AMENDMENT _2 _ 4400 City of Vidalia Fixed Gen.pdf
PDF 146 KB Posted
- Attached to
- Generators & Generator Installation
- Solicitation number
- PE-73850-NONST-2026-000000015
- Issued by
- Terrell County, Georgia
About this file
This is Amendment #2 to a Request for Bids issued by the City of Vidalia for procurement of generators, solicitation number 4400-0066, dated November 12, 2025. The amendment provides essential electrical specifications for nine generator installation sites across the city's water and wastewater infrastructure, as well as emergency services facilities. The sites include three water wells, three lift stations, two fire stations, and one additional lift station, with generators required to support peak demand and running load requirements that vary by location. Peak demand specifications range from 10.6 kW at Lift Station 7 to 126 kW at Wells #1 and #2, while running loads range from 9.6 kW to 119 kW across the operational sites. Fire Station 1 and Fire Station 2 have running load specifications of 12 kW and 16 kW respectively, with original sizing of 25 kW for both locations.
This amendment clarifies and standardizes the electrical load requirements that were not fully specified in the original solicitation documents, ensuring bidders have accurate technical specifications necessary to submit compliant proposals. The addition of peak demand and running load data for all sites provides the foundational information required for generators to be properly sized and selected for each critical infrastructure location. No additional information regarding pricing terms, set-asides, contract duration, bid submission deadlines, or award timelines is contained within this amendment document.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT #2
Request for Bids (RFB)
CITY OF VIDALIA
4400-0066 - City of Vidalia Generators
Amendment Date: November 12, 2025
Bidders for the above referenced project shall take note of the following revisions, additions, deletions, clarifications, etc. relative to the solicitation, which in accordance with the Contract Documents shall become a part of and have precedence over anything shown or described otherwise.
Please note the following regarding the Request for Bids for 4400-0066 - City of Vidalia Generators.
1. The Peak Demand and Running Load has been added for all sites:
a. Site 1 - Well #1: Peak Demand - 126 kW, Running Load - 119 kW
b. Site 2 - Well #2: Peak Demand - 126 kW, Running Load - 119 kW
c. Site 3 - Well #3: Peak Demand - 108.3 kW, Running Load - 99.2 kW
d. Site 4 - Lift Station 4: Peak Demand - 56.9 kW, Running Load - 41.4 kW
e. Site 5 - Lift Station 7: Peak Demand - 10.6 kW, Running Load - 9.6 kW
f. Site 6 - Lift Station 15: Peak Demand - 99.6 kW, Running Load - 81.1 kW
g. Site 7 - Lift Station 31: Peak Demand - 55.9 kW, Running Load - 41.4 kW
h. Site 8 - Fire Station 1: Peak Demand not available. Running load is 12 kW and originally sized for 25 kW.
i. Site 9 - Fire Station 2: Peak Demand not available. Running load is 16 kW and originally sized for 25 kW.
1/1