Infrastructure Cost Estimates Summary

Appendix D Infrastructure Cost Estimates is a detailed cost breakdown document prepared by LaBella Associates for the Empire State Development's Mohawk Valley Psychiatric Center redevelopment project in Utica, New York. The estimate provides unit prices and total costs for all site infrastructure required to support the 6.13-acre parcel redevelopment as of December 1, 2025. Major infrastructure categories include sitework (site preparation, grading, and erosion control across 6.0 acres), site improvements (asphalt paving of 7,250 square yards, concrete work, permeable pavers, landscaping, and site amenities), site utilities (water, sanitary, and stormwater systems serving 14 residences and 3 multi-use buildings), site electrical systems (multiple transformers ranging from 75 kVA to 1,500 kVA with associated feeders and lighting), telecommunications infrastructure, and miscellaneous utility removal and relocation.

The subtotal infrastructure cost is estimated at $4,232,500, with general conditions (10%), overhead and profit (8%), and design contingency (20%) bringing the subtotal to $6,033,852. An additional 15% escalation factor for Q1 2029 results in a total site utilities cost of $6,938,930. This comprehensive estimate serves as the baseline for infrastructure investment required to support the residential redevelopment project, which is subject to New York State's Minority/Women Business Enterprise (MWBE) contracting goals of 15% for both MBE and WBE participation, as well as a 6% Service-Disabled Veteran-Owned Business (SDVOB) goal.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MASTER PLAN ESTIMATE

12/1/2025

DESCRIPTION UNIT PRICE TOTAL

SITEWORK

SITE PREP

Clear, strip and prep 6.0 ACRES $8,500.00 $51,000

Soil and erosion control 6.0 ACRES $4,500.00 $27,000

Regrade as required (assume balanced) 6.0 ACRES $12,000.00 $72,000

SITE IMPROVEMENTS

Asphalt paving 7,250 SY $50.00 $362,500

Mill and Overlay Pavement 2,700 SY $20.00 $54,000

Concrete curb 3,000 LF $29.25 $87,750

Concrete walks (allowance) 23,500 SF $13.50 $317,250

Permeable pavers and subbase 20,000 SF $28.00 $560,000

Spread existing topsoil, seed 3.0 ACRES $25,000.00 $75,000

Trees/plantings 3.0 ACRES $20,000.00 $60,000

Site amenities 1 ALLOW $50,000.00 $50,000

SITE UTILITIES

Water, main loop (8") 1,200 LF $175.00 $210,000

Water service to residences 14 EA $1,000.00 $14,000

Water service to multi-use buildings (Domestic and F.P.) 3 EA $10,000.00 $30,000

Fire hydrants 1 EA $10,000.00 $10,000

Sanitary, main loop (8") 1,200 LF $175.00 $210,000

Sanitary laterals to residences 14 EA $1,000.00 $14,000

Sanitary laterals to multi-use buildings 3 EA $10,000.00 $30,000

Stormwater swales, bioretention, catch basins, piping, etc. 1 ALLOW $380,000.00 $380,000

Storm laterals at residences 14 EA $1,000.00 $14,000

UTICA SITEWORK

QUANTITY

EMPIRE STATE DEVELOPMENT

MOHAWK VALLEY - UTICA NY

LABELLA ASSOCIATES

Mohawk Valley Psychiatric Center RFP Appendix D - Infrastructure Cost Estimates

Storm laterals at multi-use buildings 3 EA $10,000.00 $30,000

SITE ELECTRICAL

De-energize and disconnect existing main service feeder / coordinate with Utility Company 1 ALLOW $10,000.00 $10,000

Site lighting fixture and circuit removal 1 ALLOW $5,000.00 $5,000

Underground main electrical service feeder (includes shared trench) 900 LF $125.00 $112,500 300 kVA 3-ph transformer, pad, and grounding 1 EA $60,000.00 $60,000

300 kVA transformer secondary feeder including earthwork 100 LF $175.00 $17,500 75 kVA, 1-ph transformer, pad, and grounding 1 EA $45,000.00 $45,000

75- kVA transformer secondary feeder including earthwork 150 LF $205.00 $30,750 100 kVA, 1-ph transformer, pad, and grounding 4 EA $50,000.00 $200,000

100- kVA transformer secondary feeder including earthwork 900 LF $205.00 $184,500

1,500 kVA transformer, pad, and grounding 1 EA $175,000.00 $175,000

1500 kVA,3-ph transformer secondary feeder including earthwork 100 LF $850.00 $85,000

Underground main tele / data service feeder including handholes (in conduit) 2,200 LF $100.00 $220,000

Underground tele / data service lateral - per building 15 EA $5,000.00 $75,000

LED road / walkway lighting including below grade conduit and circuiting 35 EA $9,250.00 $323,750

MISCELLANEOUS

Existing utility removal/relocation 1 ALLOW $30,000.00 $30,000

SUB-TOTAL $4,232,500

GENERAL CONDITIONS 10% $423,250

OVERHEAD AND PROFIT 8.0% $372,460

DESIGN CONTINGENCY 20% $1,005,642

SUB-TOTAL $6,033,852

ESCALATION Q1 2029 15% $905,078

TOTAL SITE UTILITES $6,938,930

Mohawk Valley Psychiatric Center RFP Appendix D - Infrastructure Cost Estimates