About this file

This is a Direct Labor Burden Calculation form issued by the State of Colorado Office of the State Architect, State Buildings Program, for a construction project involving the Colorado Department of Agriculture. The project, designated 2027-034M26, concerns Insectary Foundation Repair and requires submission of the labor burden calculation prior to execution of any construction agreement. The form mandates that contractors and major subcontractors (including electricians, plumbers, mechanical contractors, excavators, millwork, concrete, and block layers) each submit one completed Labor Burden Calculation Sheet detailing the percentage composition of total labor overhead, including payroll taxes, pension costs, health insurance, dental insurance, life insurance, and other specified benefits paid by the contractor to employees on their payroll.

The calculated Labor Burden percentage must be mutually agreed upon by both the contractor and the Principal Representative and will be incorporated into the contract as part of Exhibit A. This percentage will serve as the basis for calculating any future Change Order Proposals under SC-6.312. The State reserves the right to require backup documentation confirming all information included in the calculation. The form, issued in August 2023, includes fields for contractor/subcontractor name and itemized breakdown of burden components, with the total labor burden percentage to be entered upon completion.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATE OF COLORADO

OFFICE OF THE STATE ARCHITECT

STATE BUILDINGS PROGRAM

DIRECT LABOR BURDEN CALCULATION

Institution/Agency:
Colorado Department of Agriculture
Project No./Name:
2027-034M26 / Insectary Foundation Repair

This form is required to be submitted for review prior to execution of a construction agreement.

List items below by the percentage of what makes up the total labor overhead; Items include benefits that a contractor pays to employees on their payroll. Examples include taxes, pension cost, health and dental insurance etc. The Labor Burden percentage must be agreed to by both the contractor and Principal Representative and will be included in the contract as part of Exhibit A and will be used in the calculation of any future Change Order Proposals (SC-6.312) Line 2.

Major sub-contractors defined as electricians, plumbers, mechanical contractors, excavators, millwork, concrete, block layers etc. Please provide one (1) Labor Burden Calculation Sheet per contractor and for each sub-contractor. These labor burdens shall be used in the calculation of any future Change Order Proposals (SC-6.312) Line 10.

State reserves the right to require back-up confirmation of all information included in this calculation.

State Form SBP–6.18 Issued 8/2023 image1.jpg image2.emf

Microsoft_Excel_Worksheet.xlsx Sheet1

Contractor/Subcontractor Name:

Percent of Salary Paid

Payroll Taxes

Pension Costs

Health Insurance

Dental Insurance

Life Insurance

Other (Specify) Description: _________________________

Other (Specify) Description: _________________________

Total Labor Burden Percentage: 0%