This document is a detailed Questions & Answers (Q&A) record from the COBL (Consolidated On-Base Lodging) Industry Forum held on 29 May 2025, covering a comprehensive Department of the Air Force (DAF) lodging privatization initiative. The Q&A addresses multiple critical aspects of the solicitation, including hotel operator requirements, development experiences, financial structures, operational expectations, and transition details. Key highlights include clarifications on minimum experience requirements for hotel management, brand standards, employee transition, construction oversight, insurance expectations, and financial considerations such as replacement reserves and system expenses.
The document provides extensive guidance for potential offerors, addressing complex topics like intra-offeror relationship restrictions, brand and loyalty program flexibility, accounting system usage, and government expectations for hotel operations. Notably, the Air Force seeks a comprehensive proposal that can manage on-base lodging across multiple installations, with flexibility for brand development, technology integration, and meeting specific government lodging needs. The Q&A emphasizes that while there are specific requirements, the government is seeking a best-value proposal that can adapt to unique installation demands while maintaining high operational standards for official and unofficial travelers.
View the file
Other files
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
COBL Industry Forum
29 May 2025
Questions & Answers
Questions Asked During the Industry Forum
1. Question: Does the Air Force option to enter into an agreement with the hotel operator for the non-U.S. lodging apply during Group A and/or Group B, or just during Group B award?
Answer: There are no time limits or restrictions on the ability of the Air Force to exercise any of the options contained in the Group A RFP. The Air Force can choose to offer any of the three options (additional installations (e.g. Group B), non-U.S. lodging operations, and/or unaccompanied housing) to the Group A Lessee/Hotel Operator at any time after the Effective Date of the COBL Lease where the Lessee has demonstrated superb performance.
2. Question: How does permitting for construction work?
Answer: There are installation-specific local approvals required from the local DAF Civil Engineering Office regarding on-base construction. Installation representatives (e.g., engineering, fire department, security, etc.) will participate as needed during project planning efforts, as coordinated through the COBL Program Management Office (PMO).
Specific requirements vary by installation. For installations in concurrent or proprietary jurisdiction, local state and municipal permitting requirements may also apply. Please consult with the local jurisdictions for specific information.
3. Question: How does the 90% per diem cap work?
Answer: Please refer to the RFP Section 1.8 “Lodging Per Diem & COBL Rates” and Condition 24.2 (Room Rate Cap.) of the COBL Lease for detailed explanations and examples of how the 90% per diem cap will work.
4. Question: For the Minimum Experience Requirements (MERs) – is the 10,000 room management requirement set over a 10-year period, or at one moment in time?
Answer: To meet the MERs, the Hotel Operator must manage 10,000 rooms or 100 hotels on the day the Step One submissions for the Request for Proposals (RFP) are due. The hotels must meet the requirements found in the RFP (e.g. Appendix G, direct-managed, etc.) to be counted toward this requirement.
5. Question: Can the same entity serve as both Hotel Operator and Asset Manager if it has internal firewalls?
Answer: No.
6. Question: Are there any limits on subcontracting elements of hotel operations or development beyond the named entities?
Answer: There are no limits on subcontracting, however, the named entity is still ultimately responsible and accountable for the execution of the COBL Lease. In addition, if the Offeror proposes subcontracting elements, the effect of the proposed subcontracting arrangement(s) cannot result in the MERs, or other terms of the RFP or COBL Lease, not being met. Effectively, the team that incorporates any subcontracting elements must still be able to meet the Step One MERs. The scope, complexity, and past experience of the proposed subcontractor relationship(s) will be considered during evaluation of Step Two, Preliminary Project Concept.
7. Question: Will we be provided with occupancy by seasonality (month over month)?
Answer: Yes, detailed occupancy, including by month, will be provided in the Document Room during Step Two.
8. Question: What will be the prioritization in guest stay (official vs non-official)? Are we to expect at the last minute to accommodate Official Travelers?
Answer: Please refer to COBL Lease Conditions 2.3, 24, and 25 and Exhibit K of the COBL Lease for details regarding preferences and incentives to accommodate Official Travelers.
While the Hotel Operator will be allowed to market to Unofficial Travelers, and it is encouraged as a way of maximizing occupancy to rent rooms not otherwise needed by Official Travelers, the Air Force desires that the priority be to accommodate Official Travelers. If an Unofficial Traveler has made a room reservation, there is not a requirement to cancel that reservation to make room for an Official Traveler, except in instances of priority missions or national security requirements in accordance with the COBL Lease.
Such missions may result in the displacement of both Unofficial and Official Travelers depending on the circumstances.
9. Question: Regarding current employees that service these facilities, do they stay in place during this transition (i.e. housekeeping, revenue managers, front desk)?
Answer: Yes, the intent of the Government is for DAF lodging employees to stay in place up until the Effective Date of the COBL Lease. The Lessee and Hotel Operator will need to provide/hire all employees required to operate the hotels and oversee the project beginning with the day of closing/conveyance. The Lessee and Hotel Operator are under no obligation to hire former DAF Lodging employees. Current DAF Lodging employees will be subject to a Business Based Action (BBA). All BBA actions are the responsibility of the Government, and all hiring actions are separate and distinct actions by the Lessee and the Hotel Operator.
10. Question: Outline privatized utilities in line with the Ground Lease that states utilities may be terminated within one year.
