Appendix B - Drawings.pdf

PDF 1 MB Posted

Attached to
PMAA, SEPU, Juniper Road Chip Seal, Maintenance, C27PU1
Solicitation number
DQ1 PMAA 2027000012 2
Issued by
El Paso County, Colorado Springs City, Colorado

About this file

This file contains construction drawings for the Juniper Road Chip Seal project at Lake Pueblo State Park in Colorado, prepared by Colorado Parks and Wildlife Southeast Region Office. The project encompasses road resurfacing and striping work on Juniper Road from station JR 36+40 to JR 113+00, a total distance of approximately 76,600 linear feet. The scope includes asphalt paving totaling approximately 20,838 square yards across six segments, with extensive centerline and edge striping in various configurations including solid yellow, broken yellow, and double solid yellow markings. The project also includes ADA-compliant parking lot striping at the Pike View parking lot (station JR 64+75) with designated accessible parking spaces, access aisles, and crosswalk bars. The drawings consist of a cover sheet with general notes and six site plan sheets (SP-1 through SP-6) that detail the pavement layout, striping patterns, and construction specifications at a scale of 1 inch equals 100 feet.

The general notes establish comprehensive contractor responsibilities including site surveying and construction staking, utility location and protection, traffic maintenance throughout construction, debris removal, soil compaction to specified standards (95% for structures and earthwork, 90% for remainder), and protection of trees and vegetation. All work must conform to Colorado Department of Transportation Construction Standards and Specifications, and the contractor is responsible for obtaining all required permits from appropriate agencies. The contractor must maintain a full set of plans and specifications on-site at all times and provide adequate safety measures including flagging, barriers, and temporary fencing for vehicle and pedestrian traffic. Any property damage or defective work resulting from unsatisfactory conditions becomes the contractor's responsibility, and asphalt segments with wavy edges, humps, or dips must be removed and replaced at contractor expense.

View the file

Other files

File Type Posted
Appendix C - SC622PerfBond (DNR) (1).docx DOCX document
Appendix A - 2018 CPW GCs 071818 FINAL.pdf PDF
BID DOCUMENTS 071426.pdf PDF
Appendix D - SC6221LMBond (1).docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Ju ly

3, D ra w in gs .d w g

D R

A W

N

D E

S

IG

N E

D

D A

TE

FI

LE

S C

G

S C

G

P R

O

JE

C T

C O

V

S H

E E

T C

O V

E R

S H

E E

T

JU

N

IP

E

R R

O A

D C

H

IP

S E

A L

C O

LO

R

A D

O P

A R

K S

W

IL

D

LI

FE

S ou th ea st R eg io n O ffi ce

S in to n

R oa d

C ol or ad o S pr in gs , C

O

P ho ne

9)

-5

F ax

9)

-5 w ild lif e.

st at e.

co .u s pa rk s.

st at e.

co .u s

La ke

P ue bl o

S ta te P ar k

P ue bl o

R es er vo ir R d.

P ue bl o, C

O

R E

V

IS

IO

N

C O

M M

E N

T D

A

TE

R E

V

1 2 3 4 5

C

P U

1. THE COLORADO PARKS AND WILDLIFE PROJECT MANAGER WILL ASSIST THE CONTRACTOR IN GENERAL PAVEMENT LAYOUT AND IDENTIFYING FINISH GRADES. CONTRACTOR IS RESPONSIBLE FOR ANY SURVEYING/CONSTRUCTION STAKING THEY FEEL NECESSARY FOR CONSTRUCTION OPERATIONS. STRIPING LAYOUT IS THE SOLE RESPONSIBILITY OF THE CONTRACTOR.

2. CONTRACTOR SHALL BE FAMILIAR WITH THE EXISTING CONDITIONS. BID SHALL BE BASED ON ACTUAL SITE CONDITIONS.

3. CONTRACTOR SHALL VERIFY LOCATION AND BURY DEPTHS OF ALL UTILITIES ON THE SITE. EXISTING UTILITIES SHALL BE PROTECTED FROM DAMAGE BY THE CONTRACTOR. DAMAGED UTILITIES SHALL BE REPAIRED AT THE CONTRACTOR'S

EXPENSE.

