Appendix E - Government Provided Data to be Used in Pro Forma Final 6Aug2025.pdf

PDF 149 KB Posted

Attached to
Commercial On-Base Lodging (COBL) RFP AFCOBL-25-0001
Solicitation number
AFCOBL-24-0001
Issued by

About this file

This document is Appendix E of the Commercial On-Base Lodging (COBL) solicitation, providing standardized financial assumptions for offerors to use in their pro forma financial models. The appendix details specific requirements for mortgage terms, including a 30-year mortgage with a 10-year interest-only period, an 8.00% all-in interest rate, and a 1.75x debt service coverage ratio. It also specifies reserve account funding, such as a Project and Hotel Operating Disbursement Account, Impositions Reserves Account, and Extraordinary Expense Account, with a transfer date of 1 Aug 2027 and an annual inflation rate of 2.5%.

The document further outlines hotel operating expense assumptions, including 5% reserves for replacement, $700 PAR insurance expenses, and specific utility and real estate tax costs for 23 Air Force installations. Additional financial guidelines include $4.0 million in additional rent per fiscal year, $350,000 site work per new hotel, $600,000 annual DTS GDS charges, and $10 PAR for firefighting and police protection services. The appendix also includes a table of recently completed on-base lodging construction projects, noting that construction costs are typically higher due to Davis-Bacon wages, Anti-Terrorism requirements, base access restrictions, and government oversight.

View the file

Other files

Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation No. AFCOBL-25-0001 E-1

APPENDIX E

GOVERNMENT PROVIDED DATA TO BE USED IN PRO FORMA

The Government is requiring that each Offeror use standardized assumptions for key pro forma inputs. This is intended to limit overly aggressive assumptions in select areas. All assumptions below are strictly for the purposes of this solicitation. Unless otherwise stated, dollar amounts cited are in base year FY27.

With respect to the private mortgage, Offerors should assume the following:

1. A mortgage term length of 30 years

2. An interest-only period on the mortgage of 10 years

3. An annual debt service coverage ratio of 1.75x sized on the 11th full Fiscal Year of operations with inflation off

4. No debt service reserve account

5. An all-in interest rate of 8.00%

6. No fee on undrawn debt proceeds, debt draws taken down as needed

7. A payment to the lender of 1.75% of the total loan amount payable at closing

8. Transition Costs paid at Closing of $7,000,000

9. Reserve Accounts in the following amounts funded at Closing:

a. Project and Hotel Operating Disbursement Account totaling one sixth of the sum of the pro forma’s FY28 Departmental and Undistributed Operating Expenses

b. Impositions Reserves Account totaling one half the sum of the pro forma’s FY28 Fixed Charges

c. Extraordinary Expense Account of 5% of the pro forma’s FY28 Total Revenue

10. A transfer date of 1 Aug 2027

11. An annual inflation rate of 2.5% for income, expenses and construction costs

12. FY26 Per Diem rates inflated to base year FY27 at 2.5%

13. A toggle to turn off inflation and view the pro forma and all summary tabs in base year dollars

14. No refinancing of the initial mortgage

With respect to hotel operating expenses and reserves, Offeror’s should assume the following:

1. Reserves for replacement of 5% of Total Revenue

2. Insurance expenses of $700 PAR

3. Real Estate & Property Taxes by installation per Table E-1

4. Utility costs by installation per Table E-1

5. Additional Rent per Lease Condition 45.2 (Not including utilities): $4.0 million per

Fiscal Year

6. Site work of $350,000 per new hotel consistent with Section 4.6.2.1 of the RFP

7. No payout of the Variable Incentive Fee Component

Solicitation No. AFCOBL-25-0001 E-2

8. DTS GDS Charges of $600,000 per annum.

9. Reimbursement of both firefighting and fire protection services as well as police protection services of $10 PAR per annum. These costs should be treated by the Offerors as “Security” costs under the Administrative & General expenses.

10. No Service Contract Act (SCA) wage applicability. SCA wage applicability will only be known once the Applicant and the Government determine their mutual approach to contracted demand requirements.