Answer: COBL is using the same language and procedures that the DAF uses for its Military Housing Privatization Initiative (MHPI) program. Per the “Utility Services Agreement” template, “If the Government is terminating any of the Utility Services in connection with the anticipated divestiture of all or any part of the Installation’s Utility Distribution System and the privatization of the associated Utility Services, the Government shall notify the Project Owner prior to entering into any such privatization contracts and the Government and the Project Owner shall cooperate with each other to effect an orderly and uninterrupted transition of such Utility Services from the Government to the privatized utility contractor or third party utility provider.”
11. Question: Will we be provided with templates for financials, etc. for the RFP response?
Answer: Appendix E of the RFP will outline certain assumptions that should be used in order to standardize all proposals for ease of Government review.
12. Question: Will we have access to DoD/DAF long term readiness plan as to best align development plan to right sizing?
Answer: Any publicly announced mission changes or mission bed-downs at installations are a matter of public record and will continue to be throughout pre- and post-closing periods. The Government will not be providing any information that attempts to quantify how those mission changes will affect demand for hotel rooms. For purposes of the RFP, Offerors should base their development plan on historical demand patterns and not assume any major changes in demand due to projected mission changes at the installations.
13. Question: What is the mix by installation of Official to Unofficial Travelers? In other words, how much of the occupancy can we assume will be per diem rates vs. market rates?
Answer: Detailed historical occupancy data will be provided in Step Two in the Document Room that contains a breakout of Official (P1) and Unofficial (P2) Travelers by installation.
14. Question: How do you define Long Term Stay – up to 6 months?
Answer: The Air Force does not have a formal definition of “Long Term Stay”. Different demand types (i.e., VQ vs TLF) are defined more by the needs of the traveler than length of stay. For example, TLF travelers generally need cooking capabilities since they are families moving to new installations and waiting for their permanent housing to be available. The length of stay may be short or long depending on how long it takes for their permanent housing to be ready. Likewise, a TDY traveler may be on extended orders (e.g., a 6-month training class) but may not require a kitchen under current DoD adequacy standards.
15. Question: How do you define Short Term Stay – a few days, 2-3 weeks?
Answer: Similar to the answer to the question above, stays are generally defined more in line with what type of hotel facilities a traveler requires than the actual length of their stay.
16. Question: How do you anticipate future programming (instruction/training)? Would it be scheduled where there is room to accommodate or specific to certain bases?
Answer: The Air Force does not anticipate changing the locations of future training events to locations where there is excess hotel capacity. Generally, training missions are established at specific installations based on where the supporting infrastructure is located, and those training missions remain in place unless there is some larger realignment of missions from one installation to another.
17. Question: What security restrictions do you foresee for internet, door locks, thermostats, etc. (terrorism requirements reduced)?
Answer: The Air Force does not anticipate any specific security or force protection requirements related to internet, door locks, or thermostats. Offerors should consult the Unified Facilities Criteria (the “UFC”) Section 4-010-01 of 12 December 2018, including Change 3 24 May 2024, DoD Minimum Antiterrorism Standards for buildings (Antiterrorism Force Protection or “ATFP”) for a particular location, as may be further amended or superseded; UFC Section 3-301-01, of 1 October 2019, including Change 1 of 2 October 2023 Structural Engineering, as may be further amended or superseded; and UFC Section 4-023-03 of 14 July 2009, including Change 4 of 10 June 2024 Design of Buildings to Resist Progressive Collapse, as may be further amended or superseded for applicable requirements.
18. Question: What services do families need? Parks, pools, etc.? What is provided in a
TLF?
Answer: For the solicitation, it should be assumed from the Offeror’s perspective that Air Force families will have the same needs as other families that relocate for work.
Currently, TLFs resemble a small house or apartment with 1 or more bedrooms, living room, full kitchen, and dining area. Styles of TLFs vary by installation, with some installations having former family housing units as TLFs, and other installations having a single building with up to 50 TLF units. More information on the particulars of existing TLF units at each installation will be provided in the Document Room at Step Two of the RFP.
Offerors are free to make their own determination on the best way to meet this extended stay demand segment in their proposals.
19. Question: From lessons learned, what were the most challenging issues for construction?
Answer: Consistent with the private sector, the Government has seen the most successful construction projects be ones where the developer executes a robust up front planning effort with key risks to cost, schedule, and quality identified, tracked, and resolved during the project development process. The most challenging issues tend to occur on projects where this up front planning effort has not been executed effectively, resulting in costly design changes, construction delays, or compromises to scope and/or quality.
20. Question: Please confirm that DAF will make attendee list and contact information available to all via SAM.gov
Answer: Yes, the attendee list has been posted to SAM.gov.
21. Question: Can you elaborate on the decline in room nights sold at the majority of locations from 2018 to 2024?
Answer: There are several potential causes. One issue was the large increase in room rates from 2018 to 2019 at Air Force-owned and operated lodging. This was a result of the DoD directive that the Military Departments’ lodging operations be funded 100% by non-appropriated funds beginning in 2019. This may have decreased the attractiveness to Unofficial Travelers and also, may have made it easier for Official Travelers to find off-base hotels at or below the rates they would be reimbursed for under the Joint Travel Regulations (JTR). The second issue is the decline in travel from the COVID-19 pandemic. Some of that TDY travel has not returned to pre-pandemic levels, and some meetings and training requirements that began to be conducted virtually during the pandemic have remained virtual.
