About this file
The document is the Ames Laboratory Contractor Safety & Quality Assurance Information Questionnaire (Form 10200.140), a comprehensive assessment form designed to evaluate a potential contractor's safety and quality management practices. The form requires detailed reporting on workplace safety metrics, including three years of injury and illness data, Experience Modification Rate (EMR), accident reporting frequencies, safety policy documentation, meeting and inspection practices, and new hire orientation procedures.
The questionnaire also includes a quality assurance section where contractors must classify themselves into one of four levels based on their existing quality assurance documentation and prior performance at Ames Laboratory. Contractors are asked to indicate the types of work they can perform or subcontract, covering an extensive range of construction and technical disciplines such as site work, concrete, masonry, metals, mechanical systems, electrical systems, wood and plastics, conveying systems, equipment installation, and laboratory-specific work. The form is designed to comprehensively assess a contractor's safety culture, operational practices, and technical capabilities before potential engagement with the Ames Laboratory.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Form 10200.140
ESH&A, 4-9769
Rev 1.3, 04/01/2017 1
APPENDIX D - AMES LABORATORY
CONTRACTOR SAFETY & QUALITY ASSURANCE
INFORMATION QUESTIONNAIRE
RFP #
Project Name
Contractor
Address
Phone Contact # Email
1. List your firm's interstate Experience Modification Rate (EMR) for the past three consecutive years.
NOTE: This information can be obtained from your Worker's Compensation carrier.
Year Identify your Worker's Compensation carrier:
Year
Year
Address:
Phone:
2. Using the information from the OSHA No. 300 log, provide the following information on injuries and illnesses for the past three consecutive years.
Year Year Year A. Total number of recordable cases
(i.e., sutures, fractures, burns, rashes, foreign body in eye, etc.) including cases involving lost time.
B. Number of lost workday cases.
C. Number of lost workdays.
D. Number of fatalities.
E. Employee hours worked each year.
Rate Calculation Formulas:
A ) Number of OSHA Recordable Cases x 200,000 Number of Hours Worked Per Year
B) Number of Lost Time Accidents x 200,000 Number of Hours Worked Per Year
C) Number of Days Lost x 200,000 Number of Days Worked Per Year
ESH&A
Signature
Approved Approved as noted Not approved – Resubmit
Rev 1.3, 04/01/2017 2
3. How often are accident reports (OSHA 300) and report summaries sent to the following:
Never Monthly Quarterly Annually
Field Superintendent Vice President of Construction President/CEO
4. Does your firm:
Have a written company safety policy signed by a company officer?
Have an established written safety plan?
Have a written Hazard Communication Program?
Yes No Yes No
5. Identify by name and title the person within your firm directly responsible for your firm's safety program: Phone:
6. How often do you hold site safety meetings for field supervisors?
7.
8. How often do you conduct safety inspections?
Who performs this inspection?
9. Do you have orientation for new hires?
If yes, does it include:
Head Protection Eye Protection Hearing Protection Respiratory Protection Safety Belt and Lifeline (Fall Protection)
Scaffolding/Work Platform, Competent Person Perimeter Guarding/Floor, Wall and Roof Openings Housekeeping Fire Protection First-Aid Emergency Procedures – Rescue/Evacuation Toxic Substances Trenching and Excavation, Competent Person Signs, Barricades, Flagging Electrical Safety, Lockout/Tagout Procedures Rigging and Crane Safety Hazard Recognition
Weekly Monthly Never Bi-Weekly As Required
How often do you hold craft “tool box” safety meetings?
Weekly Monthly Never Bi-Weekly As Required
Rev 1.3, 04/01/2017 3
10. Do you have a program for newly hired/promoted foremen? Yes No
If yes, does it include:
Safe Work Practices
Methods of Safety Supervision Toolbox Meetings Emergency Procedures First-Aid Accident Investigation Fire Protection and Prevention New Worker Orientation
QUALITY ASSURANCE
Check one of the following boxes:
LEVEL 1
Contractor has a documented quality assurance program.
LEVEL 2
Contractor has a documented Quality Assurance Program that adequately addressed the quality requirements applying to work normally performed.
LEVEL 3
Contractor currently does not have a documented Quality Assurance Program, but has successfully performed construction activities at the Ames Laboratory.
LEVEL 4
Contractor currently does not have a documented Quality Assurance Program, and has not previously performed construction activities at the Ames Laboratory.
If you check the block in either 1 or 2 above, please enclose a copy of your Quality Assurance Manual.
Rev 1.3, 04/01/2017
Check all blocks that apply to this contract:
(1) Work to be performed by your Company
(2) Work to be performed by a Sub-Contractor to your Company
1 2 Site Work 1 2 Thermal and Moisture Protection 1 2 Furnishings
Demolition Waterproofing Cabinets and Casework Earthwork Insulation Window Treatment Site Improvements Fireproofing Furniture and Accessories Landscaping Preformed Siding Paving and Surfacing Flashing and Sheet Metal Special Construction
Roofing (General) Concrete Shingles and Roofing Tiles Clean Rooms
Preformed Roofing Insulated Rooms Cast-in Place Concrete Membrane Roofing Radiation Protection Precast Concrete Pre-engineered Structures Cementitious Decks Doors and Windows Liquid and Gas Storage Tanks Restoration and Cleaning Industrial/Process Control Systems
Metal Doors and Frames Fire Suppression/Supervisory Systems Masonry Wood and Plastic Doors
Special Doors Mechanical Unit Masonry Entrances and Store Fronts Stone Metal Windows General Restoration Wood and Plastic Windows Insulation
Special Windows Special Process Piping Systems Metals Hardware and Specialties Plumbing and Sewerage
Glazing Fire Protection General Power or Heat Generation Structural Metal Framing Finishes Air Distribution Joists Decking Miscellaneous and Ornamental
Lath and Plaster/Drywall Acoustical Treatment Wood Flooring Stone and Brick Flooring Resilient Flooring Carpeting Painting Wall Covering
Controls and Instrumentation
Rev 1.3, 04/01/2017
1 2 Wood and Plastics
Rough Carpentry Heavy Timber Construction Prefabricated Structural Wood Finish Carpentry Architectural Woodwork
Conveying Systems
Elevators Hoists and Cranes Lifts Material Handling Systems
1 2 Equipment
Waste Handling Equipment Water Supply and Treatment Equipment Communication Systems Fluid Waste Disposal and Treatment Equipment Laboratory Equipment
1 2 Electrical
General Substations Primary Distribution Secondary Distribution Lighting Cathodic Protection Controls
| APPENDIX D - AMES LABORATORY CONTRACTOR SAFETY & QUALITY ASSURANCE INFORMATION QUESTIONNAIRE |
| Check one of the following boxes: |
| LEVEL 1 |
| LEVEL 2 |
| LEVEL 3 |
| LEVEL 4 |
(1) Work to be performed by your Company
File details come from the government source that posted it. Updated .