Amendment 2.pdf
PDF 77 KB Posted
- Attached to
- New Sewer Installation
- Solicitation number
- 22-494DOT-FINAD-B-24991
- Issued by
- Edgar County, Illinois
About this file
This document is an amendment to a solicitation issued by the Illinois Department of Transportation (IDOT) District 7 for the installation of a new sewer line. The amendment provides responses to vendor questions regarding the project scope, including the sewer line length, depth, connection to an existing structure, cleanout types and locations, backfill and bedding requirements, disposal of materials, and locating and connecting drain lines. The project must be completed prior to ground freeze, and normal business hours are 6:30 a.m. to 3:30 p.m.
The contract opportunity is for the installation of a new sewer line within the state of Illinois. Permits required for the project need to be obtained by the vendor from the City of Effingham. Storage may be available on-site if needed. The vendor will be responsible for providing their own loading and offloading equipment for the disposal of materials, which will occur off-site at a designated location.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Scope of Work~1.docx | DOCX document | |
| Walk Through Information~5.docx | DOCX document | |
| Overhead View A.pdf | ||
| Amendment 1.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Amendment #2 – REVISED Vendor Questions and IDOT Responses Illinois Department of Transportation District 7 ‐ New Sewer Line Installation BidBuy Bid # 22‐494DOT‐FINAD‐B‐24991
Responses are in red.
1. 325' 6" Sewer Line ‐ is this storm sewer, do you want this PVC? Yes.
2. How deep? Contractor’s discretion. Approximately 2’ – 4’ at the building.
3. Are we out letting this into an existing structure? Yes, there is an existing structure.
4. 6 Clean outs ‐ what type of clean outs and what locations? Will need to be suitable for heavy duty equipment to drive over.
5. Backfill Aggregate ‐ what type of backfill? Are you requiring bedding material?
Contractor discretion that is best for IDOT to top with asphalt at a later date.
6. Cap existing sewer ‐ are we capping the existing line that is running to Wabash? if so, how big and how deep? Yes. Capping the existing line to Wabash. It will be either a 6 or
8 in cap and it will be less than 6 ft deep.
7. Disposal of Materials ‐ Is the disposal on site or off? If off site is there any sites available? Disposal will be off site and vendor will need to locate the disposal site.
Disposal will be off site if vendor wishes to use it. It will be at 1900 W. National Ave, Effingham. Vendor must supply own loading and off‐loading equipment for disposal of materials.
8. Locate & connect drain lines ‐ any existing plans to show locations and how deep? IDOT is unsure if there are plans, if we locate plans, we will update this information.
9. Permits ‐ any anticipated? Vendor will need to contact City of Effingham and find out what permits will be needed to complete this project.
10. Normal business hours? 6:30 a.m. – 3:30 p.m.
11. Is this project to be completed this year? Work must be completed prior to ground freeze.
12. Will there be enough line to hook or will they need to run new? This will depend on where they run the new line.
13. Will there be storage available for supplies needed for job? Yes, if needed.