22. Question: Can you provide insight for how unaccompanied housing will be managed if the option is exercised since there will be no hotelier involvement?
Answer: If the Government exercises the option to award an unaccompanied housing project to the Group A lessee at a single, or group of, installation(s) the Lessee will be expected to set up a completely separate project with no cross-collateralization to the COBL project. Since apartments are a very different product type than hotels, with different expertise needed, the Government anticipates the Lessee will hire a Government-approved property manager with experience managing apartment or rental housing type product to perform the property management responsibilities.
23. Question: Will we have access to daily occupancy by installation in Step 2?
Answer: Yes, daily occupancy by installation will be provided in the Document Room during Step Two.
24. Question: Why are total room revenues limited to 90%? Please explain the purpose and why penalize success?
Answer: Weighted average room rates for Official Travelers will initially be limited to 90% of per diem on an annual portfolio basis. This is for a number of reasons. First, current DAF Lodging rates are set at approximately 90% of per diem. Second, the DoD Integrated Lodging Program (ILP) generally requires off-base hotels to be at least 10% below per diem rates in order to participate, and the Government anticipates the on-base COBL hotels will likely want to remain part of the ILP program.
25. Question: Why can’t the hotelier be the Lessee?
Answer: The hotelier can be the Lessee, but the intra-party relationship restrictions and MER requirements of the RFP still hold.
26. Question: What is the purpose of the 5-year “renewal” for the entities performing the development, asset management, and construction services to the project?
Answer: In response to lessons learned on the Military Housing Privatization Initiative (MHPI) program and feedback from Congress, the Government desires a way to more easily sunset service providers that are not performing their duties as expected. The Government does not anticipate blocking the “renewals” except in cases of significant underperformance. Note that the hotelier is not subject to this 5-year “renewal”.
27. Question: Can you identify the historic buildings and/or programmatic agreements in place by location?
Answer: Historic buildings will be identified in the overall inventory and on the GIS Maps provided in the Document Room, released during Step Two of the selection process. Historic and other Culture & Natural Environmental Programmatic Agreements will be identified after the selection process is completed and the National Environmental Policy Act (NEPA) process has begun.
28. Question: Are there restrictions for demolition of historic buildings?
Answer: The ability to demolish a historic building will depend on what type of historic designation is placed on the building and other restrictions that may be in the existing programmatic agreement. There are often offsetting mitigation requirements negotiated between the Government, the State Historic Preservation Office and the Lessee under the “Section 106” process. If the Lessee takes a non-historic building as a short-term hold, the Lessee shall assume the demolition costs once use of the building has concluded. For purposes of the solicitation, if a historic building is taken as a short-term hold, assume the building will be returned to the Government. Current lodging facilities that are not conveyed to the Lessee, plus those returned to the Government after a short-term hold, may be repurposed by the Government for other uses (e.g. office space, dorms, alert facilities, Rec Lodging, etc.).
29. Question: What is Rec Lodging, and will bases in Group A continue to have Rec Lodging?
Answer: Many installations included in Group A currently have Recreational Lodging and will continue to offer Recreational Lodging in the future. Please see DODI 1015.11 (page
38) for a definition of Recreational Lodging.
30. Question: Will buildings to be renovated be subject to current ATFP requirements?
Answer: Please refer to UFC 4-010-01 DoD Minimum Antiterrorism Standards for Buildings referenced in the COBL Lease for the full requirements related to ATFP.
31. Question: Does the Applicant have the ability to right size key count based on historical occupancy data? Can the end-state key count be reduced, and can the number of buildings be consolidated?
Answer: Yes. The Government realizes there are, at some installations, too many hotel rooms in the inventory, and expects that each Offeror will propose a development scope that optimizes the end-state inventory to meet the historical demand while remaining responsive to mission needs. Offerors could propose a combination of some existing DAF Lodging buildings not to convey as part of the COBL Lease, some buildings to be demolished during the development period, and/or some rooms in buildings to be converted to other uses or otherwise reduced. The Government has completed its own analysis of what a potential end-state for each installation might be based on the number of needed rooms and the ability to reach, or limitations on reaching, that demand requirement based on the existing inventory. Those internal end state room count estimates will be provided to the Offerors as a helpful data point in Appendix F of the RFP, but the Government does not expect the Offerors to necessarily use that as their end-state.
The Government expects each Offeror to conduct their own analysis and explain why their proposed development plan and resulting end-state best achieves the Government’s goals as outlined in the RFP.
32. Question: Will recently completed improvements, improvements planned/budgeted between now and Group A closing and/or annual maintenance logs be shared?
Answer: Yes, that information will be included in the Document Room as part of Step Two.
33. Question: Are utility capacity studies available to show current condition and possibility to add demand to capacity (i.e. electric car charging stations)?
Answer: All Offerors should assume, for purposes of the RFP, that there is sufficient utility capacity available at the site to support all the needs of the project.
Questions Received After the Industry Forum
34. Question: Does the Hotel Operator that the Lessee contracts with have to be the same company that owns the brands (i.e., a brand-managed operator) the on-base properties will be operated under, or can the properties be operated by a Hotel Operator under a separate franchise/license agreement between the franchisor/brand and the Lessee?