4. ALL CUT AND FILL SLOPES SHALL BE GRADED AS SHOWN IN THE DETAILS. MAXIMUM SLOPE AND CROSS-SLOPE OF ASPHALT PAVEMENT AT ACCESSIBLE PARKING AREAS IS 2% AND FOR LANDSCAPED/NATURAL AREAS THE MAXIMUM SLOPE IS 4:1

UNLESS OTHERWISE NOTED.

5. ALL WORK AND MATERIALS SHALL CONFORM TO COLORADO DEPARTMENT OF TRANSPORTATION CONSTRUCTION STANDARDS

AND SPECIFICATIONS.

6. THE CONTRACTOR SHALL OBTAIN ALL REQUIRED PERMITS FROM THE APPROPRIATE AGENCIES AND JURISDICTIONS (AT THE CONTRACTOR'S EXPENSE). IT IS NOT EXPECTED THAT THERE WILL BE DISTURBANCE OUTSIDE OF THE EXISTING FOOTPRINT

OF THE ROAD OR LOT.

7. THE CONTRACTOR SHALL MAINTAIN THROUGH TRAFFIC, ON ALL ROADWAYS AT ALL TIMES, INCLUDING SIGNAGE, STAFF AND

FLAGGING. PARK STAFF WILL NOT BE AVAILABLE FOR TRAFFIC CONTROL.

8. ANY DAMAGE TO PROPERTY WILL BE REPAIRED AT THE CONTRACTOR'S EXPENSE.

9. CONTRACTOR SHALL PROTECT ALL TREES AND OTHER VEGETATION NOT DESIGNATED FOR REMOVAL. ALL DISTURBED AREAS SHALL BE PROPERLY PREPARED, SEEDED AND MULCHED AS DESCRIBED IN THE SPECIFICATIONS.

10. CONTRACTOR WILL BE RESPONSIBLE FOR PROVIDING ADEQUATE SAFETY AND SECURITY OF THE SITE DURING CONSTRUCTION, INCLUDING BUT NOT LIMITED TO FLAGGING, BARRIERS AND TEMPORARY FENCING FOR VEHICLE/ROAD AND

PEDESTRIAN/TRAIL TRAFFIC.

11. ALL RUBBLE AND DEBRIS WITHIN THE PROJECT LIMITS OF WORK WILL BE HAULED FROM SITE AND DISPOSED OF PROPERLY AT

CONTRACTOR'S EXPENSE UNLESS OTHERWISE NOTED IN THE PLANS OR SPECIFICATIONS.

12. THE CONTRACTOR SHALL HAVE ONE (1) FULL SET OF THE PLANS AND SPECIFICATIONS AT THE JOB SITE AT ALL TIMES.

13. SOIL COMPACTION REQUIREMENTS BENEATH STRUCTURES, AND EARTHWORK ARE 95% OF THE MAXIMUM DRY DENSITY MEASURED IN ACCORDANCE WITH ASTM D 698 (STANDARD PROCTOR) UNLESS OTHERWISE NOTED. SOILS WITHIN REMAINDER OF THE PROJECT SHALL BE COMPACTED TO 90% OF THE MAXIMUM DENSITY, MEASURED AS REFERENCED.

14. ALL PROPOSED FINISH GRADES SHALL ABUT EXISTING CURBS, PAVEMENT, ETC. IN BOTH LINE AND GRADE. THE CONTRACTOR

SHALL NOTIFY THE OWNER'S REPRESENTATIVE IMMEDIATELY OF ANY DISCREPANCIES.

15. CONTRACTOR MUST PROTECT NEWLY POURED CONCRETE FROM VANDALS AND OTHER PERILS. DAMAGED CONCRETE WILL BE

REMOVED AND REPLACED AT CONTRACTOR'S EXPENSE.

