Amendment 01_W91QF426BA0110001 SF 30 Answers.pdf
PDF 1 MB Posted
- Attached to
- Amendment 01 Elevator Replacement Bldg. 246
- Solicitation number
- W91QF426_Elevator
About this file
This is a Standard Form 30 (SF 30) Amendment of Solicitation for federal contract W91QF426BA011, issued by the U.S. Army Corps of Engineers at Fort Leavenworth, Kansas on September 2, 2026. The amendment extends the response due date from September 8, 2026 to September 15, 2026 at 2:00 PM CST for the B246 Elevator Modernization project. The solicitation seeks elevator modernization services at Fort Leavenworth, with the delivery schedule extended from 200 calendar days to 300 calendar days from the date of award to completion of performance.
The amendment adds three revised contract documents: B246 Elevator Modernization Drawings (reduced from 39 to 6 pages), B246 Elevator Modernization SOW_Rev3 (increased from 9 to 14 pages), and Questions and Answers documentation (3 pages). The amendment deletes two outdated documents: Drawings 01_B246_20141219 and SOW_B246 Elevator Replacement Rev 2. Offerors must acknowledge receipt of this amendment prior to the extended bid opening date through one of three specified methods: completing and returning the amendment document, acknowledging receipt on each copy of the offer, or submitting separate written or electronic communication referencing the solicitation and amendment numbers. The contracting officer is Jennifer Walker, reachable at (520) 945-9613 or JENNIFER.S.WALKER12.CIV@ARMY.MIL.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SOW_Rev3_B246 Elevator Modernization.pdf | ||
| B246 Elevator Modernization Drawings.pdf | ||
| Q_A_W91QF426BA011_B246_Elevator.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER.
If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
16C. DATE SIGNED
Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
J 1 4
0001 02 SEP 2026 W91QF426IFBELEVATOR
W91QF4
W6QM MICC-FT LEAVENWORTH
731 MCCLELLAN AVENUE, FORT LEAVENWORTH KS 66027-0000
FORT LEAVENWORTH, KS 66027-0000
UNITED STATES
JENNIFER WALKER, EMAIL: JENNIFER.S.WALKER12.CIV@ARMY.MIL TELEPHONE:
(520) 945-9613
SCD: PAS:
W91QF426BA011
07 AUG 2026
SEE SECTION G - CONTRACT ADMINISTRATION DATA
Added Questions and Answers, New Drawings, and Revised SOW. The Bid Opening date has changed to 15 September 2026 at 2pm CST.
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
Section A - Solicitation/Contract Form
The following changes have been made:
INFORMATION FROM TO
Response Due Date
08 Sep 2026 15 Sep 2026
Section F - Deliveries or Performance
The delivery information for the following CLIN(s) / SLIN(s) / ELIN(s) were modified:
INFORMATION FROM TO
Delivery 200 Calendar Days, From Date of
Award to completion of performance 300 Calendar Days, From Date of Award to completion of performance
Section J - List of Attachments
The attachments table has changed from:
Identifie r
Document Name
Document Description Reference Identifier
Date Line Item Page N umbers
Docum ent Type
Provide d
W91QF426BA0110001
Under Separat e Cover
0003 B246 Elevator Modernization Drawings
Drawings 02 Sep
39 Attach ment
No
0004 B246 Elevator Modernization SOW_Rev3
Statement of Work 02 Sep
9 Attach ment
No
0005 Q_A_W91QF4
26BA011_B246
_Elevator
Questions and Answers 02 Sep
Attach ment
No
To:
Identifie r
Document Name
Document Description Reference Identifier
Date Line Item Page N umbers
Docum ent Type
Provide d Under Separat e Cover
0003 B246 Elevator Modernization Drawings
Drawings 02 Sep
6 Attach ment
No
0004 B246 Elevator Modernization SOW_Rev3
Statement of Work 02 Sep
14 Attach ment
No
0005 Q_A_W91QF4
26BA011_B246
_Elevator
Questions and Answers 02 Sep
3 Attach ment
No
The following contract documents were added:
B246 Elevator Modernization Drawings B246 Elevator Modernization SOW_Rev3 Q_A_W91QF426BA011_B246_Elevator
The following contract documents were deleted:
Drawings 01_B246_20141219 SOW_B246 Elevator Replacement Rev 2
The following contract documents Page Counts were changed:
DOCUMENT PAGE COUNTS
DOCUMENT NAME FROM TO
B246 Elevator Modernization Drawings 39 6
B246 Elevator Modernization SOW_Rev3 9 14
Q_A_W91QF426BA011_B246_Elevator none 3
File details come from the government source that posted it. Updated .