Answer: The Hotel Operator must be the same company that owns the brands that will be utilized by the on-base hotels.
35. Question: Can the Hotel Operator be an affiliate of the Lessee?
Answer: Yes. However, if the Hotel Operator is an affiliate of the Lessee, then the Asset Manager, Developer, and Construction Contractor can NOT be an affiliate of the Lessee. In addition, the Government will either have the ability to remove the Hotel Operator for cause (i.e., fraud against the Government) or the Lessee will have an obligation to remove the Hotel Operator for cause. The intra-offeror relationships outlined in this RFP must be adhered to regardless of whether the Lessee’s Principal Member(s) are associated with the developer, the hotelier or other additional parties.
36. Question: Can a Hotel Operator (unaffiliated with the Lessee) delegate certain management and operating functions of the properties to an affiliate of the Lessee?
Answer: No.
37. Question: Exhibit G – Waterfall and Lockbox Accounts - Please provide the form/priority of waterfall accounts.
Answer: This is a placeholder until the Lessee, the Government and the Lender set the waterfall and lockbox account structure.
38. Question: Exhibit H – Please provide the specific historic preservation act compliance documents.
Answer: This is a placeholder until the specific historic preservation documents are negotiated with the State Historic Preservation Officers.
39. Question: Exhibit K - Are the Lessee and Hotel Operator required to craft fees that fit within the methodologies contemplated in the lease? Or is there room to negotiate different fee structures with different caps?
Answer: The Government has created “Appendix I – COBL Fee Template” for Offerors to fill out. Additionally, Exhibit K has been updated into three sections. Please refer to the new version of the COBL Lease posted as part of this RFI. It is the Government’s intent to have the Offeror state what fee percentages they propose, using the fee bases outlined in Exhibit K to enable the Government to evaluate all Offerors’ proposed fee percentages using the same fee bases. For the purpose of this solicitation, the metrics in the provided Exhibit K should be used. The Government may, but is not required to, change any element of the COBL Lease once negotiations with the Applicant begin.
40. Question: Exhibit K - Can the Hotel Operator use existing guest stay surveys for other hotels for purposes of satisfying the Guest Survey metric in 2(b)(4), if not, are there pre-approved surveyors who are well-versed in applying this metric (i.e., do we know who did the survey for the Army)?
Answer: The Hotel Operator can use a survey provider of their choice so long as the COBL Lease requirements are met. Ideally, this survey product is the same as that used by the Hotel Operator’s brands located off-base. If the hotelier uses a different scale than that shown in Exhibit K, the Government may work with the Hotel Operator to align its expectations of performance to the Hotel Operator’s survey format.
41. Question: Exhibit K - Hotel Operator System Expenses: Will there be an ability to adjust the System Expenses paragraph conform to the Hotel Operator’s centralized services/fee systems and standards?
Answer: The Government has attempted to provide greater clarity regarding its expectations for Fees and Expenses in the new RFP Appendix I. This includes fees to the Hotel Operator for centralized services/fee systems. The Government is seeking a best value proposal from the Offerors. As noted in the new Appendix, Offerors have flexibility to outline their approach to Fees, Centralized Costs, Shared Services, Reimbursables, and other Fees and Expenses.
42. Question: Exhibit L (Employment Clauses) – Does this exhibit apply to Hotel Operator’s employees who are hired to operate/run the facilities?
Answer: The title of the exhibit has been updated to “DAVIS-BACON ACT, CONTRACT
WORK HOURS AND SAFETY STANDARDS ACT--OVERTIME COMPENSATION, APPRENTICES
AND TRAINEES, PAYROLLS AND BASIC RECORDS, COMPLIANCE WITH COPELAND ACT
REQUIREMENTS, SUBCONTRACTS (LABOR STANDARDS), COMPLIANCE WITH DAVIS-
BACON RELATED ACT REGULATIONS, OR CERTIFICATION OF ELIGIBILITY.” The aforementioned acts are governed by the Department of Labor. Thus, this will apply to Hotel Operator’s employees if the Hotel Operator conducts work that is covered by the Davis-Bacon Act. The Hotel Operator should consult with their legal advisors on what work is covered.
43. Question: Section 18.4 - Can the Lessee utilize Hotel Operators Quality Assurance program to satisfy its lease requirements?
Answer: Yes. It is expected that the Hotel Operator’s Quality Assurance program will be used in COBL.
44. Question: Section 25.3 - Are there specific standards available for the rooms available for Distinguished Visitors?
Answer: Current DAF lodging operations operate under the Department of Defense Instructions that defines Distinguished Visitor lodging as “Lodging units available for rental that are often larger with multiple rooms and enhanced amenities” (See DoD Instruction 1015.11). Within that broad framework, current Distinguished Visitor rooms/suites/houses vary widely by installation in terms of size, quality, and amenities offered. Upon privatization under COBL, the DoD Instructions will no longer apply, and the COBL Lease Exhibit J will govern, which calls for enhanced services to be mutually determined by the installation protocol office and the Lessee. Offerors should propose Distinguished Visitor Suites as part of their project concept that they determine meet the needs of executive level travelers at each location and fit within their overall hotel concept for each installation.
45. Question: Section 27.6 - Can Hotel Operator require the Lender to enter into a non-disturbance agreement?
Answer: It depends, and all parties (Lessee, Hotel Operator, Government, and Lender) would have to agree at the time the documents are executed.
