Appendix B SOW.docx

DOCX document 52 KB Posted

Attached to
Scaffolding Design and Assembly for Facility Decommissioning
Solicitation number
5-B185-Q-00586-00
Issued by

About this file

This document is an Appendix B Statement of Work (SOW) for the Building 361 LINAC Decommissioning Project at Argonne National Laboratory. The project involves designing and erecting scaffolding in two pre-accelerator enclosures (rooms K018 and K017) to facilitate the disassembly of legacy voltage multiplier and ion source generator components from a decommissioned neutron source facility. The scaffolding must meet strict safety standards, including OSHA requirements, with specific design criteria such as load-bearing capacity, stability, guardrails, and access methods.

The project is solicited under Department of Energy Office of Science Request for Quote (RFQ) Number 5-B185-Q-00586-00, with a period of performance from September 2024 to December 2024. The contractor will be responsible for complete scaffolding design, erection, inspection, and removal, including submitting detailed documentation like approved job safety analyses, training records, and scaffolding designs. The solicitation will be evaluated using a lowest-price, technically acceptable methodology, with proposal responses due by 5:00 PM CST on June 25, 2025. All work will be performed at Argonne National Laboratory's Building 361, with normal business hours between 7:00 am and 3:30 pm, Monday through Friday.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

APPENDIX B – SOW for <Project Title> Page 4 of 5

Statement of Work

Project title
Building 361 LINAC Decommissioning Project
Version created date
Revision 0

April 22, 2025

Project No.
PRJ1010390
Version #
0
Period of Performance
September 2024 – December 2024
Version status
Current

Description:

Design and erect scaffolding in two pre-accelerator enclosures to allow worker access for disassembly of legacy voltage multiplier and ion source generator. Work will be performed in one room at a time.

Building 361 Scaffolding Statement of Work

SOW for Building 361 LINAC Decommissioning Project Page 2 of 10

1Background3
2Scope3
3Objectives4
4Tasks6
5Deliverables8
6Quality Assurance9
7Government-Owned Property9
8Security9
9Place of Performance9
10Period of Performance9
11Attachments9
SOW for Building 361 LINAC Decommissioning ProjectPage 3 of 5

Background The Intense Pulsed Neutron Source (IPNS) was an accelerator-based spallation neutron source facility dedicated to condensed matter research at Argonne National Laboratory (ANL). IPNS was shut down in December 2007 after 26 years of operation.

The H- ion source and associated equipment are housed in the terminal of a 750Kev Cockcroft-Walton pre-accelerator. The decommissioning of the facility will largely involve dismantling and removing the accelerator operational components and instruments. Selective demolition of the facility components and support equipment will be accomplished by conventional methods that have been used on decommissioning projects at Argonne.

Limited access, elevations, and space constraints necessity the construction of a scaffolding system to provide a safe working surface at elevations to permit worker access to equipment for disassembly.

Scope The contractor shall furnish all labor, equipment, materials, supplies, guarantees and warranties, transportation, qualified supervision, and any other items necessary to complete the work described herein. All work shall be performed in accordance with all provisions of applicable law, regulation or code and the specifications included in this package. All work shall be performed during normal business hours, between 7:00 am – 3:30 pm, Monday through Friday. If necessary, additional hours will be scheduled as needed and as mutually agreed upon. The contractor is expected to protect all work and staging areas during the course of the work.

Scaffolds shall be designed by a qualified person and shall be constructed in accordance with that design.

Site Inspection It is expected that the Contractor has visited the site and has become thoroughly acquainted with all conditions relative to the site, work location and all other matters which might affect the work to be performed. Bidder's proposals shall include all incidental items as required to complete the work specified or shown in the contract documents.

Supervision By Contractor The Contract stipulates that the Contractor shall, at all times during the progress of the work, provide a competent supervisor. This supervisor shall be vested with the necessary authority to direct and schedule the work of the Subcontractors, who may be engaged in the work and represent his/her firm in matters that may be referred to him/her by the authorized Laboratory representative.

Safety The Contractor shall be responsible for ensuring a safe and healthful work environment, compliance with the applicable OSHA and DOE standards and for the supervision, coordination and safe execution of the work. The Contractor shall at all times follow established safety procedures as contained in the Contractor’s Safety and Implementation Program and Job-Safety Hazard Analysis as well as facility and operation-specific safety procedures. Additionally, the individual must follow safe work practices, comply with permit requirements, immediately report to the supervisor any conditions that may lead to an incident, and participate in appropriate training for job assignments.

All scaffolding used on the project shall be erected and used in accordance with requirements specified in 29 CFR 1926 Subpart L. Each scaffold and scaffolding component shall be inspected by Argonne once it is brought on site, prior to erection. Rejected items shall be removed from the worksite. When scaffolding is required for a job, a competent person is to provide guidance for erecting scaffolds. Workers erecting scaffolding shall be trained and qualified in the type of scaffolding being erected and be familiar with 29 CFR 1926 Subpart L requirements.

When a scaffold work level is 4 feet or more above a walking/working surface, whether it is used for construction or non-construction work, workers on the scaffold must use approved fall protection. Fall protection may be achieved with the use of a body harness and lanyard, or with the use of guardrails (top and midrails) and toe boards.

Objectives Scaffolding design is a critical component in ensuring both safety and efficiency. The design shall meet all Argonne requirements, comply with safety standards, and accommodate project needs.

Needs and Requirements The scope of work, being performed and the specific requirements of the project require the ability to access equipment components at elevations. The work requires manual disassembly and handling of the voltage multiplier and ion source generator components.

Design must provide allowance for necessary hoisting and lifting of material and equipment from elevations.

