This is Amendment #2 to a Request for Proposal issued by the South Carolina Department of Transportation (SCDOT) seeking consultant services for Pavement Quality Index (PQI) development and analysis. The solicitation does not require the selected consultant to perform hands-on work within the agency's Highway Pavement Management Application (HPMA) software system, nor does it anticipate coordination with a separate PMS vendor replacement project. The pre-proposal conference is scheduled for April 15, 2021 at 10:00 AM via WebEx, with questions from offerors due by April 16, 2021 at 12:00 PM. Proposals must be submitted online by May 6, 2021 at 2:30 PM, with one original and one redacted copy required. The award is expected to be posted on June 01, 2021. Offerors must hold their proposals open for a minimum of thirty calendar days following the opening date.
The amendment clarifies that remote access to the HPMA software will be provided only through webinar platforms such as Microsoft TEAMS, while onsite access can be arranged as needed. The PDI model was developed using windshield survey data rather than fully automated surveys. Additionally, a new compliance requirement has been added prohibiting contractors from procuring or obtaining telecommunication or video surveillance equipment, services, or systems produced by Huawei Technologies Company, ZTE Corporation, Hytera Communications Corporation, Hangzhou Hikvision Digital Technology Company, or Dahua Technology Company, or any subsidiaries or affiliates thereof, in accordance with 2 CFR 200.216. Redacted proposals must be submitted even if offerors have no confidential, trade secret, or protected information to ensure proper handling of future Freedom of Information Act requests.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment C.pdf | ||
| Solicitation 5400021146.pdf | ||
| Attachment A.pdf | ||
| Attachment B.pdf | ||
| Attachment E.pdf | ||
| Attachment D.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
State of South Carolina
Request for Proposal
AMENDMENT #2
Solicitation:
Date Issued:
Procurement Officer:
Phone:
E-Mail Address:
Mailing Address:
5400021146 04/19/2021
EMMETT KIRWAN
(803) 737-0676 KirwanEI@scdot.org SCDOT Procurement Office PO Box 191 Columbia SC 29202-0191
DESCRIPTION: Pavement Quality Index Consultant USING GOVERNMENTAL UNIT: SC Department of Transportation
SUBMIT YOUR OFFER ON-LINE AT THE FOLLOWING URL: http://www.procurement.sc.gov SUBMIT OFFER BY (Opening Date/Time): 05/06/2021 @ 14:30 (See "Deadline For Submission Of Offer" provision) QUESTIONS MUST BE RECEIVED BY: 04/16/2021 12:00:00 (See "Questions From Offerors" provision) NUMBER OF COPIES TO BE SUBMITTED: One Online plus One Redacted Copy Online CONFERENCE TYPE: Pre-Proposal
DATE & TIME: 04/15/2021 10:00:00
(As appropriate, see "Conferences - Pre-Bid/Proposal" & "Site Visit" provisions)
LOCATION: WebEx. Contact Emmett Kirwan at KirwanEi@scdot.org for WebEx link.
AWARD &
AMENDMENTS
Award will be posted on 06/01/2021. The award, this solicitation, any amendments, and any related notices will be posted at the following web address: http://www.procurement.sc.gov
You must submit a signed copy of this form with Your Offer. By signing, You agree to be bound by the terms of the Solicitation. You agree to hold Your Offer open for a minimum of thirty (30) calendar days after the Opening Date. (See "Signing Your Offer" provision.)
NAME OF OFFEROR
(full legal name of business submitting the offer)
Any award issued will be issued to, and the contract will be formed with, the entity identified as the Offeror. The entity named as the offeror must be a single and distinct legal entity. Do not use the name of a branch office or a division of a larger entity if the branch or division is not a separate legal entity, i.e., a separate corporation, partnership, sole proprietorship, etc.
AUTHORIZED SIGNATURE
(Person must be authorized to submit binding offer to contract on behalf of Offeror.)
DATE SIGNED
TITLE
(business title of person signing above)
STATE VENDOR NO.
(Register to Obtain S.C. Vendor No. at www.procurement.sc.gov)
PRINTED NAME
(printed name of person signing above)
STATE OF INCORPORATION
(If you are a corporation, identify the state of incorporation.)
OFFEROR'S TYPE OF ENTITY: (Check one) (See "Signing Your Offer" provision.)
___ Sole Proprietorship ___ Partnership ___ Other_____________________________
___ Corporate entity (not tax-exempt) ___ Corporation (tax-exempt) ___ Government entity (federal, state, or local)
COVER PAGE - ON-LINE ONLY (MAR. 2015)
mailto:KirwanEI@scdot.org http://www.procurement.sc.gov/ mailto:KirwanEi@scdot.org http://www.procurement.sc.gov/
AMENDMENTS TO SOLICITATION (JAN 2004)
(a) The Solicitation may be amended at any time prior to opening. All actual and prospective Offerors should monitor the following web site for the issuance of Amendments: www.procurement.sc.gov (b) Offerors shall acknowledge receipt of any amendment to this solicitation (1) by signing and returning the amendment, (2) by identifying the amendment number and date in the space provided for this purpose on Page Two, (3) by letter, or (4) by submitting a bid that indicates in some way that the bidder received the amendment. (c) If this solicitation is amended, then all terms and conditions which are not modified remain unchanged. [02-2A005-1]
QUESTIONS FROM OFFERORS - AMENDMENT (JUN 2017)
THE SOLICITATION IS AMENDED AS PROVIDED HEREIN. INFORMATION OR CHANGES RESULTING
FROM QUESTIONS WILL BE SHOWN IN A QUESTION-AND-ANSWER FORMAT. ALL QUESTIONS
RECEIVED HAVE BEEN REPRINTED BELOW. THE “STATE’S RESPONSE” SHOULD BE READ
WITHOUT REFERENCE TO THE QUESTIONS. THE QUESTIONS ARE INCLUDED SOLELY TO PROVIDE
A CROSS-REFERENCE TO THE POTENTIAL OFFEROR THAT SUBMITTED THE QUESTION.
QUESTIONS DO NOT FORM A PART OF THE CONTRACT; THE “STATE’S RESPONSE” DOES. ANY
RESTATEMENT OF PART OR ALL OF AN EXISTING PROVISION OF THE SOLICITATION IN AN
ANSWER DOES NOT MODIFY THE ORIGINAL PROVISION EXCEPT AS FOLLOWS: UNDERLINED TEXT
IS ADDED TO THE ORIGINAL PROVISON. STRICKEN TEXT IS DELETED. [02-2A097-1]
1. Does SCDOT expect the selected offeror to perform “hands on” work within the agency’s HPMA?
No
2. Is Stantec currently supporting SCDOT’s HPMA and if so, are they precluded from proposing on this project?
Stantec is supporting the HPMA software. However since we don’t expect offeror’s to provide any hands on software assistance, we haven’t excluded Stantec or any other vendors from proposing on this project.
3. SCDOT has a separate procurement underway to replace their existing Asset Management Systems, including PMS (HPMA). To what extent does SCDOT anticipate that the selected offeror will be required to coordinate with the selected PMS vendor?
We don’t expect the selected offeror to coordinate with the selected PMS vendor. SCDOT anticipates that any updates to the PQI will not be reliant on any particular software.
4. Does SCDOT anticipate the scope of services for this solicitation to include pavement management consulting services beyond PQI calculations?
SCDOT does not anticipate this, but can’t rule it out if any recommended PQI updates approved by the SCDOT committee requires some additional assistance by the selected offeror.
5. If we do not have any information in our proposal that we consider as "Confidential," "Trade Secret," or "Protected" do we still have to submit a redacted copy of our proposal?
You do not have to find items to redact, however a copy labeled “Redacted” is necessary in order to ensure the correct proposal response is released when the agency receives a FOIA request for documents related to this procurement.
6. Will the selected consultant have access to the HPMA software for review?
SCDOT can arrange this while the selected consultant is on site. However remote access will only be allowed via a webinar such as Microsoft TEAMS.
7. Was the PDI model developed using distresses from manual foot-on-ground/windshield survey or fully automated surveys?
Windshield surveys
The following clause is added to SECTION VII – TERMS AND CONDITIONS – B. SPECIAL
COMPLIANCE WITH 2 CFR 200.216
In accordance with 2 CFR 200.216, Contractors, in the performance of this Contract, are prohibited from procuring or obtaining telecommunication or video surveillance equipment, services, or systems produced by:
• Huawei Technologies Company or ZTE Corporation (or any subsidiary or affiliate of such entities).
• Hytera Communications Corporation, Hangzhou Hikvision Digital Technology Company, or Dahua Technology Company (or any subsidiary or affiliate of such entities).
File details come from the government source that posted it. Updated .