46. Question: Section 28 – Will any of the insurance requirements be applicable to the Hotel Operator?
Answer: Yes. The Government imposes insurance requirements on the Lessee, and it is expected the Lessee to impose such applicable COBL Lease provisions on the Hotel Operator.
47. Question: Section 28.14 – Will the limitations on litigation settlement apply to any claims made against the Hotel Operator where Hotel Operator would otherwise be entitled to indemnification from Lessee pursuant to the Hotel Management Agreements?
Answer: Yes.
48. Question: Section 31.3 - Does the Government have a form of the report of the monthly risk assessment review report the Hotel Operator is required to conduct?
Answer: No. It is expected that the Hotel Operator conducts risk assessments of its hotels.
It is expected that this report would meet the Government’s needs under the COBL Lease.
If no such report exists, the Applicant and the Government would negotiate one to meet the requirements of the COBL Lease. The COBL Lease requirement in the monthly report package is submission of the risk assessments completed but not yet submitted in the previous month’s submission. It is not a requirement to perform an assessment each month.
49. Question: Section 32 – Can existing Hotel Operator retention policies apply to books and records of these facilities?
Answer: Maybe. It depends on the Hotel Operator’s retention policies. This would be a discussion item with the Applicant. However, if the Hotel Operator’s retention policies are at industry standards, the starting point would be for the Government to review such policies to ensure that Government requirements are also met. As with any Condition found in the COBL Lease, the Government may, but is not required to, change any Condition found within.
50. Question: Section 46 – Please provide further information on the “In-License” and how these systems would be able to communicate with Hotel Operator systems?
Answer: The in-license would be between the Lessee and the Government. There is not a direct interface between Government systems and the Hotel Operators property management system (PMS). Once an order for rooms is placed under the in-license, an authorized Government representative will communicate specifics like names, dates, etc.
for the covered guests to the Hotel Operator for entry into the hotel PMS.
51. Question: What will the employment status be for current on property employees upon commencement of operations under the incoming Hotel Operator/Brand? If the incoming Hotel Operator desires to employ those current on property employees, would the current employees first be terminated from government employment and then the incoming Hotel Operator could rehire them?
Answer: All existing DAF Lodging employees will have their Government employee status addressed as part of the Government’s Business Based Action (BBA) prior to conveyance of the facilities. Some existing DAF Lodging employees may elect to remain with the Government and as such, move to other Government positions. Some existing DAF Lodging employees may retire or resign, while others will be terminated under the BBA.
52. Question: If the incoming Hotel Operator re-hires current on property employees, would the Hotel Operator be responsible for any prior employee benefits upon rehire?
Answer: No, their prior Government employment will cease. To the extent their employment is terminated by the Government, they will be paid any required severance or benefits per the terms of their existing employment with the Government.
53. Question: Would the answers to the above two questions remain the same if those current on property employees are union members?
Answer: Yes.
54. Question: RFP Reference 4.3.2.b3 - To confirm, must the Hotel Management Company’s MER-qualifying experience be specifically on U.S. Government installations (e.g., prior COBL, PAL, or other DoD lodging contracts)? Or may “comparable civilian/municipal contracts” (e.g., large select-service management portfolios) satisfy the
MER?
Answer: The Hotel Management Company’s qualifying experience does not need to be on a U.S. Government installation and may be from hotels located in the private sector.
55. Question: Lease Reference Exhibit K, Section 3: Hotel Operator Systems Expenses - Please clarify whether the Hotel Operator must use DAF-approved brand / reservation / loyalty / accounting platforms (e.g., Sabre CRS, other proprietary systems) or if any GDS-compatible system is acceptable as long as total system expenses do not exceed 1% of Rooms Revenue in each category.
Answer: The Government does not require approval of the brand / reservation / loyalty / accounting platforms. The Government notes that integrating with DoD systems like the Defense Travel System (utilized by Official Travelers to make their official travel reservations and facilitate reimbursement) requires rooms be made available through the GDS via providers such as Worldspan and Sabre. It is expected that the Hotel Operator would be able to connect to the GDS so as to make its COBL hotel rooms available to Official Travelers through DTS. With regard to cost of the system, please see Appendix I of the RFP.
56. Question: Lease Reference Exhibit K, Section 2.a.(2)-(3): Asset and Hotel Management Incentive Fees - Can the Government provide sample scorecards or historical benchmarks for each of the seven performance metrics (e.g., floor/ceiling scores on Guest Surveys, typical target for “Accommodation of Official Travelers”)? In particular, what is the minimum acceptable score on each metric to earn the Incentive Fee, and how are the 90/10 weightings operationalized?
Answer: For metrics using the Floor and Ceiling construct, scores below the Floor earn no fee for that metric. For scores above the Ceiling, full award for that metric is earned. For scores between the ceiling and the floor, a pro rata award is made for that metric.
For the 90/10 review of segmentation, the award is granted on satisfaction of a series of IF- THEN statements, as detailed in that section of Exhibit K. The metrics are assessed at the end of each Fiscal Year.
57. Question: RFP Reference 4.3.2.g; 5.0 - Are pre-opening staffing and training costs for front-desk, housekeeping, and back office (accounting) fully reimbursable as Transition Costs, or must the Hotel Management Company absorb these costs until the first guest?
