Infrastructure Cost Estimates Summary
Appendix D Infrastructure Cost Estimates is a detailed cost breakdown document prepared by LaBella Associates for the Empire State Development's Mohawk Valley Psychiatric Center redevelopment project in Utica, New York. The estimate provides unit prices and total costs for all site infrastructure required to support the 6.13-acre parcel redevelopment as of December 1, 2025. Major infrastructure categories include sitework (site preparation, grading, and erosion control across 6.0 acres), site improvements (asphalt paving of 7,250 square yards, concrete work, permeable pavers, landscaping, and site amenities), site utilities (water, sanitary, and stormwater systems serving 14 residences and 3 multi-use buildings), site electrical systems (multiple transformers ranging from 75 kVA to 1,500 kVA with associated feeders and lighting), telecommunications infrastructure, and miscellaneous utility removal and relocation.
The subtotal infrastructure cost is estimated at $4,232,500, with general conditions (10%), overhead and profit (8%), and design contingency (20%) bringing the subtotal to $6,033,852. An additional 15% escalation factor for Q1 2029 results in a total site utilities cost of $6,938,930. This comprehensive estimate serves as the baseline for infrastructure investment required to support the residential redevelopment project, which is subject to New York State's Minority/Women Business Enterprise (MWBE) contracting goals of 15% for both MBE and WBE participation, as well as a 6% Service-Disabled Veteran-Owned Business (SDVOB) goal.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Appendix C Phase 1 ESA Building 51.pdf | ||
| Appendix F- HFA-Underwriting-Model-2026.xlsx | XLSX spreadsheet | |
| Appendix G- RUSH Budget Utica-template.xlsx | XLSX spreadsheet | |
| Appendix I- Site Tour RSVP Form.doc | DOC document | |
| Mohawk Valley Psychiatric Center RFP.pdf | ||
| Appendix H Access Permit.MVPC.RFP respondents.docx | DOCX document | |
| Appendix E- ESD IT Security_Briefv6.pdf | ||
| Appendix B Phase 1 ESA.pdf | ||
| Appendix A MV Psych Feasibility Study.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MASTER PLAN ESTIMATE
12/1/2025
DESCRIPTION UNIT PRICE TOTAL
SITEWORK
SITE PREP
Clear, strip and prep 6.0 ACRES $8,500.00 $51,000
Soil and erosion control 6.0 ACRES $4,500.00 $27,000
Regrade as required (assume balanced) 6.0 ACRES $12,000.00 $72,000
SITE IMPROVEMENTS
Asphalt paving 7,250 SY $50.00 $362,500
Mill and Overlay Pavement 2,700 SY $20.00 $54,000
Concrete curb 3,000 LF $29.25 $87,750
Concrete walks (allowance) 23,500 SF $13.50 $317,250
Permeable pavers and subbase 20,000 SF $28.00 $560,000
Spread existing topsoil, seed 3.0 ACRES $25,000.00 $75,000
Trees/plantings 3.0 ACRES $20,000.00 $60,000
Site amenities 1 ALLOW $50,000.00 $50,000
SITE UTILITIES
Water, main loop (8") 1,200 LF $175.00 $210,000
Water service to residences 14 EA $1,000.00 $14,000
Water service to multi-use buildings (Domestic and F.P.) 3 EA $10,000.00 $30,000
Fire hydrants 1 EA $10,000.00 $10,000
Sanitary, main loop (8") 1,200 LF $175.00 $210,000
Sanitary laterals to residences 14 EA $1,000.00 $14,000
Sanitary laterals to multi-use buildings 3 EA $10,000.00 $30,000
Stormwater swales, bioretention, catch basins, piping, etc. 1 ALLOW $380,000.00 $380,000
Storm laterals at residences 14 EA $1,000.00 $14,000
UTICA SITEWORK
QUANTITY
EMPIRE STATE DEVELOPMENT
MOHAWK VALLEY - UTICA NY
LABELLA ASSOCIATES
Mohawk Valley Psychiatric Center RFP Appendix D - Infrastructure Cost Estimates
Storm laterals at multi-use buildings 3 EA $10,000.00 $30,000
SITE ELECTRICAL
De-energize and disconnect existing main service feeder / coordinate with Utility Company 1 ALLOW $10,000.00 $10,000
Site lighting fixture and circuit removal 1 ALLOW $5,000.00 $5,000
Underground main electrical service feeder (includes shared trench) 900 LF $125.00 $112,500 300 kVA 3-ph transformer, pad, and grounding 1 EA $60,000.00 $60,000
300 kVA transformer secondary feeder including earthwork 100 LF $175.00 $17,500 75 kVA, 1-ph transformer, pad, and grounding 1 EA $45,000.00 $45,000
75- kVA transformer secondary feeder including earthwork 150 LF $205.00 $30,750 100 kVA, 1-ph transformer, pad, and grounding 4 EA $50,000.00 $200,000
100- kVA transformer secondary feeder including earthwork 900 LF $205.00 $184,500
1,500 kVA transformer, pad, and grounding 1 EA $175,000.00 $175,000
1500 kVA,3-ph transformer secondary feeder including earthwork 100 LF $850.00 $85,000
Underground main tele / data service feeder including handholes (in conduit) 2,200 LF $100.00 $220,000
Underground tele / data service lateral - per building 15 EA $5,000.00 $75,000
LED road / walkway lighting including below grade conduit and circuiting 35 EA $9,250.00 $323,750
MISCELLANEOUS
Existing utility removal/relocation 1 ALLOW $30,000.00 $30,000
SUB-TOTAL $4,232,500
GENERAL CONDITIONS 10% $423,250
OVERHEAD AND PROFIT 8.0% $372,460
DESIGN CONTINGENCY 20% $1,005,642
SUB-TOTAL $6,033,852
ESCALATION Q1 2029 15% $905,078
TOTAL SITE UTILITES $6,938,930
Mohawk Valley Psychiatric Center RFP Appendix D - Infrastructure Cost Estimates
File details come from the government source that posted it. Updated .