This document contains a building systems functional test checklist and federal contract opportunity notice. The checklist outlines acceptance testing procedures for various life safety and emergency systems in a facility, including fire alarms, sprinklers, standpipes, fire pumps, gas detection, exit lighting, fire doors, air handlers, kitchen hood suppression, and signage. The related federal contract opportunity is a pre-solicitation notice for repair work on Facility 1362 at Aviano Air Base in Italy, with an estimated value between $500,000 and $1,000,000. Interested vendors must hold an active System for Award Management registration and Italian Statement of Authorization certification in category OG01. The solicitation is expected to be issued in January 2023.

View the file

Other files

File Type Posted
AVIANO MASTERSPECS 2020.pdf PDF
ASHE 21-1027 PSC.pdf PDF
ASHE 21-1027 CCEB.xlsx XLSX spreadsheet
ASHE 21-1027 DRAWINGS 40-71.pdf PDF
ASHE 21-1027 DRAWINGS 1-39.pdf PDF
ASHE 21-1027 TECH-SPECS.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REPAIR FAC.1362 FOR OHWS & LMOC PROJECT: ASHE 21-1027

FINAL (100%) TECHNICAL SPECIFICATIONS

ANNEX TO THE TECHNICAL SPECIFICATIONS

FACILITY SYSTEMS

FUNCTIONAL TEST

CHECKLIST

REPAIR FAC.1362 FOR OHWS & LMOC PROJECT: ASHE 21-1027

FINAL (100%) TECHNICAL SPECIFICATIONS

THIS PAGE LEFT INTENTIONALLY BLANK

Revision: 19 Jan 2021 1

FACILITY SYSTEMS

FUNCTIONAL TEST

CHECKLIST

PURPOSE:

This checklist provides actions to be taken when conducting functional operation checks of the following life and emergency systems: Fire alarms, sprinklers, standpipes, fire pumps, gas detection, exit & emergency lighting, exit passage, exit doors, air handler units, fire rated doors, wall penetrations, extinguishers, hood & duct extraction systems, and emergency signage. Of course not all systems may be installed in each facility. Operationally check all that apply to the facility.

Do not conduct the operational check without the presence of the installing contractor, project manager, and 31 CES/CEOEM Fire Alarm Maintenance

Contract QA.

A copy of this checklist must be provided to the appropriate project manager to ensure all outlined items will be included in the SOW. The project manager should forward a copy to the appropriate contractor.

Ensure the project manager will receive the final fire alarm testing documentation

IAW all applicable Italian Fire Standards and Laws outlined below. This is required for all facilities that are subject to C.P.I. (Italian Fire Prevention Certification

Program)

BUILDING NUMBER: ___________________________ DATE: ____________

PROJECT #:____________________________________________________________

Revision: 19 Jan 2021 2

1-FIRE ALARM AND MASS NOTIFICATION SYSTEM:

1. Ensure all devices are operational and transmit the fire alarm radio signal to

Aviano Fire Alarm Communications Center.

_________ Pull stations_________ Heat detectors _________Smoke detectors

_________ Duct detectors _______Alarm/horns _______ Strobes

_________ under floor smoke detectors ________ Sprinkler flow switches

_________ Supervisory devices _________ Stand pipes

2. _________ Shall notification of all alarm appliances occur within 10 seconds after the activation of an initiating device?

3. _________ Are evacuation pre-recorded messages preceded and followed by a minimum of two cycles of the emergency evacuation signal?

4. _________ Is the pre-recorded message in English and Italian?

5. _________ Do the fire alarm / mass notification speakers and strobes activate within 10 seconds after a fire alarm initiating device is activated?

6. _________ Are the fire alarm / mass notification system’s strobes sincronized?

7. _________ Test cross-zone detection feature if installed.

8. _________ Do all the alarms have the same tone?

9. _________ Are detectors installed in all areas? (see above ceiling tiles)

10. _________ Are detectors reachable for maintenance? (see above ceiling)

11. _________Are above ceiling detectors indicated with alarm visual repeaters?

12. _________Are above ceiling detectors on their own zone?

13. _________Are smoke detectors located at least 3 feet (1m) away from air diffusers?

14. _________Is FACP accessible? If not, acquire key to gain entrance to panel.

15. _________Does all indicator lights illuminate on annunciator and/or F.A.C.P?

16. _________Are proper resetting instructions and code located nearby the F.A.C.P?

17. _________Is there a building diagram indicating all zones and alarm devices near the F.A.C.P? Also, are all instructions written in English_______?