Likewise, will initial marketing, staff lodging, and site inspection travel be reimbursed, or treated as Hotel Marketing Company overhead?
Answer: The Government and Lessee / Hotel Operator will draft a Transition Agreement that outlines specifically what start-up costs and expenses will be reimbursed. The Government will issue the Notice to Transition a few months prior to the expected close, at which point, all expenses covered in the Transition Agreement will be reimbursable at closing. All costs mentioned in the question are consistent with allowed reimbursable expenses in prior MHPI Transition Agreement budgets provided the expenses occur during the established Transition Period.
58. Question: Lease Reference 12-13 - Can the Government provide the exact minimum coverage limits required for General Liability, Auto Liability, Workers’ Compensation, and Property Insurance? Will the Government accept self-insurance for Workers’
Compensation if the Hotel Management Company’s plan meets DoD standards, or must all policies be placed with A-rated carriers and specific endorsements?
Answer: No, the Government cannot provide exact minimum coverage. Assumptions on insurance will be provided in the RFP Appendix E, or the Offerors will use the minimums in the COBL Lease for their proposals. However, it is expected that the Lessee, the Lessee parties, Lender, and Government shall review insurance coverage before the COBL Lease effective date and review periodically. As to self-insurance, this will be an open discussion with the Applicant.
59. Question: RFP Reference 4.2.2.c Security & Access - To clarify base access requirements, will all on-site Hotel Management Company employees—including housekeeping attendants, front-desk agents, and maintenance staff—be required to hold a DoD security clearance (e.g., Public Trust or Secret)? Or is a Tier-1 visitor pass (standard base badge) sufficient for any/all of these positions? If a clearance is required, please confirm the specific level of investigation (e.g., Public Trust versus Secret), and whether the clearance requirement pertains to all levels of staff?
Answer: No employees will be required to hold a DoD security clearance. To access the installation, employees will need to pass a basic background check in order to obtain an access badge onto the installation, Government contractor Common Access Card, or similar (depending on the specific access procedures for a given installation). Please see DAFFARS 5352.242-9000, Contractor Access to Department of the Air Force Installations, for what would be expected for Lessee employees who work at an installation.
60. Question: RFP Reference 4.2.2.c Security & Access - Can you confirm what pay schedule is used for operational staff working on base. Are they paid under a Government GS pay scale (e.g., GS-5, GS-7, etc.), or a commercial wage (e.g., off-base rate for comparable roles)? If GS pay, can you indicate the grade range applicable to position type (housekeeper, front-desk agent, maintenance technician, etc.) prior to Step 2?
Answer: Non-appropriated Fund (NAF) employees are not on the GS scale. They are on the either the NAF or Crafts and Trades pay scales (depending on their position). Information the pay scales for each position will be available to the Offerors in the Document Room in Step Two.
61. Question: RFP Reference 4.2.2.c Security & Access - Can you confirm whether there will be a “first right of refusal” for incumbent workforce when the Hotel Management Company assumes operations – what is the government policy for protecting existing employees? If FROS, can you clarify if there will be specific personnel policies (e.g., pay protections, service credits)?
Answer: The Government cannot require the Lessee / Hotel Management Company to offer existing employees a “First Right of Refusal”, other form of hiring preference, or any guarantee of hiring existing employees. All existing employees’ current employment with DAF lodging will end on the date the COBL Lease is executed, and for employees separating from the Government, no employment liabilities, pay protections, service credits or any other employment terms will remain in effect past that effective date. The Lessee and Hotel Management Company will not begin the COBL Lease period with any employment liabilities or requirements.
62. Question: RFP 4.4.2.2.a.5.ii and RFP 4.4.2.2.a.5.iii - The draft RFP for Step Two – Section 4.4.2.2.a.5.ii requests information on debt and equity financing for satisfying a requirement for Development Experience. Will the Government accept adding the qualifier, “If the identified project is a hotel project in which a principal member of proposed contractor currently holds an ownership interest…” which mirrors the qualifier provided in the following section 4.4.2.2.a.5.iii?
Answer: The section has been revised to read: “ii. If the identified project is a project in which a Principal Member or proposed contractor currently holds an ownership interest provide information on the project’s financing, including debt (short and long-term) and other sources of funds. If the Offeror was not involved with the financing of the project, so state.”
63. Question: Lease Reference 22.4 Obligations for Major Work - The Lease provides a scope of work for the ICC (Section 22.4), which implies active management of construction, for example, the review and approval of construction change orders. Is the intent that the ICC will perform their services alongside what would otherwise be provided by the Developer/Development Manager or in place of the Developer/Development Manager?
Answer: The role of the Independent Construction Consultant (ICC) is not intended to replace any normal development management functions. The ICC ensures the development is meeting law, the COBL Lease, and the specs in the as-approved construction drawings. This is vital to protect the Lessee, the Lessor and the Lender’s interests. The Government is not satisfied with only relying on the Development Manager for oversight of the construction contractor.
64. Question: Lease Condition 22.4 Lessee Obligations for Major work - Given potential differences in opinion between the Developer/Development Manager and the ICC during performance, what dispute resolution provisions (e.g., escalation to the Government’s Commander, formal mediation) should be considered? Who shall have ultimate approving authority?
