Appendix E - SC622PerfBond (DNR) (1).docx
DOCX document 18 KB Posted
- Attached to
- Carpios Ridge Restroom Replacement - C26TR1
- Solicitation number
- IFB1 PMAA 2027000010 1
- Issued by
- El Paso County, Colorado Springs City, Colorado
About this file
This is a Performance Bond document issued by the State of Colorado Office of the State Architect State Buildings Program for the Carpios Ridge Restroom Replacement project (C26TR1) in Colorado. The bond establishes a contractual obligation between the contractor (Principal), surety bonding company, and the State of Colorado to ensure faithful performance of construction work. The bond is conditioned upon the Principal's prompt and complete performance of all contract undertakings, covenants, terms, conditions, and agreements during the original contract term, any authorized extensions, and the life of any required guaranties. The document specifies that the Principal and Surety are jointly and severally liable for the bond amount, with interest accruing at eight percent per annum on all payments due under the contract from the time payments become due until made.
The bond establishes that if the Principal defaults on the contract, the Surety may either remedy the default, complete the contract in accordance with its terms and conditions, or obtain and submit bids for contract completion to the State of Colorado. The Surety must make available sufficient funds to pay completion costs, less the remaining balance of the contract price but not exceeding the bond amount set forth in the document. The bond amount, contract execution date, contractor name, bonding company name, and institution/agency details are to be completed by the Institution/Agency upon contract execution. This Performance Bond must be accompanied by a Power of Attorney effectively dated and is issued simultaneously with a payment bond covering all labor and material costs under the contract. The bond references State Form SC-6.22 (Revision 9/2006) and requires corporate seals and proper execution by both the Principal and Surety's attorney-in-fact.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| BID DOCUMENTS C26TR1.pdf | ||
| Appendix A - Drawings Bid Set.pdf | ||
| Appendix D - Sample State Bid Bond Form.docx | DOCX document | |
| Appendix B - 2018 CPW GCs 071818 FINAL.pdf | ||
| Appendix F - SC6221LMBond (1).docx | DOCX document | |
| Appendix C - Sample Construction Agreement (June 2024) .docx.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATE OF COLORADO
OFFICE OF THE STATE ARCHITECT
STATE BUILDINGS PROGRAM
PERFORMANCE BOND
Institution/Agency:
Project No./Name:
BONDING COMPANY: DO NOT MAKE ANY CHANGES TO THE LANGUAGE IN THIS BOND.
KNOW ALL PERSONS BY THESE PRESENTS:
That the Contractor:
as Principal and hereinafter called “Principal,” and:
as Surety and hereinafter called "Surety," a corporation organized and existing under the laws of are held and firmly bound unto the STATE OF COLORADO acting by and through the Institution/Agency identified above hereinafter called "Principal Representative," and to all subcontractors and any others who have supplied or furnished or shall supply or furnish materials, rental machinery, tools, or equipment actually used in the performance of the hereinafter identified Contract, or who have performed or shall perform labor in the performance of or in connection with said Contract, hereinafter called "Obligees" in the sum of:
| Dollars ($ | ) | |
| (Written Amount) | (Numerical Amount) |
together with interest at the rate of eight per cent (8%) per annum on all payments becoming due in accordance with said Contract, from the time such payments shall become due until such payment shall be made, for the payment of which, well and truly made to the Obligees, the Principal and the Surety bind themselves, their heirs, executors, administrators, successors and assigns, jointly and severally, firmly, by these presents.
WHEREAS, the Principal and the State of Colorado acting by and through the Principal Representative have entered into a certain Contract, hereinafter called "Contract," dated for the construction of the (Leave blank, to be completed by Institution/Agency upon Contract execution)
PROJECT identified above, which Contract is hereby by reference made a part hereof;
NOW, THEREFORE, THE CONDITION OF THIS OBLIGATION, is such that, if the Principal shall promptly, fully and faithfully perform all the undertakings, covenants, terms, conditions and agreements of said Contract during the original term of said Contract any extensions thereof that may be granted by the Principal Representative with or without notice to the Surety, and during the life of any guaranty required under the Contract, and shall also well and truly perform and fulfill all undertakings, covenants, terms, conditions and agreements of any and all duly authorized modifications of said Contract that may hereafter be made, notice of which modifications to the Surety being hereby waived, then this obligation shall be null and void; otherwise it shall remain in full force and effect.
AND THE SAID SURETY, for value received hereby stipulates and agrees that whenever the Principal shall be, and declared by the Principal Representative to be in default under said Contract, the State of Colorado having performed its obligations thereunder, the Surety may promptly remedy the default or shall promptly (1) Complete the Contract in accordance with its terms and conditions, or (2) Obtain a bid or bids for submittal to the Principal Representative for completing the Contract in accordance with its terms and conditions, and upon determination by the Principal Representative and Surety of the lowest responsible bidder, arrange for a contract between such bidder and the State of Colorado acting by and through the Principal Representative and make available as work progresses (even though there should be a default or a succession of defaults under the contract or contracts of completion arranged under this paragraph) sufficient funds to pay the cost of completion, less the balance of the contract price but not exceeding, including other costs and damages for which the Surety may be liable hereunder, the amount hereinbefore set forth. The term “balance of the contract price” as herein used shall mean the total amount payable to the Principal under the Contract and any amendments thereto, less the amount properly paid by the State of Colorado to the Contractor.
No right of action shall accrue on this bond to or for the use of any person or corporation other than the State of Colorado.
IN WITNESS WHEREOF said Principal and Surety have executed this Bond, on
(If left blank, the Institution/Agency will date this bond to match the Contract Execution date)
(Corporate Seal)
THE PRINCIPAL
ATTEST:
By:
Title:
Secretary
(Corporate Seal)
SURETY
By:
Attorney-in-fact
THIS BOND MUST BE ACCOMPANIED BY POWER OF ATTORNEY, EFFECTIVELY DATED
| Note: |
| This bond is issued simultaneously with another bond conditioned for the full and faithful payment for all labor and material of the contract. |
State Form SC-6.22 Page of (Rev. 9/2006) image1.png image3.png image2.png
File details come from the government source that posted it. Updated .