18. _________ Does the FACP annunciate alarm, supervisory and trouble condition?

19. _________ Does the FACP reflects accurate address or zones?

Revision: 19 Jan 2021 3

20. _________ Does the instruction reflects which utilities must be turned on after any given fire alarm activation?

EXPLAIN:___________________________________________

21. _________Is the F.A.C.P protected with a heat or smoke detector in general area?

22. _________Are batteries on F.AC.P and transmitter being disconnected for 5 minutes to verify system operability? (activate 1 or 2 devices at the most)

23. _________ Does the disconnection of the AC result in a trouble signal?

24. _________ Does the disconnection of the batteries result in a trouble signal?

25. ________ Are the batteries labeled with the date of manufacture?

26. ________ Are the batteries tested for 48 hours on stand by power followed by 15 minutes on alarm power.

27. _________Are all devices supervised for trouble indication. Disconnect random devices to test: _________Pull stations __________Heat detectors __________

Smoke detectors _______Duct detectors _________Alarm/horns____________

Strobes _________ Under floor smoke detectors _______ Sprinkler flow switches _______

28. _______Are batteries on F.A.C.P and MONACO transmitter disconnected to verify “BATTERY FAULT”?

29. ______Were battery tested with a tester to verify Volatage reading, 24 V?

30. _______Was a manual pull station activated for two minutes to verify battery level drop not less then 24 V?

31. _______Is a set of keys provided for manual pull station so as to perform required fire evacuation drills?

32. _______ Is the Fire Alarm System provided with an independent electrical line?

33. _______Is FACP’s electrical switch identified with a red tag reading FIRE

ALARM?

34. _______Is FACP’s electrical switch locked with suitable plastic padlock if located inside an electrical panel ?

35. _______ Is an emergency electrical power shut off located outside the main facility entrance?

36. _______ Is all wiring running into plastic or metal conduits?

Revision: 19 Jan 2021 4

37. _______ Is wiring supported independent of other wiring or equipment?

38. _______ EMERGENCY CONTROL FUNCTIONS (elevator recall, HVAC shut down, doors releasing mechanism).

39. _______Is a fire evacuation plan being posted by main entrance?

40. Does fire evacuation plan reflects the following?

a. Location of primary and secondary passageways_______

b. Location of F.A.C.P_________

c. Location of assigned portable fire extinguishers________

d. Location of manual alarm pull stations_______

e. Location of emergency shut off devices, A/C power______ Fuel______

Gas ______ Boiler room _____External gas or fuel tank_______

f. Location of rally and accountability points_______

g. Fire reporting numbers DSN 911, Commercial 0434-301-911_______

22.________Was record of testing provided to Project Manager IAW U.N.I 11224

“Prospetto” A-1, A-2, A-3, A- 4, B-1B-2.

23.________ Is a set of FA/FS Systems plans Provided to the FPO?

2-FIRE SPRINKLERS:

1. ________ Were flow switches tested through fire inspection test valve?

2. ________ Verify receipt of water flow activation in not more than 90 seconds from W-F activation of water motro gong.

3. ________ Is the discharge testing SPKR head located or fabricated in a way that does not create damage to the facility or property?

4. ________ Are end of line restrains installed at the end of each branch line?

5. ________ Was the system hydrostatically tested for 24 hours at a pressure not minor then 15 bar prior the final functional test?

6. ________ Was the system flushed prior testing?

7. ________ Bells activated? Radio signal to FD_____? Water motor gong_____?

8. ________ Was main drain checked for required flow reading?

9. ________ Was tamper switch checked on OS &Y valve?

10. ________ Are sprinkler installed in all areas? (see above ceiling)

11. ________ Are sprinkler heads located not less then 1.8 m (6ft) apart?

Revision: 19 Jan 2021 5

12. ________ Are heads of the right type_______? Pendant_____? Up-right_____?

13. ________ Are any of the sprinkler heads blocked or obstructed in any way?

14. ________ Check height of sprinkler heads from ceiling/obstructions.

15. ________ Are fire dept. connections at required height? Signage_______?

16. ________ Is riser location in a locked room? Was key provided to F.P.O._____?

17. ________ Is each riser identified to indicate which system it supplies?

18. ________ Is back flow preventer supervised ?

19. ________ Is a permanent signage install to identify the back flow preventer’s test valves?

20. ________ Is post Indicator Valve (P.I.V.) supervised if installed?

21. ________ Is padlock with key #21 provided for not supervised P.I.V?