Answer: In short, for matters relating to commercial code, the Lessee has final word and for matters of Government regulations, the Government has final word. See Section 2 of Exhibit Q of the COBL Lease for additional details.
65. Question: Lease Condition 22.2 ICC - Regarding the Lease, where the Developer/Development Manager has only a contractual relationship with the Lessee, and assuming they are otherwise qualified, would the government also permit the Developer/Development Manager to contract with the Lessee to perform the role and services as the ICC?
Answer: No, the ICC must be an independent entity.
66. Question: RFP Reference 4.3.2.b.1 Cumulative Development Experience and RFP Reference 4.3.2.b.2 Major Development Project Experience - Can you clarify the intent regarding the type of experience which can be utilized to qualify as the “developer of record” related to the draft RFP MERs requirements as defined in Sections 4.3.2.b.1 and 4.3.2.b.2. Specifically, are projects where the developer of record provided comprehensive development services but did not have ownership equity interest in those projects be utilized to satisfy both requirements? Further, we note some discrepancies between requirements and that section 1 states “…has or had an ownership equity interest or was the developer of record” while section 2 states “…has or had an ownership equity interest and was the developer of record”.
Answer: The language in the RFP has been adjusted in both sections to only require the experience to be of the “Developer of Record”. Please see revised RFP posted with this document.
67. Question: RFP Reference 4.2.2.d and Lease Reference Exhibit K, & Exhibit J - Appendix G lists only established national brands (e.g., Hilton, Marriott, Choice), and our brand is not included. We propose to bid under the brand umbrella but co-create with the Air Force a unique, COBL-specific brand prototype (combining our brand’s operating platform with customized co-created design, service standards, and branding tailored to DAF requirements). Would the Government consider such a “co-developed” brand provided it fully meets or exceeds the Exhibit J brand standards, and, if so, what is the formal process for obtaining the required waiver under COBL Lease Condition 18.6.4?
Answer: Appendix G is included to list the applicable brands from which Hotel Management experience may be drawn for purposes of satisfying the Minimum Experience Requirements (MERs) in Step One of the RFP. For Offerors satisfying the MERs and advancing to Step Two, there is no requirement that hotels on-base be branded under COBL using Appendix G as the exclusive list of available brands. A COBL specific brand prototype is acceptable as long as it meets or exceeds the requirements in Exhibit J.
Whatever the hotel brand proposed, it will be evaluated accordingly per the factors outlined in the RFP.
COBL Lease condition 18.6.4 governs instances where a waiver is sought from the brand standards that exist for that brand, whether it be an established national brand, such as those found in Appendix G, or for a brand created specifically for COBL. COBL Lease condition 18.6.4 does not impact the establishment of a new brand.
68. Question: RFP Reference 4.4.2.2.a.5 and RFP Reference 4.4.2.2.a.6 - Can you clarify the expected timing and “conditions precedent” for our company’s equity contributions at closing and any subsequent funding draws (e.g., tranches tied to construction milestones)?
Specifically:
1. By what date must our company deposit its first equity tranche into escrow?
2. Will there be a requirement to fund a fully-capitalized Replacement Reserve before closing (per COBL Lease Condition 28.1)?
3. Are there any minimum “debt service coverage” or “loan-to-cost” thresholds that must be met at each draw?
Answer:
1. There is no set date for equity contributions to be made to the Project Company. Note, however, that the Government will not approve any financial return on an equity contribution.
2. The Replacement Reserve will be funded each month at a specified amount. Currently, there is not a requirement to fund an up-front deposit to that account.
3. Actual debt coverage ratio minimums will be established by the Lender per the terms of the loan.
The Government will consider if clarifications to initial Replacement Reserve account deposits and minimum coverage ratios are appropriate for inclusion in Appendix E of the
RFP.
69. Question: Lease Reference Condition 28 (Reserve Accounts); Lease Reference Condition 45 (Rent); and Exhibit G (Lockbox Waterfall) – Lockbox Priority - To ensure our cash-flow model is accurate, can you confirm:
1. Whether the Replacement Reserve deposit (10% of Revenue) and any Debt Service Reserve must be fully funded prior to any Equity Distributions, or if partial funding (e.g., first-year Replacement Reserve only) is acceptable at Closing?
2. If the Government will permit a first-draw equity escrow structure (e.g., 50% of equity at Closing, 50% at 50% construction completion) without disrupting the Lockbox waterfall.
3. Whether Additional Rent (ground rent) rates are expected to be invoiced monthly or quarterly, and if any true-up is required within the same fiscal year.
Answer:
1. There will be no equity distributions, and therefore, no requirement for equity contributions.
2. If the Offeror chooses to make an equity contribution, there are no requirements related to the schedule for deposit into the project.
3. The primary “Additional Rent” will be for the reimbursement of emergency and police services. These are installation-incurred costs. It should be assumed that for the purpose of this solicitation, these will be invoiced monthly. However, the Lessee and installation will work together on the timing of payment for such services. It is not expected that the COBL program will get involved unless such expenses are not being paid or if such services are not being delivered.
70. Question: Lease Reference Condition 24 (Environmental Matters) and Lease Reference Condition 13 (Property Insurance) - Please clarify:
1. Whether the Government requires a separate Environmental Liability Policy (e.g., Pollution Legal Liability) beyond standard General Liability and Property coverage.