16. CONTRACTOR SHALL BACKFILL IMPROVEMENTS TO MATCH CROSS SECTION DETAIL HEREIN. CONTRACTOR WILL STORE NEEDED FILL DURING GRADING OPERATIONS AND FURNISH AT CONTRACTOR'S EXPENSE, ANY ADDITIONAL FILL NEEDED IN

ORDER TO PROPERLY BACK FILL IMPROVEMENTS.

17. STARTING WORK CONSTITUTES ACCEPTANCE OF THE CONDITIONS UNDER WHICH WORK IS TO BE PERFORMED. AFTER SUCH ACCEPTANCE, THE CONTRACTOR SHALL AT HIS EXPENSE, BE RESPONSIBLE FOR CORRECTING ALL UNSATISFACTORY AND

DEFECTIVE WORK RESULTING FROM SUCH UNSATISFACTORY CONDITIONS.

18. THE CONTRACTOR WARRANTS THAT HIS EMPLOYEES, AGENTS, AND SUBCONTRACTORS POSSESS THE EXPERIENCE, KNOWLEDGE, AND CHARACTER NECESSARY TO QUALIFY THEM INDIVIDUALLY FOR THE PARTICULAR CONSTRUCTION TECHNIQUES THEY PERFORM UNDER THIS CONTRACT. THE CONTRACTOR SHALL INSURE THAT ALL CONSTRUCTION BE PERFORMED IN STRICT COMPLIANCE WITH OSHA, STATE AND LOCAL HEALTH AND SAFETY CODES.

19. CONTRACTOR ASSUMES THE RESPONSIBILITY FOR PROVIDING SMOOTH HORIZONTAL AND VERTICAL CURVATURE ON ASPHALT SEGMENTS. ASPHALT SEGMENTS WITH WAVY EDGES, HUMPS, AND/OR DIPS WILL BE REMOVED AND REPLACED AT THE

EXPENSE OF THE CONTRACTOR.

20. THE PARK MAY (AT THEIR DISCRETION) CHOOSE TO SALVAGE AND RETAIN SOME ITEMS DESIGNATED FOR REMOVAL AND DISPOSAL. HOWEVER, THE CONTRACTOR SHOULD ASSUME REMOVAL OF ALL ITEMS AS PART OF THEIR BID.

21. The State of Colorado is committed to providing equitable access to our services to all. Please contact our Colorado Parks and Wildlife Accessibility Specialist (accessdnr@state.co.us or 303-297-1192) for personalized accessibility assistance with project construction layouts and details below. We will contact you directly within two business days. Visit our accessibility webpage for more information and services, including AIRA, our free service for blind and low-vision users.

Lake Pueblo State Park Juniper Road Chip Seal

July 13, 2026

GENERAL NOTES:SHEET INDEX

COV COVER

SP-1 SITE PLAN - JR -36+40 TO JR 48+00

SP-2 SITE PLAN - JR 48+00 to JR 60+00 SP-3 SITE PLAN - JR 60+00 to JR 70+00 SP-4 SITE PLAN - JR 70+00 to JR 86+00 SP-5 SITE PLAN - JR 86+00 to JR 100+00 SP-6 SITE PLAN - JR 100+00 to JR 113+00

VICINITY MAP

DESIGN CRITERIA

CDOT - Colorado Department of Transportation 2012 Standard Specifications for Roads and Bridge Construction.

MUTCD - Manual on Uniform Traffic Control Devises AASHTO - American Association of State Highway and Transportation Officials ADAAG - Americans with Disabilities Act Accessibility Guidelines

JUNIPER ROAD

JR 36+40 TO JR 113+00

PRE-BID MEETING LOCATION

PIKE VIEW PARKING LOT

38.281335, -104.761848

JR 36+40

JR

+0

JR

, 3

6+00

JR

, 3

8+00

JR

, 4

0+00

JR

, 4

2+00

JR

, 4

4+00

JR

, 4

6+00

JR

, 4

8+00

JU

N

IP

E

R R

O A

D

28'-0"

J

R , 3

+4

B

A

SE

B

ID

I T

E M

C.L. STRIPING - STATION JR 36+40 TO JR

38+00

(2 X 160 L.F.) C.L. DOUBLE SOLID YELLOW

STRIPING.