22. ________ Are 6 extra sprinkler heads provided for every 36 heads installed?

23. ________ Are spare heads of the type installed?

24. ________ Is sprinkler wrench located inside extra sprinkler heads box?

25. ________ Are hydraulic calculations attached to the riser.

26. ________ Are all valves properly identified with required signage?

27. ________ Were tamper switches tested for radio connection and trouble alarm?

28. ________ Are proper anchors provided for sprinkler piping? (see above ceiling)

29. ________ Was record of testing provided Project Manager IAW UNI- EN

12845?

3-FIRE PUMPS:

1. _______Was the system pressurized for 2 hours prior to testing?

2. _______Was the pump houses inspected for proper ventilation and heating?

3. _______ Were all pump controls checked for damage?

4. _______ Were all pumps gauges checked for proper reading and operability?

5. Suction pressure gauge _______psi (bar)?

6. _______Are suction control valves sealed open?

7. Discharge pressure gauge___________ psi (bar)

8. _______ Are discharge line control valves sealed open?

9. Pump staring pressure from pressure switch in controller ______ psi (bar)

10. Pump run time from controller: ________minutes?

Revision: 19 Jan 2021 6

11. _______ Were the automatic controllers verified in the automatic (AUTO) setting? _______Were batteries verified for proper charging?

12. _______Was the system checked for water leakage?

13. _______ Start and churn to verify operability? ____unusual noise, vibration?

14. _______ Is the fire pump running alarm? ____Radio signal sent to FD?

15. _______ Was the exhaust system inspected for leaks?

16. _______ Is the jokey pump operational?

17. _______ Is the jokey pump controller power on?

18. _______ Is the jokey pump controller set on “ AUTO”

19. _______ Was operability of the relief valve checked?

20. _______Were the engine-driven pumps tested for a minimum of 30 minutes?

21. _______ Was the electric engine run up tested for a minimum of 10 minutes?

22. ELECTRIC FIRE PUMPS ONLY:

23. _______ Is the normal-phase pilot light “ON”?

24. _______ Is the reverse-phase pilot light “OFF”?

25. DIESEL FIRE PUMPS ONLY:

26. ______ Is diesel tank is 2/3 full? _____Is diesel engine oil level full?

27. ______ Are batteries fully charged?_____ Battery terminals clean?

28. ______ Is the engine-running-time meter recording pump operation properly?

29. ______ Is the diesel engine water level full?

30. ______ Are all water valves supervised and properly identified?

31. ______ Has battery been disconnected to verify trouble alarm activation?

32. ______ Was tested conducted on battery power mode?

33. ______ Were operating instructions provided to F.P.O.

34. ______ Was record of test provided to Project Manager IAW UNI 1028-1-2?

4-FIRE HYDRANTS:

1 _______ Was hydrant accessibility verified?

2________Were hydrant outlets slightly more than hand-tight?

3________Was the hydrant checked for leaks, bottom/top?

4________Were threads checked for damaged? _____Were threads lubricated?

Revision: 19 Jan 2021 7

5 ________Was hydrant opened and water flow verified for not less than 1 minute or till water became clear?

6 _______ Were bollards provided to protect hydrant from vehicular traffic?

5-STAND PIPES:

1. ______Was stand pipe system pressurized for two hours prior to testing?

2. ______W as the system checked for water leakage?

3. ______Was fire alarm activated upon stand pipe water discharge?

4. ______ Was radio signal being sent to FD Communication Center?

5. ______ Were stand pipes tested for 10 minutes verifying proper water flow?

6. ______ Is identification signage properly installed?

7. ______ Was record of test provided to Project Manager IAW UNI 10779?

6-CLEAN AGENT FIRE EXTINGUISHING SYSTEMS:

1. _______ Check hangers and supports, cylinders, manifolds, piping

2. Labels: _________Actual weight of gas ___________Date of test

3. _______ Manufacturing date ______________Hydrostatic test

4. _______ Cylinders Capacity ______________ Storage pressure

5. _______ Are cylinders, pipe work, steel work, checked for coating?

6. _______ What is the discharging count down?_________________

7. FUNCTIONAL TEST

8. _______ Were each agent storage containers release mechanism disabled?

9. _______ Were the agent release storage circuits reconnected to a functional device to indicate circuit activation as follow?

10. _______ For electrical circuits use 24-volt lamp, flashbulb or circuit breaker.

11. _______ For pneumatic circuits use pressure gauges

12. _______Were solenoid valves and nitrogen pressure switch tested for functional test?

