This document appears to be a California Water Resources Control Board Stormwater Multiple Application and Report Tracking System (SMARTS) cover page for a construction project with an erosivity waiver. The project has a designated construction window from April 15th, 2026 to October 15, 2026, and is associated with Water Discharge Identification (WDID) number 3 44W006134 and Order Number 2022-0057-DWQ.

While the document provides limited details about the specific project, it indicates a regulated construction activity with environmental oversight, suggesting the need for stormwater management and erosion control measures during the specified six-month construction period. The involvement of the California Water Resources Control Board implies strict compliance requirements for managing potential environmental impacts during the construction process.

View the file

Other files for this state and local contract opportunity

Other files attached to LEE ROAD TRAIL - PHASE 1, newest first.
File Type Posted
Revised_EXHIBIT_B_AGREEMENT_REVISION_Federal_Wage_Rate_Determination_ADDENDUM_NO._1.pdf PDF
Revised_Plans_Addendum_No._1.pdf PDF
County_of_Santa_Cruz_Encroachment_Permit_23-017_signed.pdf PDF
County_of_Santa_Cruz_Encroachment_Permit_23-017_signed.pdf PDF
20'_Trail_Easement_Map.pdf PDF
20'_Trail_Easement_Map.pdf PDF
APPENDIX_C_-_Erosivity_Waiver.pdf PDF
APPENDIX_B-_Materials_accepted_by_certificate.pdf PDF
APPENDIX_B-_Materials_accepted_by_certificate.pdf PDF
APPENDIX_A_-_GEOTECHNICAL_REPORT_Pacific_Crest.pdf PDF
DBE_Goal_REquired_documents_5_calendar_days_from_bid_opening.pdf PDF
APPENDIX_A_-_GEOTECHNICAL_REPORT_Pacific_Crest.pdf PDF
APPENDIX_D-_PROJECT_PERMITS_AND_APPROVAL_DOCUMENTS.pdf PDF
APPENDIX_A_-_GEOTECHNICAL_REPORT_Pacific_Crest.pdf PDF
APPENDIX_D-_PROJECT_PERMITS_AND_APPROVAL_DOCUMENTS.pdf PDF
DBE_Goal_REquired_documents_5_calendar_days_from_bid_opening.pdf PDF
APPENDIX_D-_PROJECT_PERMITS_AND_APPROVAL_DOCUMENTS.pdf PDF
APPENDIX_B-_Materials_accepted_by_certificate.pdf PDF
APPENDIX_C_-_Erosivity_Waiver.pdf PDF
Post-Bid_Contract_Documents.pdf PDF
Post-Bid_Contract_Documents.pdf PDF
Post-Bid_Contract_Documents.pdf PDF
TECHNICAL_SPECIFICATIONS_Mesiti_and_Miller.pdf PDF
PLANS.pdf PDF
PLANS.pdf PDF
PLANS.pdf PDF
TECHNICAL_SPECIFICATIONS_Mesiti_and_Miller.pdf PDF
TECHNICAL_SPECIFICATIONS_Mesiti_and_Miller.pdf PDF
Bid_Guarantee_Bond_Form.pdf PDF
Agreeement_for_Marco_to_Populate_Lee_Road_Trail_Phase_1.docx DOCX document
Bid_Guarantee_Bond_Form.pdf PDF
Agreeement_for_Marco_to_Populate_Lee_Road_Trail_Phase_1.docx DOCX document
Agreeement_for_Marco_to_Populate_Lee_Road_Trail_Phase_1.docx DOCX document
Bid_Guarantee_Bond_Form.pdf PDF
02_Contract_Documents.docx DOCX document
Project_Labor_Agreement.pdf PDF
Project_Labor_Agreement.pdf PDF
02_Contract_Documents.docx DOCX document
Project_Labor_Agreement.pdf PDF
02_Contract_Documents.docx DOCX document
Show all 40

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

EROSIVITY WAIVER WAS ISSUED

TO THIS PROJECT.

Construction Window April 15th, 2026 to October 15, 2026

WDID # 3 44W006134

ORDER # 2022-0057-DWQ