Appendix B - Statement of Work.docx.docx

DOCX document 2 MB Posted

Attached to
ANL Smart Labs Test and Balancing Services Federal contract opportunity
Solicitation number
1-B156-P-00400-00
Issued by
Department of Energy Office of Science

View the file

Other files for this federal contract opportunity

Other files attached to ANL Smart Labs Test and Balancing Services, newest first.
File Type Posted
Register of Wage Determinations.pdf PDF
On-Site Work (High)-05-JUN-2020.PDF.PDF PDF
Appendix A-Labor Hour-21-JAN-2019.PDF.PDF PDF
Appendix D8-29-JUN-2020.PDF.PDF PDF
Enclosure 5 Instructions to Offerors.doc DOC document
SCA Wage Flyer2009.pdf.pdf.pdf PDF
PARIS_Enclosure No 4--Evaluation Criteria.doc.doc DOC document
Request for Proposal .doc DOC document
PARIS_Enclosure No 3--Pricing Proposal Format.docx.docx DOCX document
DRAFT Sub-Contract Labor Hour .doc DOC document
PARIS_Special Cl-SCA Price Adj-Multi-21-JUL-2021.pdf.pdf PDF
Special Cl-SCA over 2500-26-JUN-2015.PDF.PDF PDF
Special Cl-Minimum Wage-26-JUN-2015.PDF.PDF PDF
Reps and Certs ANL-70B.doc DOC document
Sample Specific Assignment.docx.docx DOCX document
Show all 15

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Appendix “B”

Argonne National Laboratory Statement of Work

ANL Smart Labs – Test and Balancing Services

August 17, 2021

May 7th, 2021

Contents

Introduction2
Scope of Work2
Recurring Tasks4
Typical Labor Support8
Required Professional Credentials /Skills9
Fee Schedule10
Evaluation and Selection Criteria10
Submission Requirements and Questions11
Information Provided by Argonne National Laboratory11

ANL Smart Labs

TAB - BPA

10 | P a g e

Introduction

The building Infrastructure Services (IS) department is responsible for operating and maintaining buildings on the Argonne National Laboratory campus. In conjunction with the Project Management Organization (PMO), the Sustainability Group, the Facilities (FAC) group, and the Environmental, Safety, and Health Division (ES&H), IS has been tasked with operating buildings as energy efficiently and safely as possible. The services requested below for ASHRAE Standard 110 fume hood testing and airside/waterside system balancing will help Argonne National Lab achieve these goals established.

Scope of Work

1. Initial Tasks

a. Post Award Meeting Five working days following contract award, meet with Argonne to discuss contract details. At this meeting, discuss a process for authorizing, changing, invoicing, and closing specific assignments issued under the Blanket Purchase Agreement (BPA). Also at the meeting obtain copies of Argonne’s drawing and document numbering standards and templates.

b. Job Safety Analysis (JSA) At the Post Award Meeting discuss with Argonne the types of work tasks contemplated under this contract that will involve field investigation and data collection and the requirements for completing a High Risk Job Safety Analysis (Argonne Form ANL-209H). See Argonne High Risk Work by Contractors on the Argonne Site Supplemental Conditions, ANL-366L for further information.

2. Recurring Tasks

The following tasks are frequently required for most BPA assignments. Some minor requirements may be occasionally waived, at Argonne’s discretion, depending on project specific circumstances.

· Respond to Specific Assignment Request – To begin the process, Argonne will send a scope of work containing sufficient information for the consultant to begin preparing a scope, schedule, and cost estimate.

· The consultant will respond to Argonne by preparing a proposal containing the task scope of work, schedule and estimated cost.

· Following acceptance of the proposal by both parties, Argonne will issue a specific assignment and the consultant will obtain a Job Safety Analysis (JSA). The type of JSA required will vary depending on the task depicted in each individual Call.

· Call Scope of Work Tasks (refer to the following section for a comprehensive list)

· Argonne National Laboratory utilizes the Earned Value Management System to assess project performance. Because of this, ANL requires the Consultant to submit a “billing profile” projecting invoicing throughout the duration of the project.