12.__________Ensure all devices are operational and transmit a fire alarm radio signal to Aviano Fire Alarm Communications Center.

_________ Pull stations_________ Heat detectors _________Smoke detectors

_________ Duct detectors _______Alarm/horns _______ Strobes _________ under floor smoke detectors______ Were all devices tested on battery power?

Revision: 19 Jan 2021 8

13. ______ Is a second detector or second alarm circuit verified to ensure extinguishing system activation?

14. _______Was HWAC system shut down verified?

15. _______Were all manual extinguishing discharge pull stations tested?

16. _______Were all visual and acoustical devices activated?

17. _______ Were all interior and exterior warning luminescent panels flashing?

18. _______ Were all alarm signals verified in the Fire Alarm Control Panel?

19. _______Was MONACO radio transmission verified?

20. ______ Were all abort functions tested? EXPLAIN___________________

21. ______ Was the system tested on standby power?

22. ______ Were supervisory signals tested on standby power?

23. ______ Was the system tested for obstruction and continuity by discharging a

“puff” of compressed air or carbon dioxide?

24. ______ Was the FACP returned to normal operating condition?

25. ______ Were all agent storage containers reconnected?

22 ENCLOSURE INTEGRITY CHECK (FAN DOOR TEST)

26. _____ Are all AHU/ACs in the protected area shutted down?

27 ______ Is the affected sealed with “ Door Fan Test Panels /Plastic Sheet”?

28. ______Are all minute holes closed with the use of seal tape?

29. ______Is the Fan Door Test blower fitted on the panel?

30. ______ Was the fan switched on?

31. ______ Were all design details and area volume computations entered in the software?

32. ______ Was the room pressurized up to the test pressure as specified in the software?

33. ______ Were pressure and rates readings noted?

34. ______ Was the room depressurized and pressure & flow rates reading taken?

35. ______ Were the noted readings entered in room integrity software?

36. _____ The software will give the predicted leakage area in the room along with retention time.

37. _____ If the retention time is above 10 minutes the room passes the test.

Revision: 19 Jan 2021 9

38. ____ Was record of test provided to Project Manager IAW UNI EN 15004-1?

7-EXIT AND EMERGENCY LIGHTS:

1. _______ Test exit lights for operation. disconnect power and verify exit and emergency lights at the same time.

2. _______ Emergency lights shall be installed in all areas to include bathrooms, attics and maintenance utility rooms. Disconnect power and walk the building.

3. _______ Ares exit passageways indicated with directional arrows?

4. _______ Are emergency lights identified with a LED and a tag reading EL?

5. _______ Is the system provided with U.P.S? _______Self testing?______

6. _______ Does the system have a dedicated switch to perform a light check?

7. _______ Was record of test provided to Project Manager IAW UNI EN 1838?

8-GAS DETECTION SYSTEM:

1. _______ Is the boiler room provided with a gas detection system?

2. _______ Does the gas detection panel have written resetting instructions?

3. _______ Is there a yellow /orange visual and acoustical gas leak device installed outside the boiler room? Is it identified GAS ALARM_______?

4. _______ Is there a yellow anunciator panel in main general area which once activated reads GAS ALARM? __Is gas alarm tone different from fire alarm?

5. _______ Is gas shut off handle identified EMERGENCY GAS SHUT OFF”?

6. _______ Is gas cabinet reducers identified “NO SMOKING FLAMMABLE

GAS”? Is gas cabinet grounded______?

7. _______ Is the gas detection system local only, NOT connected to F.A.C.C.?

8. _______ Were gas detectors tested? Was gas flow interruption verified_____?

9. _______ Did external alarm activate? Did orange/yellow light turn on _____?

10. _______ Is the boiler room provided with an external electrical emergency shut off____?

9-EXIT AND EGRESS PASSAGGE WAYS:

1._______ Is panic hardware installed on high occupancies areas?

2._______ Does door with panic hardware swings in the direction of exit travel?

3._______ Is exit discharged flushed to the floor level?

Revision: 19 Jan 2021 10

4._______ Are panic hardware bars provided with a green arrow indicating where pushing force shall be apply?

5._______ Are panic hardware bars of that type flushed to the doors surface?

5._______ Are automatic doors capable to be pushed open in the event of power failure?

6._______ Do automatic doors have a sign on them indicating “IN CASE OF

FIRE PUSH TO OPEN”?

7________ Are the handrails at each stairway continuous with no gaps or brakes?

