This is a three-year contract agreement between the City of St. Petersburg, Florida and an unnamed contractor for Trenchless Soil Stabilization services. The contract allows for an initial three-year term with the option to renew for one additional two-year period. The work will be performed on a field order basis, with the City issuing individual Field Orders for specific projects. The contractor will be required to reach Substantial Completion within the time specified in each Field Order and Final Completion within 30 calendar days after the City's delivery of the punch list. The contractor must obtain a Public Construction Bond for the first annual period and subsequent riders or new bonds for each subsequent annual period.

The contract includes a detailed liquidated damages structure for delays, with daily charges ranging from $500 to $4,000 depending on the Field Order amount. The City's funding obligation is limited to budgeting and appropriating legally available funds after essential City services have been funded. The contract does not specify a fixed total contract value, but requires the City to pay the contractor based on unit prices that may be annually adjusted. The City reserves the right to pledge non-ad valorem revenues for the contract obligations, with such pledges taking priority over the contract's financial commitments.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

A G R E E M E N T

THIS AGREEMENT (“Agreement”), made and entered into on the ______ day of

_______________, 20___ ("Effective Date"), by and between

___________________________________________, ("Contractor") and the City of St.

Petersburg, Florida, ("City" or "Owner").

WITNESSETH:

NOW, THEREFORE, in consideration of the promises and covenants contained herein, and other good and valuable consideration, the receipt and adequacy of which are hereby acknowledged, the Contractor and the City agree as follows:

a) The Contractor shall furnish all material and perform all of the work for:

Trenchless Soil Stabilization

St. Petersburg, Florida, Project No. XXXXX-XXX (“Project”), in full and complete accordance with this Agreement and the Contract Documents. Contract Documents shall mean, collectively, the General Conditions and supplementals thereto, Specifications and supplementals thereto, the Plans, the Solicitation and any addenda thereto, and the Bid (as those terms, i.e., Specifications, Plans, Solicitation, and Bid, are defined in the General Conditions).

b) This Agreement and the Contract Documents form the contract (“Contract”) between the City and Contractor.

c) The initial term of this Agreement is three (3) years commencing on the Effective Date.

The City reserves the right to renew this Agreement under the same terms and conditions, except as set forth below, for one (1) two-year period at the end of the initial term, provided that the City and Contractor mutually agree through a written amendment to the Contract to (i) a renewal, (ii) the unit prices for the first annual period of the renewal term, and (iii) the method for calculating adjustments to those unit prices during the second annual period of the renewal term. In the event this

Agreement is renewed, the parties will mutually agree on a description of the work for each annual period of the renewal term.

d) After the City issues a Notice to Proceed (as defined in the General Conditions) for each annual period, Contractor shall be prepared to commence portions of the Work

(as described in the Contract Documents) set forth in individual Field Orders (as defined in the General Conditions). After the City issues a Field Order, Contractor shall, for each Field Order: (i) reach Substantial Completion (as defined in the General

Conditions) of all Work under that Field Order within the time period stated therein, and (ii) reach Final Completion within thirty (30) calendar days after the City’s delivery of the punch list in accordance with the Contract, unless a longer period of time to reach Final Completion is set forth in the punch list (collectively for each Field Order,

(i) and (ii), “Field Order Completion Time”). The Field Order Completion Time may be modified by a Change Order (as defined in the General Conditions).

e) For the first annual period of the initial term of this Agreement, Contractor shall obtain a Public Construction Bond in accordance with the applicable requirements set forth in the Contract Documents. For each annual period thereafter, Contractor shall obtain a rider to the Public Construction Bond or a new Public Construction Bond in the additional amount of the Contract Price for that annual period (as hereinafter defined).

All Public Construction Bonds and riders thereto must be approved by the City

Attorney’s Office prior to issuance of a Notice to Proceed for any new work. All Public

Construction Bonds and riders thereto must be approved by the City Attorney’s Office prior to issuance of a Notice to Proceed for any new work.

f) Provided that Contractor faithfully performs its obligations contained the Contract, the

City hereby agrees to pay Contractor pursuant to the amounts set forth in the unit prices, as those unit prices may be annually adjusted in accordance with the Contract

Documents, at the time and in the manner set forth in the Contract Documents, an amount not to exceed for the first annual period of the initial term, ________________________ for the second annual period of the initial term, and _________________ for the third annual period of the initial term (individually for each annual period, “Contract Price”) subject to additions and deductions as provided in the Contract.

g) Time is of the essence in the Contract. The parties agree that it would be extremely difficult and impractical under known and anticipated facts and circumstances to ascertain and fix the actual damages the City would incur if Contractor does not achieve Substantial Completion within the time stipulated in each Field Order.

Therefore, Contractor shall be liable for and shall pay to the City the sums hereafter stipulated as fixed, agreed and acknowledged as reasonable liquidated damages, not as a penalty, for each calendar day of delay until the Work in each Field Order reaches

Substantial Completion, in the following aggregate amounts:

Field Order Amount Daily Charge per Calendar Day

$50,000 and under ................................................................................ $500

Over $50,000 but less than $500,000 ................................................ $1,000

Over $500,000 but less than $5,000,000 ........................................... $1,500

Over $5,000,000 but less than $15,000,000....................................... $2,000

$15,000,000 and over ........................................................................ $4,000

These liquidated damages shall be the City’s sole and exclusive damages for

Contractor’s delay of the Work.

h) The obligations of the City as to any funding required pursuant to the Contract shall be limited to an obligation in any given year to budget, appropriate and pay from legally available funds, after monies for essential City services have been budgeted and appropriated, sufficient monies for the funding that is required during that year.

Notwithstanding the foregoing, the City shall not be prohibited from pledging any legally available non-ad valorem revenues for any obligations heretofore or hereafter incurred, which pledge shall be prior and superior to any obligation of the City pursuant to the Contract.

IN WITNESS WHEREOF, the parties hereto have executed this Agreement, which is effective as of the day and date first above written.

(Company Name)

By: _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ (Signature of Corporate Officer)

WITNESSES:

By: _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

(Printed Name)

By: _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

(Printed Name)

CITY OF ST. PETERSBURG, FLORIDA

By: _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ Procurement and Supply Management Director

Date

By: _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ City Clerk (Designee)

APPROVED AS TO FORM:

By: _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ City Attorney (Designee)

00532534 – 3-yr w/ 2-yr renewal, Field Order Basis

(Acknowledgment of Contractor)

Under penalties of perjury, I declare that I am authorized by the Company to execute the foregoing Agreement.

By:

Print:

File details come from the government source that posted it. Updated .