00150-1
LIST OF DRAWINGS AND SPECIFICATIONS
SECTION 00150
HANDICAP ACCESSIBLE FISHING PIER
INSTALLATION & TRAIL CONSTRUCTION
PART 1 – GENERAL
1.1 DESCRIPTION
A. List of Contract Drawings:
1. Index of Sheets:
1 Title Sheet 2 Vicinity Map 1 3 Vicinity Map 2 4 Vicinity Map 3 5 Vicinity Map 4 6 Vicinity Map 5 7 Trail Cross-Sections 8 Cross-Section Detail 9 Raised Cross-Section 10 Landing Detail 11 Parking Detail
11 Total Plan Sheets in this Contract
B. List of Contract Specifications
1. Index of Specifications
DIVISION 1 - GENERAL
REQUIREMENTS
Section 00150 List of Drawings and Specifications Section 01010 Summary of Work Section 01140 Work Restrictions Section 01170 Accident Prevention Section 01330 Submittal Procedures Section 01430 Contractor Quality Control Section 01550 Government Furnished Materials (GFM) Section 01700 Execution Requirements Section 01770 Closeout Procedures
DIVISION 2 – SITEWORK
Section 02102 Clearing and Grubbing Section 02213 Trails
00150-2
Section 02213 Curbs Section 02722 Section 02900
Traffic Control Signs Landscaping
DIVISION 6 – WOOD AND
PLASTICS
Section 06129 Timber Borders
DIVISION 13 – SPECIAL
CONSTRUCTION
Section 13700 Floating Dock System
END OF SECTION 00150
01010 - 1
SUMMARY OF WORK
SECTION 01010
SUMMARY OF WORK
PART 1 - GENERAL
1.1 SUMMARY
A. Work for this project consists of transporting and installing six (6) handicap accessible fishing piers at various lakes throughout the Rio Grande National Forest. All fishing piers are stored at the Monte Vista Administration Site and shall be transported and installed according to the manufacturer’s requirements. In addition to this, accessible trails shall be constructed from parking areas at each location to the gangway for each pier. A total of approximately 500 feet of trails will be constructed. Trail construction shall consist of excavating 6 inches of topsoil for a 48 inch wide trail, compacting the trail bed, placing 3/8 inch minus gravel and compacting the material. Brush clearing on all trails will be incidental. All trails must closely adhere to both American Disability Act (ADA) and Forest Service Trail Accessibility Guideline (FSTAG) regulations. All trail centerlines will be staked by Forest Service officials prior to construction. Five (5) precast concrete wheel stops shall be installed at various locations along with accessible parking signs. One (1) loading zone sign will be installed in addition to the other signs.
1.2 LOCATION
A. This project is located at six different popular fishing locations throughout the forest.
On the Conejos Peak District, Mix Lake and Spectacle Lake will be part of this project, and on the Divide District, Alberta Park Reservoir, Big Meadows Reservoir, Road Canyon Reservoir, and Shaw Reservoir will be part of the project. Location maps to all six locations are included in the contract drawings. The fishing piers are stored at the Monte Vista Administration Site: 291 County Road 26, Monte Vista, CO 81144.
1.3 GENERAL SITE CONDITIONS AND WEATHER
A. The elevation of these sites range from approximately 8,700 to 10,000 feet above mean sea level. The construction sites experience heavy snowfall and extremely cold temperatures, with snow on the ground typically from mid-September through May.
B. In-depth soil surveys have not been performed; however, rocks at the ground surface are evident throughout the area. The Contractor should expect to encounter such rock during excavation and grubbing operations. Blasting of rocks will not be permitted without authorization by the Contracting Officer (CO).
01010 - 2
C. In-depth water table surveys have not been performed; however, if water is encountered during excavation, the Contractor shall perform adequate dewatering to keep the excavation free from water and dispose of the water without damage to property.
1.4 USE OF PREMISES
A. Full Government Occupancy: Government will occupy site during entire construction period. Cooperate with Government during construction operations to minimize conflicts and facilitate Government usage. Perform the Work so as not to interfere with Government operations.
B. Contractor shall at all times conduct his operations to ensure the least inconvenience to the public and employees. Certain parking lot closures will be permitted, when required, upon written approval of the CO.
C. Confine storage of materials to areas as approved by the CO.
D. Contractor shall provide adequate signing and barricades and take necessary safety measures to protect the public during all construction operations. Contractor shall minimize disturbance of all undisturbed areas.