C.L. STRIPING - STATION JR 38+00 TO JR 43+00

(1 X 500 L.F.) C.L. SOLID YELLOW STRIPING.

(1 X 500 L.F.) C.L. BROKEN YELLOW STRIPING.

C.L. STRIPING - STATION JR 43+00 TO JR 46+30

(1 X 330 L.F.) C.L. BROKEN YELLOW STRIPING.

ASPHALT ROAD - STATION JR 36+40 TO JR 48+00

(3,609 S.Y.)

C.L. STRIPING - STATION JR 46+30 TO JR 48+00

(1 X 170 L.F.) C.L. SOLID YELLOW STRIPING.

(1 X 170 L.F.) C.L. BROKEN YELLOW STRIPING.

EDGE OF ROAD STRIPING

STATION JR 36+40 TO JR 48+00

(2 X 1,160 L.F.) SOLID WHITE STRIPING

D ra w in gs .d w g

D R

A W

N

D E

S

IG

N E

D

D A

TE

FI

LE

S C

G

S C

G

P R

O

JE

C T

S P

-1

S H

E E

T

JU

N

IP

E

R R

O A

D C

H

IP

S E

A L

JR

, 3 6+ to

J R

, 4 8+

C O

LO

R

A D

O P

A R

K S

W

IL

D

LI

FE

S ou th ea st R eg io n O ffi ce

S in to n

R oa d C ol or ad o

S pr in gs

, C O

P ho ne

9)

-5

F ax

9)

-5 w ild lif e.

st at e.

co s.

st at e.

co

.u s

La ke

P ue bl o

S ta te P ar k

P ue bl o

R es er vo ir R d.

P ue bl o, C

O

R E

V

IS

IO

N

C O

M M

E N

T D

A

TE

R E

V

1 2 3 4 5

SCALE : 1" = 100'-0"

NORTH

100'50'

Ju ly

3, C

P U

, 4

8+00

JR

, 5

0+00

JR

, 5

2+00

JR

, 5

4+00

JR

, 5

6+00

JR

, 5

8+00

JR

, 6

0+00

JU

N

IP

E

R R

O A

D

28'-0"

C.L. STRIPING - STATION JR 48+00 TO JR 52+00

(1 X 400 L.F.) C.L. SOLID YELLOW STRIPING.

(1 X 400 L.F.) C.L. BROKEN YELLOW STRIPING.

C.L. STRIPING - STATION JR 52+00 TO JR 60+00

(1 X 800 L.F.) C.L. BROKEN YELLOW STRIPING.

ASPHALT ROAD - STATION JR 48+00 TO JR 60+00

(3,734 S.Y.)

EDGE OF ROAD STRIPING

STATION JR 48+00 TO JR 60+00

(2 X 1,200 L.F.) SOLID WHITE STRIPING

D ra w in gs .d w g

D R

A W

N

D E

S

IG

N E

D

D A

TE

FI

LE

S C

G

S C

G

P R

O

JE

C T

S P

-2

S H

E E

T

JU

N

IP

E

R R

O A

D C

H

IP

S E

A L

JR

, 4 8+ to

J R

, 6 0+

C O

LO

R

A D

O P

A R

K S

W

IL

D

LI

FE

S ou th ea st R eg io n O ffi ce

S in to n

R oa d C ol or ad o

S pr in gs

, C O

P ho ne

9)

-5

F ax

9)

-5 w ild lif e.

st at e.

co s.

st at e.

co

.u s

La ke

P ue bl o

S ta te P ar k

P ue bl o

R es er vo ir R d.

P ue bl o, C

O

R E

V

IS

IO

N

C O

M M

E N

T D

A

TE

R E

V

1 2 3 4 5

SCALE : 1" = 100'-0"

NORTH

100'50'

Ju ly

3, C

P

, 6

0+00

JR

, 6

2+00

JR

, 6

4+00

JR

, 6

6+00

JR

JR

JU

N

IP

E

R R

O A

D

28'-0"

JR, 64+75

APPROXIMATE LOCATION

OF EXISTING "PIKE VIEW"

PARKING LOT.