10-FIRE EXTINGUISHERS:

1._______ Are recessed or semi-recessed fire extinguishers cabinets provided?

2._______ Are fire extinguisher signs installed to indicate permanent location?

3._______ Are sufficient number of fire extinguishers located in the facility?

4._______ Italian or U.S. extinguishers? EXPALIN_______________________

11-FIRE RATED DOORS / SLIDING DOORS:

1._______ Are fire doors properly rated for the area they are protecting?

2._______ Are all closure devices operational? Do they latch closed_______?

4._______ Are fire door and windows provided with magnetic holders?

5. ______ Will the magnetic holder release the door upon activation of the FAS?

5._______ Is the space between door and floor level properly sealed?

6._______ Are supporting frames sturdy attached to the door structure?

7._______ Are extra fusible links (5 every 20 doors) available for F.P.O?

8. SLIDING DOORS:

9. ______ Are doors provided with two redundant photocell motors?

10.______ Do photocells detect motion within a 180 degree radious?

11.______ Are doors provided with an alarm in case of power failure?

12.______ Will doors remain blocked open in case of power failure?

13. ______ Are bilingual “SLIDE TO OPEN” “SCORRERE PER APRIRE” signs installed?

14.______ Are signs in between one arrow point to the left and one arrow pointing to the right?

15. ______ Dose signage have green backgroung and white lettering?

Revision: 19 Jan 2021 11

16. ______ Is a manual release mechanism provided to manually open the doors in case of the opening system failure?

17. ______ Is the release device accessible for everyone to include persons below

5 ft (1.53m) in height?

18.______ Is all personne working in the affected area trained on S/A basis on how to properlu operated the doors in case of power failure or emergency condition?

19. ______ Will doors be maintained as per the manufacturing instructions?

12-WALL SEPARATION:

1.________ Ensure fire wall have NO openings or penetrations to breach the fire integrity. _____Are penetrations sealed with fire stopping material?

2.________ Is stairwell fire integrity breached?

3._______ Are fire rated walls properly red color marke “FIRE RATED WALL”?

13-AIR HANDLING UNITS:

1._______ Does air handling unit(s) shut down upon activation of any given fire alarm system component?

2._______ Are duct detectors properly identified with a label reading D.D?

3._______ Shall HWAC units be reset after fire alarm activation?

EXPLAIN: __________________________________________

14-DEEP FAT FRYERS:

1._______ Were deep fat fryer calibrated if installed?

15-FIRE DAMPERS:

1.______ Are fire dampers electronically connected to F.A.C.P for reset?

2_______Is fire damper location identified on ceiling with a label reading FD?

16-EMERGENCY SIGNAGE:

1._______ Is emergency signage provided IAW D. Lgs. n.81/08 and 10/03/98?

_______ Fire extinguishers _______manual pull stations________ stand pipes _______gas shut off ______fuel shut off ______main electrical shut off _______boiler room ______gas cabinets _____fire department connection_______inspector test valve______sprinkler valves_____electrical cabinets.

17-HOOD AND DUCT SUPPRESSION SYSTEMS:

Revision: 19 Jan 2021 12

2. _______ Was date of last hydrostatic test verified?

3.________Was manual release activated?

4.________ Was fusible link activated?

5.________ Were all extinguishing system manual pull stations tested?

6. ________Was building fire alarm activated?

7. ________Was MONACO radio signal received at the ECC?

5. _______Power and gas shut off activated?

6. _______ Was connection to shut down supply air to exhaust hood verified?

7. _______ Was connection to shut down electric power to receptcles under the hood verified?

7. _______ Are hoods and pull stations identified with same ID number?

8. ______ Is the testing label affixed on the hood indicating the testing date?

9. ______ Testing must be performed by liquid discharge utilizing the manufacture’s recommended flushing concentrate, to demonstrate equal distribution of chemical and no leakage at pipe joints.

Reference: UFC 3-600-01, Chapter 9-12.2

10. Was documentation of testing provided to Project Manager IAW UNI 11198?

18-BUILDING ACCESS:

1. Is there a sufficient free path large enough to permit FD apparatus access?

2. Is a KNOX BOX provided with a spare key inside?

3. Are spare keys or combination provided for gates access?

REMARKS:

Revision: 19 Jan 2021 13

PROJECT MANAGER SIGNATURE: DATE:

CONSTRACTOR SIGNATURE: DATE:

FIRE PREVENTION INSPECTOR SIGNATURE: DATE: