About this file
This is Amendment No. 1 to an advertised contract for Paulding County, Georgia's 2026 Safety Action Program – Thermoplastic Line Striping Project (Bid #26018-1511). The project involves thermoplastic striping and raised pavement markers on fourteen county roads. The amendment, issued on January 23, 2026, precedes the February 6, 2026 letting date and clarifies project scope through responses to bidder inquiries. Key clarifications include confirmation that only items listed in the bid schedule quantities will be striped with no additional elements such as arrows, stop bars, or crosswalks; that Paulding County Department of Transportation (PCDOT) will clip and blade roadway edges prior to edge line installation; and that work on Coach Bobby Dodd Road will consist solely of refreshing existing striping within the project limits rather than adding new striping in previously unmarked areas.
The amendment includes a corrected cover sheet with a fixed bid number and requires bidders to acknowledge receipt by checking the appropriate certification space. Bidders are responsible for incorporating any necessary changes in ink on their proposals. No pricing terms, set-asides, incumbent information, or specific funding amounts are detailed in this amendment document.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 5 _ Advertisement 1_9_26.pdf | ||
| Amendment No_ 2.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
01/23/2026
AMENDMENT TO ADVERTISED CONTRACT
PROJECT NAME: 2026 Safety Action Program – Thermoplastic Line Striping Project
BID # 26018-1511
COUNTY: PAULDING
AMENDMENT NUMBER: 1
LETTING DATE: February 6, 2026
THE FOLLOWING AMENDMENTS ARE HEREBY MADE TO THIS CONTRACT.
THE BIDDER IS RESPONSIBLE FOR MAKING ANY NECESSARY CHANGES IN
INK IN THE PROPOSAL. BIDDER SHALL ACKNOWLEDGE THIS AMENDMENT
BY CHECKING THE APPROPRIATE SPACE ON THE AMENDMENT
CERTIFICATION PAGE.
ITEMS INCLUDED IN THIS AMENDMENT:
**Fixed Bid number on cover sheet. New Cover sheet attached.
Questions received by bidders. Responses shown in RED.
1. Will only the items included in the bid schedule be striped? (IE. No arrows, stop bars, crosswalks, etc.)
R: Only items in the bid package quantities are to be included.
2. Will the County clip/blade the edges of the roadway prior to installing edgelines?
R: PCDOT will clip/blade the edges of the roadway prior to edge line installation.
3. Coach Bobby Dodd Road does not appear to have ever had striping outside of the intersection with SR 6. Is it the intention of this project to only re-stripe existing markings or will striping be add that did not previously exist?
R:Coah Bobby Dodd Rd is currently striped within the project limits listed in the bid documents. Project will consist of refreshing existing striping included on the bid quantities.