E. Preservation of Natural Features: Confines all operations to work limits of the project.
Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.
1. Provide temporary barriers to protect existing trees and plants and root zones.
2. Do not remove, injure, or destroy trees or other plants without prior approval.
Consult with CO and remove agreed-on roots and branches that interfere with construction.
3. Do not fasten ropes, cables, or guys to existing trees.
4. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.
F. Ensure that all equipment on site has been cleaned for noxious weeds and certify that all materials brought on site are weed free.
1.5 MEALS AND LODGING
A. Meals and lodging are commercially available in the Town of South Fork, Town of Creede, Town of Del Norte, Town of La Jara, City of Alamosa, and City of Monte Vista, all a few hours away from each of the construction sites. Meals or lodging will not be available at Forest Service facilities.
01010 - 3
1.6 CAMPING
A. Camping is available at many locations near project sites. Contact the Conejos Peak and/or the Divide Ranger Districts for more information. All normal Forest Service campground regulations, including usage fees and space availability, will be applicable.
1.7 CONSTRUCTION SEQUENCE
A. In all instances, the fishing piers must be assembled and installed before construction of the trail begins.
B. Depending on conditions, normal fire restrictions may apply to activities associated with this project.
1.8 FIELD VERIFICATION
A. Field verify all new and existing dimensions affecting the work of this contract before ordering products. All trail lengths are approximates and shall be verified in the field prior to construction.
1.9 PAYMENT
A. Payment for pier installation shall be each.
B. Payment for aggregate shall be per truckload.
C. Payment for signs and concrete wheel stops shall be each.
D. Payment for trail and landing construction shall be per foot.
E. Payment for trail work will be for the actual quantity of feet of trail constructed. The feet of each typical trail cross section at each location provided in the drawings is estimated.
1.10 PERMITS
A. Special permits for oversized or overweight transporting (if necessary), or any other permits required by County, State, or Federal laws or regulations shall be the responsibility of the Contractor.
PART 2 - PRODUCTS (NOT USED)
PART 3 - EXECUTION (NOT USED)
END OF SECTION 01100
01140 - 1
WORK RESTRICTIONS
SECTION
WORK RESTRICTIONS
01140
PART 1-GENERAL
1.1 USE OF PREMISES
A. Use of Site: Limit use of premises to work in areas indicated. Do not disturb portions of site beyond areas in which the Work is indicated.
1. Limits: Confine constructions operations to the locations directly involved in the project.
2. Government Occupancy: Allow for Government occupancy of site and use by the public.
3. Driveways and Entrances: Keep driveways and entrances serving premises clear and available to Occupants, Government employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials. If neces-sary, parking lot closures will only be allowed after written approval from the Contracting Officer (CO).
a. Schedule deliveries to minimize use of driveways and entrances.
b. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
1.2 OCCUPANCY REQUIREMENTS
A. Full Government Occupancy: Government will occupy site during entire construction period. Cooperate with Government during construction operations to minimize con-flicts and facilitate Government usage. Perform the Work so as not to interfere with Government operations.
PART 2- PRODUCTS (NOT USED)
PART 3- EXECUTION (NOT USED)
END OF SECTION 01140
01170-1
ACCIDENT PREVENTION
SECTION 01170
ACCIDENT PREVENTION
PART 1 - GENERAL
1.1 DESCRIPTION
A. The work of this section consists of establishing an effective accident prevention program and providing a safe environment for all personnel and visitors.
1.2 SUBMITTALS
A. Submit a copy of test reports, as required by OSHA, for personnel working with hazardous materials.
B. Upon request, submit proof of employees' qualifications to perform assigned duties in a safe manner.
1.3 QUALITY ASSURANCE
A. In case of conflicts between Federal, state, and local safety and health requirements, the most stringent shall apply. Equipment or tools not meeting OSHA requirements will not be allowed on the project sites. Failure to comply with the requirements of this section and related sections may result in suspension of work.
B. Qualifications of Employees
1. Ensure that employees are physically qualified to perform their assigned duties in a safe manner.
2. To as great an extent as possible, do not allow employees to work whose ability or alertness is impaired because of drugs, fatigue, illness, intoxication, or other conditions that may expose themselves or others to injury.
3. Operators of vehicles, mobile equipment, hoisting equipment, and hazardous plant equipment shall be able to understand signs, signals, and operating instructions, and be capable of operating such equipment. Provide operating instructions for all equipment. Newly hired operators shall be individually tested by an experienced operator or supervisor to determine if they are capable of safely operating equipment.
1.4 ACCIDENT REPORTING
A. Reportable Accidents: A reportable accident is defined as death, occupational disease, traumatic injury to employees or the public, property damage by accident in excess of $100, and fires. Within 7 days of a reportable accident, fill out and forward to the CO a DI-134 form, which may be obtained from CO.
B. All Other Accidents: The Contractor shall report all other accidents to the CO as soon as possible and assist the CO and other officials as required in the investigation of the accident.
01170-2
ACCIDENT PREVENTION
PART 2 – PRODUCTS
2.1 First Aid Facilities: provide adequate facilities for the number of employees and the type of construction at the site.
2.2 Personal Protective Equipment: meet requirements of NIOSH and OSHA, where applicable, as well as ANSI.
2.3 Barriers: provide adequate barriers and signage to protect the public at all points during the project.
PART 3 – EXECUTION
3.1 EMERGENCY INSTRUCTIONS
A. Post telephone numbers and reporting instructions for ambulance, physician, hospital, fire department, and police in conspicuous locations at the work site. Cell phone coverage may not exist in several of the work locations however.
3.2 PROTECTIVE EQUIPMENT
A. Inspect personal protective equipment frequently and maintain in a serviceable condition.
Clean, sanitize, and repair, as appropriate, personal items before issuing them to another individual.
B. Inspect and maintain other protective equipment and devices before use and on a periodic basis to ensure safe operation.
3.3 TRAINING
A. First Aid: Provide adequate training to ensure prompt and efficient first aid.
B. Hazardous Material: Train and instruct each employee exposed to hazardous material in safe and approved methods of handling and storage. Hazardous materials are defined as explosive, flammable, poisonous, corrosive, oxidizing, irritating, or otherwise harmful substances that could cause death or injury.
END OF SECTION 01170
01330 - 1
SUBMITTAL PROCEDURES
SECTION
SUBMITTAL PROCEDURES
01330
PART 1- GENERAL
1.1 SUMMARY
A. This Section includes administrative and procedural requirements for submitting Product Data, Samples, and other miscellaneous submittals.
1.2 DEFINITIONS
A. Action Submittals: Written and graphic information that requires Contracting Offic-er’s (CO's) responsive action.
B. Informational Submittals: Written information that does not require CO's approval.
Submittals may be rejected for not complying with requirements.
1.3 SUBMITTAL PROCEDURES
A. Coordination: Coordinate preparation and processing of submittals with performance of construction activities.
1. Coordinate transmittal of different types of submittals for related parts of the Work so processing will not be delayed because of need to review submittals concurrently for coordination.
a. CO reserves the right to withhold action on a submittal requiring coordina-tion with other submittals until related submittals are received.
B. Processing Time: Allow enough time for submittal review, including time for re-submittals, as follows. Time for review shall commence on CO's receipt of submittal.
1. Initial Review: Allow five (5) days for initial review of each submittal. Allow additional time if processing must be delayed to permit coordination with subse-quent submittals. CO will advise Contractor when a submittal being processed must be delayed for coordination.
2. If intermediate submittal is necessary, process it in same manner as initial sub-mittal.
3. Allow five (5) days for processing each re-submittal.
4. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing.
C. Identification: Place a permanent label, title block, or title page on each submittal for identification.
1. Indicate name of firm or entity that prepared each submittal on label, title block, or title page.
01330 - 2
2. Provide a space on label or beside title block to record Contractor's review and approval markings and action taken by CO.
3. Include the following information on label for processing and recording action taken:
a. Project name.
b. Date.
c. Name and address of Contractor.
d. Name of manufacturer.
e. Unique identifier, including revision number.
f. Number and title of appropriate Specification Section.
g. Drawing number and detail references, as appropriate.
h. Other necessary identification.
D. Deviations: Highlight, encircle, or otherwise identify deviations from the Contract Documents on submittals.
E. Additional Copies: Unless additional copies are required for final submittal, and un-less CO observes noncompliance with provisions of the Contract Documents, initial submittal may serve as final submittal.
F. Use for Construction: Use only final submittals with mark indicating action taken by CO in connection with construction.
PART 2 – PRODUCTS
2.1 ACTION SUBMITTALS
A. General: Prepare and submit Action Submittals required by individual Specification Sections.
1. Number of Copies: Submit two (2) copies of each submittal, unless otherwise indicated. CO will return one copy. Mark up and retain returned copy as a Project Record Document.
2. Action Submittals Required:
a. Aggregate source and sieve analysis.
2.2 INFORMATIONAL SUBMITTALS
A. General: Prepare and submit Informational Submittals required by other Specification Sections.
1. Number of Copies: Submit one (1) copy of each submittal, unless otherwise in-dicated. CO will not return copies.
01330 - 3
2. Certificates and Certifications: Provide a notarized statement that includes sig-nature of entity responsible for preparing certification. Certificates and certifi-cations shall be signed by an officer or other individual authorized to sign doc-uments on behalf of that entity.
3. Informational Submittals Required:
a. Timber treatment certification.
b. Weed free certification for all aggregates, topsoil, and seed.
c. Product information for concrete wheel stops.
d. Seed mixture.
B. Material Test Reports: Prepare reports written by a qualified testing agency, on test-ing agency's standard form, indicating and interpreting test results of material for compliance with requirements.
PART 3 – EXECUTION (NOT USED)
END OF SECTION 01330
01430-1
CONTRACTOR QUALITY CONTROL
SECTION 01430
CONTRACTOR QUALITY CONTROL
PART 1 – GENERAL
1.1 DESCRIPTION
A. The work of this section consists of preparing and executing a quality control program.
1.2 SUBMITTALS
A. As specified in Division 1 Section “Submittal Procedure”.
1.3 QUALITY ASSURANCE
A. General:
1. The quality of all work shall be the responsibility of the Contractor.
2. Inspect and test all work often enough to ensure that the quality of materials, workmanship, construction, finish, and functional performance is in compliance with applicable specifications and drawings.
B. Quality Control Staff:
1. The Contractor’s Quality Control Supervisor may also perform the duties of Project
Superintendent.
2.
PART 2 – PRODUCTS (NOT USED)
The Contractor’s designated Quality Control Supervisor, or a qualified designated replacement, shall be on the project site whenever contract work is in progress.
PART 3 – EXECUTION
3.1 OFF-SITE CONTROL
A. Items that are fabricated or assembled off-site shall be inspected for quality control at the place of fabrication.
3.2 ON-SITE CONTROL
A. Preparatory Phase: Perform before beginning each feature of work.
1. Review all applicable specifications sections and drawings related to the feature of work.
2. Ensure that provisions have been made for field control testing.
3. Examine the work area to ensure that all preliminary work has been completed.
4. Verify all field dimensions and advise the Contracting Officer of discrepancies with contract documents.
01430-2
CONTRACTOR QUALITY CONTROL
5. Ensure that necessary equipment and materials are at the project site.
B. Initial Phase:
1. As soon as work begins, inspect and test a representative portion of a particular feature of work for quality of workmanship.
2. Review control-testing procedures to ensure compliance with contract requirements.
C. Follow-Up Phase: Inspect and test as work progresses to ensure compliance with contract requirements until completion of work.
D. Additional Preparatory and Initial Phases: Additional preparatory and initial phases may be required on the same feature of work for the following reasons:
1. Quality of on-going work is unacceptable.
2. Changes occur in the applicable quality control staff, on-site production supervision, or work crew.
3. Work on a particular feature of work is resumed after a substantial period of inactivity.
3.3 ENFORCEMENT
A. The Contractor shall stop work on any item or feature pending satisfactory correction of any deficiency noted by the quality control staff or the Contracting Officer.
END OF SECTION 01430
01550_02.doc - 1
GOVERNMENT FURNISHED MATERIALS (GFM)
SECTION 01550
PART 1 - GENERAL
1.1 SUMMARY
A. This section applies to materials that shall be provided by the Government and installed by the Contractor.
1.2 INSPECTION
A. The Contractor shall notify the Contracting Officer (CO) at least five (5) calendar days prior to picking up or returning Government-furnished materials.
1. The Contractor and the CO shall jointly inspect all materials during the loading operation at the storage area.
1.3 LIABILITY
A. The Contractor's liability for Government-furnished materials shall start at the time they accept the materials at the storage area and shall terminate upon completion and final acceptance of the work.
1. It shall be implied that the Contractor has accepted Government-furnished materials from the storage area to the worksite.
2. The Contractor shall provide all labor, equipment, and incidentals materials necessary between the worksite and specified storage area.
1.4 REPLACEMENT AND/OR SUPPLEMENTAL MATERIALS
A. Any defective materials discovered prior to the Contractor's acceptance of the materials shall be replaced by the Government.
B. If the quantity of Government-furnished material accepted by the Contractor is insufficient to complete the specified work, supplemental materials complying with these specifications shall be provided by the Government at no expense to the Contractor.
C. The Government shall not replace any materials that, in the opinion of the CO, are damaged or lost due to the Contractor's negligence after the Contractor accepts the materials. Such materials shall be replaced at the Contractor's expense.
1.5 SURPLUS MATERIAL
A. After completion and final acceptance of the work, surplus Government-furnished materials shall be returned to the specified storage area in the same mechanical and physical condition as originally accepted.
B. Damaged surplus materials shall be replaced at the Contractor's expense.
C. The Contractor's liability for surplus materials shall terminate upon completed installation and final acceptance by the CO.
01550_02.doc - 2
PART 2 – PRODUCTS
2.1 GOVERNMENT-FURNISHED MATERIALS
A. Government-furnished materials shall be limited to:
1. Floating dock system
2. All provided installation hardware
PART 3 – EXECUTION
3.1 GENERAL
A. Installation and testing of Government-furnished materials shall comply with the applicable contract specifications covering work requiring the use of such materials, and the manufacturer’s recommendations.
END OF SECTION 01550
01700 - 1
EXECUTION REQUIREMENTS
SECTION
EXECUTION REQUIREMENTS
01700
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes general procedural requirements governing execution of the Work including, but not limited to, the following:
1. General installation of products.
2. Progress cleaning.
3. Adjusting.
4. Protection of installed construction.
5. Correction of the Work.
B. See Division 1 Section "Closeout Procedures" for submitting recording of Govern-ment-accepted deviations from indicated lines and levels and final cleaning.
PART 2 - PRODUCTS (NOT USED)
PART 3 – EXECUTION
3.1 EXAMINATION
A. Existing Conditions: The existence and location of site improvements and other con-struction indicated as existing are not guaranteed.
B. Acceptance of Conditions: Examine substrates, areas, and conditions, with Installer or Applicator present where indicated, for compliance with requirements for installation tolerances and other conditions affecting performance. Record observations.
1. Verify compatibility with and suitability of substrates, including compatibility with existing finishes or primers.
2. Proceed with installation only after unsatisfactory conditions have been cor-rected. Proceeding with the Work indicates acceptance of surfaces and condi-tions.
3.2 PREPARATION
A. Field Measurements: Take field measurements as required to fit the Work properly.
Recheck measurements before installing each product. Where portions of the Work are indicated to fit to other construction, verify dimensions of other construction by field measurements before fabrication. Coordinate fabrication schedule with construc-tion progress to avoid delaying the Work.
01700 - 2
B. Space Requirements: Verify space requirements and dimensions of items shown dia-grammatically on Drawings.
C. Review of Contract Documents and Field Conditions: Immediately on discovery of the need for clarification of the Contract Documents, submit a request for information to CO. Include a detailed description of problem encountered, together with recom-mendations for changing the Contract Documents.
3.3 INSTALLATION
A. General: Locate the Work and components of the Work accurately, in correct align-ment and elevation, as indicated.
1. Make vertical work plumb and make horizontal work level.
2. Where space is limited, install components to maximize space available for maintenance and ease of removal for replacement.
B. Comply with manufacturer's written instructions and recommendations for installing products in applications indicated.
C. Install products at the time and under conditions that will ensure the best possible re-sults. Maintain conditions required for product performance until Substantial Comple-tion.
D. Conduct construction operations so no part of the Work is subjected to damaging op-erations or loading in excess of that expected during normal conditions of occupancy.
E. Anchors and Fasteners: Provide anchors and fasteners as required to anchor each component securely in place, accurately located and aligned with other portions of the Work.
1. Mounting Heights: Where mounting heights are not indicated, mount compo-nents at heights directed by CO.
F. Hazardous Materials: Use products, cleaners, and installation materials that are not considered hazardous.
3.4 PROGRESS CLEANING
A. General: Clean Project site and work areas daily, including common areas. Coordi-nate progress cleaning for joint-use areas where more than one installer has worked.
Enforce requirements strictly. Dispose of materials lawfully.
1. Comply with requirements in NFPA 241 for removal of combustible waste ma-terials and debris.
2. Do not hold materials more than 7 days during normal weather or 3 days if the temperature is expected to rise above 80 deg F (27 deg C)
B. Site: Maintain Project site free of waste materials and debris.
01700 - 3
C. Work Areas: Clean areas where work is in progress to the level of cleanliness neces-sary for proper execution of the Work.
1. Remove liquid spills promptly.
D. Installed Work: Keep installed work clean. Clean installed surfaces according to written instructions of manufacturer or fabricator of product installed, using only cleaning materials specifically recommended. If specific cleaning materials are not recommended, use-cleaning materials that are not hazardous to health or property and that will not damage exposed surfaces.
E. Waste Disposal: Burying or burning waste materials on-site will not be permitted.
F. During handling and installation, clean and protect construction in progress and ad-joining materials already in place. Apply protective covering where required to ensure protection from damage or deterioration at Substantial Completion.
G. Clean and provide maintenance on completed construction as frequently as necessary through the remainder of the construction period.
H. Limiting Exposures: Supervise construction operations to assure that no part of the construction completed or in progress is subject to harmful, dangerous, damaging, or otherwise deleterious exposure during the construction period.
3.5 PROTECTION OF INSTALLED CONSTRUCTION
A. Provide final protection and maintain conditions that ensure installed Work is without damage or deterioration at time of Substantial Completion.
3.6 CORRECTION OF THE WORK
A. Repair or remove and replace defective construction. Restore damaged substrates and finishes.
1. Repairing includes replacing defective parts, refinishing damaged surfaces, and touching up with matching materials.
B. Restore permanent facilities used during construction to their specified condition.
C. Remove and replace damaged surfaces that are exposed to view if surfaces cannot be repaired without visible evidence of repair.
END OF SECTION 01700
01770 - 1
CLOSEOUT PROCEDURES
SECTION
CLOSEOUT PROCEDURES
01770
PART - GENERAL
1.1 SUMMARY
A. This Section includes administrative and procedural requirements for contract clo-seout, including, but not limited to, the following:
1. Inspection procedures.
2. Project Record Documents.
3. Instruction of Government personnel.
4. Final cleaning.
B. See Divisions 2 through 16 Sections for specific closeout and special cleaning re-quirements for products of those Sections.
1.2 FINAL COMPLETION
A. Preliminary Procedures: Before requesting final inspection for determining date of Final Completion, complete the following:
1. Submit certified copy of CO’s Substantial Completion inspection list of items to be completed or corrected (punch list), endorsed and dated by CO. The certified copy of the list shall state that each item has been completed or otherwise re-solved for acceptance.
2. Instruct Government personnel in operation, adjustment, and maintenance of products, equipment, and systems.
B. Inspection: Submit a written request for final inspection for acceptance. On receipt of request, CO will either proceed with inspection or notify Contractor of unfulfilled re-quirements. CO will prepare a final Certificate for Payment after inspection or will notify Contractor of construction that must be completed or corrected before certifi-cate will be issued.
1. Reinspection: Request reinspection when the Work identified in previous in-spections as incomplete is completed or corrected.
1.3 LIST OF INCOMPLETE ITEMS (PUNCH LIST)
A. Preparation: Submit three copies of list. Include name and identification of each space and area affected by construction operations for incomplete items and items needing correction including, if necessary, areas disturbed by Contractor that are out-side the limits of construction.
01770 - 2
CLOSEOUT PROCEDURES
PART 2 – PRODUCTS
2.1 MATERIALS
A. Cleaning Agents: Use cleaning materials and agents recommended by manufacturer or fabricator of the surface to be cleaned. Do not use cleaning agents that are poten-tially hazardous to health or property or that might damage finished surfaces.
PART 3 – EXECUTION
3.1 FINAL CLEANING
A. General: Provide final cleaning. Conduct cleaning and waste-removal operations to comply with local laws and ordinances and Federal and local environmental and anti-pollution regulations.
B. Cleaning: Employ experienced workers for final cleaning. Comply with manufactur-er's written instructions.
1. Complete the following cleaning operations before requesting inspection for cer-tification of Final Completion for entire Project or for a portion of Project:
a. Clean Project site, yard, and grounds, in areas disturbed by construction activities, including landscape development areas, of rubbish, waste ma-terial, litter, and other foreign substances.
b. Remove petrochemical spills, stains, and other foreign deposits.
c. Rake grounds that are neither planted nor paved to a smooth, even-textured surface.
d. Remove tools, construction equipment, machinery, and surplus material from Project site.
e. Clean exposed exterior hard-surfaced finishes to a dirt-free condition, free of stains, films, and similar foreign substances. Avoid disturbing natural weathering of exterior surfaces.
f. Remove labels that are not permanent.
g. Touch up and otherwise repair and restore marred, exposed finishes and surfaces. Replace finishes and surfaces that cannot be satisfactorily re-paired or restored or that already show evidence of repair or restoration.
h. Replace parts subject to unusual operating conditions.
i. Leave Project clean and ready for occupancy.