· For any tools required to perform testing of building systems, Argonne National Laboratory requires a Tool Inspection procedure to take place. ANL’s Project Manager assigned will provide more information to the Consultant in order to ensure compliance.

Scope of Work Task

Argonne National Laboratory may issue individual Calls for one or more of the services depicted in the following list.

1. Laboratory Fume Hood Performance Testing

Perform fume hood performance testing according to ASHRAE 110-2016. Testing can be subcontracted out to a firm that is certified to perform ASHRAE 110-2016 tests.

a. Deliverables

i. The results of hood performance testing can be communicated in multiple ways. The following outline (sections 1.b. through 1.i) includes major points that are often incorporated into a report describing performance testing using this standard. The outline is only a suggestion to ensure completeness of the report.

ii. Design criteria (defined by the owner (Argonne), hood specifications, or test documents)

1. Sash design position or positions (ANL PROC-210 is 16” above airfoil)

2. Average face velocity

3. Acceptable range of face velocities

4. Average face velocity for sash at 25% and 50% of the design hood opening

5. Performance rating

6. Sash movement effect performance rating

7. For VAV hoods:

a. VAV speed of response time

b. VAV time to steady state

8. For auxiliary air hoods only: the percentage of auxiliary air supply

b. General

i. Test site, owner, reason for testing

ii. Investigator, date, project number or identifier

c. Hood information

i. Hood type, including sash type

ii. Hood manufacturer and model

iii. Controller type, make and model

iv. Location (room number) and identification (hood number)

d. System information

i. Exhaust system description

ii. Supply air description

iii. Record general settings during testing (inquired from building Maintenance)

e. Laboratory configuration

i. Hood location

ii. Supply and exhaust systems

iii. Room activity

iv. Room sketch or reference to drawings

f. Test equipment

i. Velocity probes

ii. Smoke visualization methods (local and large-volume smoke generation)

iii. Tracer gas detector

iv. Mannequin

g. Calibration (methods, frequency, and results)

i. Detector

ii. Ejector

iii. Velocity instruments

h. Test conditions

i. Sash opening heights depths

ii. Clutter in hood

iii. Baffle position (slot size)

iv. Background (zero) testing

i. Hood monitor

i. Type

ii. Current reading at 16” sash opening

iii. Percentage difference from measurement

iv. Threshold to low alarm measurement/setpoint

v. Threshold to high alarm measurement/setpoint (for VAV)

vi. Record calibration changes (if any)

j. Test Results

i. Face velocity readings

1. Grid description

2. Average face velocity

3. High and low grid readings

4. Face velocity control tests (for VAV systems)

5. VAV response tests

a. VAV speed of response

b. VAV time to steady state

ii. Smoke observation

1. Description of methods

2. Observation

a. Local visualization challenge

b. Large-volume visualization challenge

iii. Tracer gas results

iv. Provide Pass/Fail results (ANSI Z9.5)

v. Sash movement effects

vi. Peripheral scan

k. Factors affecting hood performance (if an explanation of results is indicated)

i. Cross-drafts

ii. Activities in the room

iii. Thermal effects

iv. Short circuiting

l. Conclusions

i. Comparison to design criteria

ii. Recommendations for performance improvements

2. Balancing:

Argonne National Laboratory is comprised of a wide variety of building types and building systems. To ensure system performances, we need to monitor and identify system components that are out of tolerance. Balancing service requests will range in scope and size to include system heating, ventilating, and air-conditioning systems. All building system balancing services, measurement devices and practices, calibrating procedures, and reporting should comply with the profession’s best practices set forth by the following standards, or unless approved by Argonne:

- NEBB’s Procedural Standards for Testing Adjusting and Balancing of Environmental Systems, 9th edition, 2019.

-ASHRAE’s Standard 111-2008 (RA 2017): Measurement, Testing, Adjusting, and Balancing of Building HVAC Systems.

i. Air Balancing:

1. Preliminary system review

2. TAB plan creation

3. Establishing fan total airflow and characterization curves

4. Basic air system balancing procedures

5. Verifying airflow meter measurements and calibrating

6. Manipulation of damper positions and fan speeds

7. Constant volume supply systems

8. Multizone systems

9. Induction unit systems

10. Variable volume systems

11. Dual duct systems

12. Packaged DX Systems

13. Energy recovery wheels

14. Variable volume terminal unit systems

15. Fan coil units

16. Return air systems

17. Exhaust air systems

18. Duct leakage estimates

19. Laboratory fume hoods

20. Laboratory pressurization

21. Biosafety cabinets

22. Industrial exhaust hoods and equipment

23. Building static control methods

24. Stairwell pressurization testing

25. Elevator pressurization testing

ii. Water Balancing:

1. Preliminary system review and TAB plan creation which any of the following:

a. Variable and constant volume hydronic systems

b. Boilers

c. Chillers

d. Cooling towers

e. Valves

f. Primary and secondary system loops

g. Pumps

h. AHU and Terminal Coils

i. Heat exchangers

2. Establishing pump totals and characterization curves

3. Hydronic system testing

4. Verifying flow meter measurements and calibrating

5. Hydronic system balancing via manipulation of balancing valves and pump speeds

b. Deliverables

i. Preliminary TAB plan

1. Outlines the project scope of work, to be reviewed by Argonne before work is begun

2. Description of testing instrumentation and methods that will be used to execute the scope of work.

3. Sample test reports.

4. Instrument calibration certificates

ii. Final TAB report with applicable field notes and drawings

Typical Labor Support

Typical support expected of the disciplines which may be needed in the general areas of engineering, project management and project support are described below:

a. Category 1 – TAB Technician Typical support from a TAB Technician may include:

· Collaborate with engineers, contractors, and ANL project team members.

· Develop detailed testing and balancing plans.

· Perform testing and balancing activities according to TABB, NEBB, ASHRAE standards.

· Develop and issue detailed balancing reports.

· Local 73 - Apprentice, Journeyman, Foreman, Superintendent

· All work will be performed during standard business hours.

b. Category 2 – Project Management Typical support from a project manager may include:

· Coordination and completion of projects.

· Set deadlines, assigns responsibilities, monitors and summarize progress of a project.

· Leads, direct, and/or provide oversight of field activities for some or all aspects of a project.

Required Professional Credentials /Skills Minimal requirements for labor categories are described below. Qualified personnel shall have strong knowledge and implementation skills in specific technical areas as defined by the individual work orders. Excellent oral and written communication skills, the ability to use a personal computer (including standard office software applications and waste-related databases), and good interpersonal skills are required for all assignments.

a. Category 1 – TAB Technician

· TABB - Certified

· NEBB – Certified

i. Testing, Adjusting & Balancing (TAB)

ii. Vibration Measurement (VM)

iii. Sound Measurement (SM)

iv. Fume Hood Testing (FHT)

v. Cleanroom Performance Testing (CPT)

· Prior experience with laboratory spaces

· ANL Specific training requirements

i. Contractor Safety Orientation (ESH382)

ii. Radiological Worker II

· Training provided by Argonne.

· Training typically takes 6 hours.

iii. Class IV - Working Near Asbestos (not provided by Argonne)

b. Category 2 – Project Management Project Management is comprised of various engineering, scientific, and business disciplines. The following level is required:

· Project Manager – Requires a BS or BA degree in preferably engineering, science or business and 9-12 years relevant experience or a Master’s degree and 5-8 years relevant experience. Relies on experience and judgment to plan and accomplish goals. Leads and directs the work of others. Project Management Professional certification and Professional Engineer license desired.

Information Provided by Argonne National Laboratory

· EXHIBIT A: ANL - Example ASHRAE 110 Report

EXHIBIT A: ANL - Example ASHRAE 110 Report image2.jpg image3.jpg image4.jpg image5.jpg image1.jpeg