ADA STRIPING (INCLUDING 5' X 20'

ACCESS AISLE HATCH, SYMBOL AND

PAINTING CONCRETE WHEEL STOP BLUE.

125'-0"

72'-0"

PAVING

STOP BAR

(200 L.F.) YELLOW PARKING SPACE STRIPING.

C.L. STRIPING - STATION JR 60+00 TO JR 64+40

(2 X 440 L.F.) C.L. DOUBLE SOLID YELLOW

STRIPING.

C.L. STRIPING - STATION JR 65+10 TO JR 70+00

(2 X 490 L.F.) C.L. DOUBLE SOLID YELLOW STRIPING.

ASPHALT ROAD - STATION JR 60+00 TO JR 70+00

PLUS PARKING LOT

(3,844 S.Y.)

EDGE OF ROAD STRIPING

STATION JR 60+00 TO JR 70+00

(2 X 1,000 L.F.) SOLID WHITE STRIPING

D ra w in gs .d w g

D R

A W

N

D E

S

IG

N E

D

D A

TE

FI

LE

S C

G

S C

G

P R

O

JE

C T

S P

-3

S H

E E

T

JU

N

IP

E

R R

O A

D C

H

IP

S E

A L

JR

, 6 0+ to

J R

, 7 0+

C O

LO

R

A D

O P

A R

K S

W

IL

D

LI

FE

S ou th ea st R eg io n O ffi ce

S in to n

R oa d C ol or ad o

S pr in gs

, C O

P ho ne

9)

-5

F ax

9)

-5 w ild lif e.

st at e.

co s.

st at e.

co

.u s

La ke

P ue bl o

S ta te P ar k

P ue bl o

R es er vo ir R d.

P ue bl o, C

O

R E

V

IS

IO

N

C O

M M

E N

T D

A

TE

R E

V

1 2 3 4 5

SCALE : 1" = 100'-0"

NORTH

100'50'

Ju ly

3, C

P

JR

JR

JR

JR

JR

JUNIPER ROAD

28'-0"

JR

JR

JR

PROVIDE CLEAN TRANSITION AT

PAVEMENT TO REMAIN.

STOP BAR

C.L. STRIPING - STATION JR 70+00 TO JR 78+00

(1 X 800 L.F.) C.L. SOLID YELLOW STRIPING.

(1 X 800 L.F.) C.L. BROKEN YELLOW STRIPING.

C.L. STRIPING - STATION JR 82+00 TO JR 86+00

(2 X 400 L.F.) C.L. DOUBLE SOLID YELLOW

STRIPING.

C.L. STRIPING - STATION JR 78+00 TO JR 81+30

(2 X 330 L.F.) C.L. DOUBLE SOLID YELLOW

STRIPING.

ASPHALT ROAD - STATION JR 70+00 TO JR 86+00

(PLUS APRON)

(5,200 S.Y.)

EDGE OF ROAD STRIPING

STATION JR 70+00 TO JR 86+00

(2 X 1,600 L.F.) SOLID WHITE STRIPING

D ra w in gs .d w g

D R

A W

N

D E

S

IG

N E

D

D A

TE

FI

LE

S C

G

S C

G

P R

O

JE

C T

S P

-4

S H

E E

T

JU

N

IP

E

R R

O A

D C

H

IP

S E

A L

JR

, 7 0+ to

J R

, 8 6+

C O

LO

R

A D

O P

A R

K S

W

IL

D

LI

FE

S ou th ea st R eg io n O ffi ce

S in to n

R oa d C ol or ad o

S pr in gs

, C O

P ho ne

9)

-5

F ax

9)

-5 w ild lif e.

st at e.

co s.

st at e.

co

.u s

La ke

P ue bl o

S ta te P ar k

P ue bl o

R es er vo ir R d.

P ue bl o, C

O

R E

V

IS

IO

N

C O

M M

E N

T D

A

TE

R E

V

1 2 3 4 5

SCALE : 1" = 100'-0"

NORTH

100'50'

Ju ly

3, C

P

JR

JR

JR

JR

JR

JR

JR

JUNIPER ROAD

28'-0"

C.L. STRIPING - STATION JR 92+00 TO JR 100+00

(1 X 800 L.F.) C.L. SOLID YELLOW STRIPING.