11. No state or federal income taxes on Project Company net operating income.

Table E-1:

Installation Utility Cost PAR Real Estate & Property Taxes Cost PAR

Altus Air Force Base, OK $1,400 $768 Barksdale Air Force Base, LA $1,050 $768 Beale Air Force Base, CA $1,250 $1,384 Buckley Space Force Base, CO $1,100 $719 Davis–Monthan Air Force Base, AZ $1,000 $719 Dobbins Air Reserve Base, GA $1,200 $844 Edwards Air Force Base, CA $1,850 $1,384 Eglin Air Force Base, FL $1,500 $844 Goodfellow Air Force Base, TX $950 $768 Hurlburt Field, FL $1,200 $844 Joint Base Andrews, MD $1,750 $844 Joint Base Charleston, SC $1,050 $844 Joint Base Elmendorf–Richardson, AK $1,500 $1,384 Joint Base McGuire–Dix–Lakehurst, NJ $1,400 $2,272 Little Rock Air Force Base, AR $1,600 $768 MacDill Air Force Base, FL $1,250 $844 Maxwell-Gunter Air Force Base, AL $1,150 $674 Nellis Air Force Base, NV $900 $719 Robins Air Force Base, GA $1,100 $844 Seymour Johnson Air Force Base, NC $1,200 $844 Shaw Air Force Base, SC $1,300 $844 Sheppard Air Force Base, TX $950 $768 Travis Air Force Base CA $1,250 $1,384

The Government will not prescribe the cost per key or cost per square foot of new construction but, in the interest of receiving reasonable proposals, Offerors should note the following recently completed on-base lodging construction projects completed by the Department of the Air Force and their respective costs.

Solicitation No. AFCOBL-25-0001 E-3

Offerors will likely find these costs higher than off-base commercial hotel construction projects. Some of the reasons for the higher cost include Davis-Bacon wages, Anti- Terrorism and Force Protection (including progressive collapse) requirements, additional Unified Facilities Criteria guidelines applicable to government construction, base access restrictions and associated background investigations, limited participation from construction firms and local subcontractors interested in bidding on contracts on military installations, and significant Government oversight and reviews. Many of these factors could similarly impact pricing for commercial hotels constructed on-base by the Lessee.

The Government encourages Offerors to perform due diligence on on-base construction pricing as the Government values proposals that can realistically account for the premium that is associated with construction on military installations.

The aforementioned recent Government lodging construction projects include:

With respect to Construction Management Fees (see Appendix H) earned under Construction Contracts, Offerors should assume, for the purposes of this solicitation, a fee basis equal to Major Work executed under, design costs incurred under, and third-party consulting contracts directly supporting the COBL Construction Contract(s).

Installation Group A (Y/N)

Completion Date Type Rooms Square-

Feet Construction

Cost* FF&E

Beale Air Force Base, CA Y Dec-19 TLF 34 44,191 $16,920,566 $1,376,098 Cannon Air Force Base, NM N Oct-20 TLF 30 38,406 $14,564,088 $1,614,638 Davis–Monthan Air Force Base, AZ Y Dec-20 VQ 262 164,200 $50,840,494 $5,016,500 Eglin Air Force Base, FL Y May-19 TLF 32 44,748 $13,541,822 $1,143,113 Goodfellow Air Force Base, TX Y Feb-20 TLF 10 14,494 $5,269,574 $373,300 Hurlburt Field, FL Y Sep-15 TLF 8 11,895 $2,529,704 $274,396 Joint Base Charleston, SC Y Jul-21 VQ 266 149,210 $64,783,051 $4,159,410 Joint Base Charleston, SC Y Nov-23 TLF 16 22,550 $9,484,647 $1,510,754 Little Rock Air Force Base, AR Y Sep-22 VQ 250 136,332 $51,311,197 $4,727,758 Luke Air Force Base, AZ N Sep-15 TLF 30 42,936 $9,276,339 $868,341 MacDill Air Force Base, FL Y Jan-16 VQ 350 205,752 $48,307,019 $3,099,686 Minot Air Force Base, ND N Jan-17 TLF 30 48,202 $18,251,783 $1,055,545 Nellis Air Force Base, NV Y Jan-21 TLF 40 44,558 $18,305,537 $1,661,088 Scott Air Force Base, IL N Nov-17 VQ 284 171,533 $47,395,480 $3,457,638

* Construction includes construction, contingency and supervision, inspection and overhead (SIOH)

File details come from the government source that posted it. Updated .