C. Comply with safety standards for cleaning. Do not burn waste materials. Do not bury debris or excess materials on Government property. Do not discharge volatile, harm-ful, or dangerous materials into drainage systems. Remove waste materials from Project site and dispose of lawfully.
END OF SECTION 01770
02102 - 1
CLEARING & GRUBBING
SECTION 02102
CLEARING & GRUBBING
PART 1 - GENERAL
1.1 SUMMARY
A. This work shall consist of clearing, grubbing, trimming, removing, and disposing debris.
This work shall also include preservation of vegetation and objects designated to remain from injury or defacement.
1.2 MEASUREMENT
A. Linear measurements will be horizontal along each accessible trail centerline.
B. All clearing and grubbing shall be an incidental cost.
PART 2 – PRODUCTS (NOT USED)
PART 3 – EXECUTION
3.1 CLEARING & GRUBBING
A. All debris, roots, and other protruding vegetative material within the trail work limits, not designated to remain, shall be cleared, grubbed, removed, and disposed of, except the following:
1. Grubbing of pits, channel changes, rock sections, and ditches, below the depth of the proposed excavation.
B. All roots over 3 inches in diameter within the trail area shall be grubbed to a minimum depth of 6 inches below subgrade. Roots over 3 inches in diameter protruding from the excavated slope shall be cut flush with the excavated slope surface.
END OF SECTION 02102
02213 - 1
TRAILS
SECTION 02213
TRAILS
PART 1 - GENERAL
1.1 SUMMARY
A. This work shall consist of constructing accessible trails in close conformity to the dimensions, lines and grades as shown on the drawings and staked on the ground.
B. Work shall include clearing, excavation and embankment, compacting trail beds, placing timber borders, placing and compacting gravel, placing and compacting fill material, and seeding all fill areas.
1.2 RELATED WORK SPECIFIED ELSEWHERE
A. Clearing and Grubbing – Section 02102.
B. Landscaping – Section 02900.
C. Timber Borders – Section 06129.
1.3 LINEAR FEET OF TRAIL
A. Contractor to install the approximate linear feet of trail according to the specification within this section.
1. 4 foot wide trail - approximately 500 linear feet (LF).
2. See drawings for lengths at each location of each typical trail cross-section.
1.4 SUBMITTALS
A. Contractor shall submit to the CO for approval source of aggregate base and backfill materials and certified sieve analysis for source.
B. Aggregate and topsoil sources shall be approved by the Government to be weed free.
PART 2 - PRODUCTS
2.1 BACKFILL MATERIALS, GENERAL
A. Excavated material may be processed and used for backfill if the Contractor can show compliance with the material specified herein to the satisfaction of the CO. If excavated material is not sufficient to meet requirements, Contractor shall import needed material.
02213 - 2
B. Satisfactory Soils: ASTM D 2487 soil classification groups GW, GP, GM, SW, SP, and SM, or a combination of these group symbols; free of rock or gravel larger than 3 inches (75 mm) in any dimension, debris, waste frozen materials, vegetation, and other deleterious matter.
C. Unsatisfactory Soils: ASTM D 2487 soil classification groups GC, SC, ML, MH, CL, CH, OL, OH, and PT, or a combination of these group symbols.
1. Unsatisfactory soils also include satisfactory soils not maintained within 2 percent of optimum moisture content at time of compaction.
2.2 BACKFILL AND FILL
A. Satisfactory soil materials.
2.3 AGGREGATE BASE
A. Aggregate base shall be crushed gravel, free from vegetable matter and lumps of clay.
B. Material shall conform to the quality requirements of AASHTO M147 except that the requirements for the ratio of minus No. 200 sieve fraction to the minus No. 40 sieve fraction, stated in 2.2.2 of AASHTO M147 shall not apply.
