Laboratory. If Radiation contamination is positively identified, a mitigation plan will be developed by subcontractor and Ames National Laboratory.
a. If unidentified material is discovered while work is being performed, Ames National Laboratory ESH should be notified immediately.
10. Crystalline Silica Exposures- Note that the Department of Energy requires that their contractors comply with the ACGIH TLV-TWA for respirable crystalline silica (RCS) as the exposure limit. This is a more stringent standard than the OSHA PEL (TLV=0.025 mg/m3 RCS; PEL=0.050 mg/m3 RCS).
a. Work pause and the reassessment of work practices and personal protection with the Industrial
Hygiene department are required if visible dust is observed in an operation.
b. Nuisance dust may be generated during work activities, if visible dust is observed, a reassessment of work practices and personal protection by Ames National Laboratory is required.
11. Activities that produce noise above 85 dBA using ACGIH standards shall be accounted for using engineering control, or using PPE such as earplugs, earmuffs or a combination of.
12. Subcontractor Affirmation Form needs to be completed and signed by all subcontractor’s and sub-tier subcontractor’s company representatives to acknowledge that all rules and regulations listed in the Terms and
Conditions, along with any other safety related documents and or conversations, are being communicated and adhered to through all tiers of subcontractors. It is the responsibility of the subcontractor awarded the contract to make sure all sub-tier subcontractors are following all rules and regulations at all times, and enforce proper escalation protocols if rules and regulations are not being followed.
13. All construction debris will be surveyed before being removed from work area.
14. Electrical work must be performed, per NFPA 70E, only by qualified and approved electrical workers, with approved equipment and PPE, using the electrical safe work practices.
a. An electrical assessment and work plan must be reviewed by AHJ before work can be performed.
15. Wall/ceiling/floor penetrations necessitate a review of historical records, engineering plans, and as-built drawings that pertain to the area/location where the penetration is planned.
a. Failure to understand what may lie behind a penetration may lead to contact and exposure to hazardous materials, electrical and other utilities. Contact may result in serious injury, death and/or property damage.
b. Non-destructive scanning should be performed.
c. All drilling or cutting work should use double insulated tools and wear appropriate insulating gloves in the event a hidden live feed is encountered
16. Application of a mechanical lockout device and a tag on an energy isolation by a LOTO authorized person in accordance with established procedures to control hazardous energies and prevent the equipment from being operated until the lockout device is removed.
17. All ladder usage will comply with 29 CFR 1910.23 or 29 CFR 1926.1053 as applicable.
a. All ladders will be visually inspected daily prior to use.
18. Standard PPE must be worn by persons performing or assisting with performing the work. This includes but is not limited to safety glasses with side shields/safety goggles and hard hats where overhead hazards exist.
a. Additional PPE may be required depending on hazard and mitigation requirements.