2. Whether any pre-identified environmental assessments or Remedial Action Plans (RAPs) must be completed or escrowed prior to Closing, or if they will remain Government responsibilities.
3. If the Government will reimburse Lessee for any Government-directed environmental compliance audits (e.g., soil sampling, lead paint surveys) during the Transition Period.
Answer:
1. The Government requires “environmental liability or pollution legal liability insurance.”
However, how the Lessee provides this coverage is up the Lessee. It can be a separate policy or covered in a larger policy.
2. Pre-existing conditions are the responsibility of the Government unless the Lessee disturbs the contaminated soils. The plan is for the Lessee to construct on uncontaminated land. If the leased land is contaminated to the point that it causes a material cost, the practical solution is for the Lessee to return such Government contaminated land and for the Government to provide a suitable clean parcel.
3. The Lessee will reimburse the Applicant for transition costs as identified in the RFP and as codified in the Transition Agreement.
71. Question: RFP Reference 4.2.2.d and Lease Reference Exhibit K, & Exhibit J - Can you confirm:
1. Whether we may subcontract a third-party CRS (e.g., Sabre, Pegasus) or use our proprietary CRS—provided total reservation fees remain less than or equal to 1% of Rooms Revenue.
2. If any preferred loyalty/guest-recognition programs qualify under the “Loyalty Program fee” category, and whether custom Government-only loyalty modules (e.g., “Base-Only Loyalty Tier”) are permitted.
3. How the Government views accounting system fees: must we use a DoD approved financial platform for reporting (e.g., “GovFin” ERP), or may we use our existing commercial PMS/ERP (e.g., Opera + Infor) if we can demonstrate integration capabilities?
Answer:
1. The COBL Lease will not dictate the Central Reservation System (CRS) that must be used by the Hotel Operator but notes that the system should be able to interface with the GDS so as to ensure room availability can be shown on the Defense Travel System – the system Official Travelers use to book their travel. We have issued a new Appendix I to the RFP clarifying the Government’s expectations with regard to service fees.
2. Preferred loyalty/guest-recognition programs qualify under the “Loyalty Program fee.”
There are no restrictions on how such a program can be structured, altered or customized for the Government. Whatever is offered will be evaluated per the RFP Evaluation Factors.
3. Offerors may use their existing commercial PMS/ERP (e.g., Opera + Infor). No DoD IT system will be integrated into the system. Reports to the Government will be outputs from those systems.
72. Question: Lease Reference Condition 18.9 - As Lessee, Brand and Capital Provider, can you confirm, will Government permit us to: Assign the Lease to a wholly owned special purpose entity (SPE) specifically formed for COBL operations, while retaining 100% equity.
Sublease to a separate in-house “Development” affiliate for the purposes of coordinating renovations and brand conversions, provided Lessee remains the ultimate guarantor.
Answer: [The Government did not understand the Lease citation provided.] The Government will allow the Lessee to be a SPE. The Government will need to understand the purpose of the sublease before commenting but notes that the intra-offeror relationships outlined in this RFP must be adhered to regardless of whether the Lessee’s Principal Member(s) are associated with the developer, the hotelier or other additional parties. Both the developer and the hotelier cannot be affiliates of the Lessee. One or the other may be, but not both.
73. Question: Lease Reference Condition 38.1 - To properly structure our equity waterfall, can you clarify:
1. Whether Development Manager or Brand Operator defaults (e.g., failure to maintain brand standards or complete a construction milestone) will trigger the Lessee default timeline, or if the Government will provide separate cure periods for sub-contracted parties.
2. If Lessee is required to cure defaults arising from a third-party Brand or ICC within the 30-day window, or if the Government will allow extension based on “force majeure” or “subcontractor bona fide disputes”.
Answer:
1. The Government assumes that your Lease reference is to 18.1. Defaults in the Development Management Agreement or the Hotel Management Agreement would be handled within those agreements, and would not cause a cross-default with the COBL Lease.
2. The Lessee is required to cure non-compliance with the COBL Lease in accordance with Condition 35.
74. Question: Lease Reference Condition 28.3 - If Lessee funds the Replacement Reserve at 10% of Revenue and, after five years, there is a surplus, can those funds be reallocated to:
1. Lobby renovations or technology upgrades that exceed Exhibit J standards?
2. Debt prepayment at Lessee’s discretion (i.e., “prepay a portion of the senior loan”)?
Please clarify the approval process and any priority for reallocation (e.g., must we demonstrate a capital project ROI or meet specific brand mandates).
Answer: The Lessee, Lessor and Lender will set the annual deposit percentage for deposits into the Reservation Reserve account. The Lessee can propose renovation projects for the Government’s consideration and approval. Both listed uses (lobby renovations and technology upgrades that exceed Exhibit J standards) are appropriate suggested uses for funds in the account regardless of there being a “surplus”. Pre-payment of debt would require Government approval and cannot be done at the Lessee’s discretion.
75. Question: There appears to be a discrepancy between provided “Total Revenue” provided by Government and calculated revenues from the installation data provided. The variance is too high to be a rounding error. Overall portfolio is $9.8M off. What is included in the Total Revenues provided for each installation?
Answer: The Air Force has reviewed the spreadsheet outlining your analysis and notes several issues with your calculations. First, four bases (Maxwell, Sheppard, Travis, and Goodfellow) appear to have significant numbers that are incorrect or have been transposed to the wrong line.