The height and reach needed for the scaffolding must allow access all work areas effectively. Platforms and walkways shall be as wide as feasible and at least 18 inches (46 cm) wide and shall be protected from fall hazards by the use of guardrails.

Load Requirements: The scaffolding will need to support workers, tools, materials, and any dynamic loads.

Stability and Rigidity: Design for stability, using diagonal bracing and ensuring proper foundation support, including leveling and reinforcing if necessary.

Access and Egress: Include safe and convenient access methods, such as stairs and ladders.

Guardrails and Safety: Incorporate guardrails and toe boards.

Design Criteria

1. Standards and Codes: Adhere to all site, local, national, and international scaffolding standards and regulations.

Load Limits: Clearly define and communicate load limits for each part of the scaffolding.

Inspection: Plan for regular inspections to ensure the scaffolding remains in good condition and compliant with safety standards.

Design Documentation

1. Drawings and Plans: Provide detailed drawings and plans showing the scaffolding dimensions, height, and layout, and components.

Specifications: Include material specifications, load calculations, and assembly instructions.

Installation and Dismantling

1. Procedure: Outline the procedures for safe erection and dismantling, including any specific requirements.

Qualified Personnel: Ensure that installation and dismantling are carried out by qualified and experienced personnel.

Design Review

1. The scaffolding design shall be submitted to Argonne Project Manager. Argonne review to include engineering evaluations and worker safety and health approval.

Each case of scaffold installation shall have its own design.

Tasks

1. Completed and Approved design for scaffold construction in room K018.

2. Approved JSA and training records for personnel assigned to perform work. Notice to Proceed as described in the Agreement.

3. Mobilization of equipment and materials.

a. Equipment and material deliveries shall be coordinated with Technical Representative, staging and lay down areas shall be designated by Argonne.

b. Freight elevator from ground level loading dock to lower service floor level is in adjacent Building 360, with clear access to building 361 K018.

c. If needed hoisting and rigging assistance shall be provided by Argonne. Material and equipment must be made ready for safe hoisting by the contractor to the satisfaction of the operator.

4. Erection of scaffolding per the approved design room K018.

a. After each scaffold is erected, the competent person shall inspect it before initial use. If the scaffold is not compliant, correct deficiencies.

b. If the scaffold is compliant, obtain an inspection tag, sign it, and place it on the scaffold. An independent Argonne competent person will make a final inspection.

c. If scaffold passes the inspection, the Argonne competent person signs the tag and places it on the scaffold. Workers shall not use a scaffold that does not have a tag.

d. The competent person must tag the scaffold in accordance with its allowed use:

i. A green tag indicates that the scaffolding is in full OSHA compliance and is safe to use. 29 CFR 1926 Subpart M provides fall protection requirements.

ii. A yellow tag indicates that the scaffolding is incomplete, missing some part that is required by 29 CFR 1926 Subpart L, or some other recognized hazard exists. Any restrictions imposed must be identified and written on the back of the tag.

iii. A red tag indicates that the scaffolding must not be used under any circumstances until it is repaired and tagged with a green or yellow tag by a competent and independent competent person.

e. Scaffold users shall inspect scaffolding before each use and after any incident or modification (no matter how slight) that could affect the scaffold’s integrity to verify that the scaffold is in a safe and usable condition.

f. If the scaffold has been damaged or is no longer safe, remove the green or yellow tag, apply a red tag, and have discrepancies corrected.

Scaffold users shall have attended and successfully completed training in the hazards of scaffold erection and use. Users must read and follow the requirements posted on a scaffold tag. If the requirements are not understandable, consult the scaffold competent person for clarification. If the scaffold appears damaged, inadequate, or deficient in any way, immediately remove the scaffold tag and contact the scaffold competent person.

5. Removal of existing non-compliant scaffolding in room K018.

6. Completed design for scaffold construction in room K017

7. Disassembly and remove scaffolding from K018.

8. Erection of scaffolding per the approved design room K017.

9. Disassembly and remove scaffolding from K017.

10. Demobilization equipment, material, and contractor generated waste.

Deliverables Deliverables

1. Corporate documents per Agreement Approved High Risk Job Safety Analysis, ANL-209H.

Training and certification records for personnel performing work.

Approved scaffolding design for each instance of erection.

Timing All necessary documentation required received and approved thirty (30) day after award.

Quality Assurance Inspection or surveillance requirements

a. Each scaffold and scaffolding component shall be inspected once it is brought on site, prior to erection. Rejected items shall be removed from the worksite.

b. After the scaffold is erected, the competent person shall inspect it before initial use. If the scaffold is not compliant, correct deficiencies.

c. If the scaffold is compliant, obtain an inspection tag, sign it, and place it on the scaffold.

d. An independent Argonne competent person will make a final inspection.

Government-Owned Property The Laboratory will make existing utilities such as water, steam and electricity available to the Contractor without cost where such utilities are conveniently located with respect to the work site. The Contractor must provide all materials, labor and equipment necessary for extending existing utilities to the point of use. The Contractor will be held responsible for the proper installation, operation and maintenance of temporary utilities and must adhere to all uniform codes governing such installations. Upon completion of the work, the Contractor shall remove all temporary utility lines and restore existing utilities to the original condition as directed by the Laboratory Security No unique security requirements or access to Argonne Business Information Systems are required for contract performance.

Place of Performance The performance will occur at Argonne National Laboratory Building 361.

Period of Performance Within thirty (30) days after signed agreement shall meet all necessary requirements for Notice to Proceed, to include scaffolding design.

Attachments Attachment 1 - Drawings Attachment 2 – Photos K017 & K018 image1.jpeg