(1 X 800 L.F.) C.L. BROKEN YELLOW STRIPING.

C.L. STRIPING - STATION JR 86+00 TO JR 92+00

(2 X 600 L.F.) C.L. DOUBLE SOLID YELLOW

STRIPING.

ASPHALT ROAD - STATION JR 86+00 TO JR 100+00

(4,356 S.Y.)

EDGE OF ROAD STRIPING

STATION JR 86+00 TO JR 100+00

(2 X 1,400 L.F.) SOLID WHITE STRIPING

D ra w in gs .d w g

D R

A W

N

D E

S

IG

N E

D

D A

TE

FI

LE

S C

G

S C

G

P R

O

JE

C T

S P

-5

S H

E E

T

JU

N

IP

E

R R

O A

D C

H

IP

S E

A L

JR

, 8 6+ to

J R

, 1

C O

LO

R

A D

O P

A R

K S

W

IL

D

LI

FE

S ou th ea st R eg io n O ffi ce

S in to n

R oa d C ol or ad o

S pr in gs

, C O

P ho ne

9)

-5

F ax

9)

-5 w ild lif e.

st at e.

co s.

st at e.

co

.u s

La ke

P ue bl o

S ta te P ar k

P ue bl o

R es er vo ir R d.

P ue bl o, C

O

R E

V

IS

IO

N

C O

M M

E N

T D

A

TE

R E

V

1 2 3 4 5

SCALE : 1" = 100'-0"

NORTH

100'50'

Ju ly

3, C

P

JR

JR

JR

JR

JR

JR

B

A S

E B

I D

I T

E M

JR

PROVIDE CLEAN TRANSITION AT

PAVEMENT TO REMAIN (TYP).

(5) CROSSWALK BARS -

ALIGN WITH PATH.

JUNIPER ROAD

28'-0"

EDGE OF ROAD STRIPING

STATION JR 100+00 TO JR 113+00

(2 X 1,300 L.F.) SOLID WHITE STRIPING

ASPHALT ROAD - STATION JR 100+00 TO JR 113+00

(4,045 S.Y.)

C.L. STRIPING - STATION JR 100+00 TO JR 108+00

(1 X 800 L.F.) C.L. BROKEN YELLOW STRIPING.

C.L. STRIPING - STATION JR 108+00 TO JR 112+00

(1 X 400 L.F.) C.L. SOLID YELLOW STRIPING.

(1 X 400 L.F.) C.L. BROKEN YELLOW STRIPING.

C.L. STRIPING - STATION JR 112+00 TO JR 113+00

(2 X 100 L.F.) C.L. DOUBLE SOLID YELLOW

STRIPING.

Ju ly

3, D ra w in gs .d w g

D R

A W

N

D E

S

IG

N E

D

D A

TE

FI

LE

S C

G

S C

G

P R

O

JE

C T

S P

-6

S H

E E

T

JU

N

IP

E

R R

O A

D C

H

IP

S E

A L

JR

, 1 to J

R , 1

C O

LO

R

A D

O P

A R

K S

W

IL

D

LI

FE

S ou th ea st R eg io n O ffi ce

S in to n

R oa d C ol or ad o

S pr in gs

, C O

P ho ne

9)

-5

F ax

9)

-5 w ild lif e.

st at e.

co s.

st at e.

co

.u s

La ke

P ue bl o

S ta te P ar k

P ue bl o

R es er vo ir R d.

P ue bl o, C

O

R E

V

IS

IO

N

C O

M M

E N

T D

A

TE

R E

V

1 2 3 4 5

C

P U

SCALE : 1" = 100'-0"

NORTH

100'50'

Sheets and Views
Drawings-cover
Drawings-SP1
Drawings-SP2
Drawings-SP3
Drawings-SP4
Drawings-SP5
Drawings-SP6

File details come from the government source that posted it. Updated .