C. The liquid limit shall not exceed 30%.
D. Aggregate base shall meet the grading requirements shown in the table below or approved equal.
Sieve Size Percentages by Weight Passing Square Mesh Sieves
3/8 inch 100 No. 4 50-80 No. 10 35-70 No. 200 8-15
2.4 SOURCE
A. Aggregate base shall be obtained from an approved commercial source, the contractor shall submit test results for aggregate gradation and a Certificate of Compliance that states gradation meets contract requirements.
B. Sampling and testing of the material before incorporation into the work shall be in accordance with AASHTO requirements and shall occur as follows:
1. For commercially produced aggregates:
a. At the producer's plant or stockpile.
2. These test results shall not preclude later sampling and testing for final acceptance after final processing of the material.
3. Crushing, screening, and mixing plants shall be equipped with sampling devices.
02213 - 3
4. The contractor shall take additional samples as required to validate the certification.
PART 3 - EXECUTION
3.1 STAKING
A. Trial centerline location (and elevation if required) shall be staked by the government at each location prior to trail construction. The Forest Service may take a maximum of four (4) working days (exclusive of weekends and holidays) for completion of this work.
3.2 SITE PREPARATION AND GRADING
A. Before commencing work, thoroughly remove all debris and rock 2 inches and larger.
B. All areas within the limit of the work shall be carefully and accurately graded and shaped to the elevations shown with the following limits:
1. All trails shall comply with the American Disability Act (ADA) and Forest
Service Trails Accessibility Guidelines (FSTAG) and shall be constructed with a maximum running grade of:
a. 5 percent for any distance.
b. 8.33 percent for up to 50 feet.
2. All trails shall be constructed flat with no cross slope.
C. All noticeable depressions shall be filled, and all mounds graded down so that the entire area presents a uniformly even surface.
D. All low areas shall be filled in and the trail area shall be filled in as shown on the drawings.
E. Clearing limits shall be 3 ½ feet on either side of the trail centerline location.
F. Stump holes shall be backfilled with compacted mineral soil or borrow material from designated source.
3.3 EXCAVATION AND EMBANKMENT
A. Excavation and embankment shall be accomplished to meet the lines and grades as shown on the drawings and designated in the specs.
B. Deviations from the trail alignment will be permitted to avoid or minimize disturbance to the physical terrain, or to attain the required grades, with prior approval from the Contracting Officer (CO).
C. All excavated material shall be conserved and used in construction of the trailbed:
02213 - 4
1. Rocks, which protrude above the trailbed, shall be removed and cavities backfilled with compacted mineral soil.
2. Rocks shall be laid in designated areas as directed by the CO.
D. Embankment shall be constructed of compacted mineral soil or borrow material from designated sources.
1. All disturbed soil within the trailbed area shall be recompacted to provide a solid bed
3.4 AGGREGATE
A. The aggregate shall be spread in a uniform layer, with no segregation of size, and to a loose depth that shall have the required thickness of 6 inches when compacted.
3.5 FILL
A. Preparation: Remove vegetation, topsoil, debris, unsatisfactory soil materials, obstructions, and deleterious materials from ground surface before placing fills.
B. Place and compact fill material in layers to required elevations as follows:
1. Under grass and planted areas, use satisfactory soil material.
2. Under trails, use satisfactory soil material.
3.6 COMPACTION
A. Trail bed: Trail bed shall be compacted using a mechanical tamper to 85% maximum density.
B. Trail: Aggregate shall be compacted using a mechanical tamper to 95% maximum density.
C. Trail shall be a firm and stable surface.
1. A firm surface is defined as a surface that is not noticeably distorted or compressed by the passage of a device that simulates a person using a wheelchair.
2. A stable surface is defined as a surface that is not permanently affected by normally occurring weather conditions and can sustain wear and tear during normal use between planned maintenance cycles.
3. A rotational penetrometer may be used to determine whether the surface is firm and stable.
D. Compacted base course surface shall be smooth and free from waves and other irregularities. Unsatisfactory portions of base course shall be torn up, re-worked, re-laid, and re-compacted, at no additional expense to Government.
02213 - 5
3.7 STOCKPILING
A. If one of the contractors elects to produce and stockpile aggregates prior to placement, the aggregates shall be handled and stockpiled in accordance with the requirements shown below.
B. Stockpile sites shall be at locations or approved by the CO.
1. All materials shall be transported and handled to preserve their quality and fitness for the work. Aggregates shall be stockpiled, loaded, and transported in a manner that will preserve specified gradation and avoid contamination.
Stockpiles of aggregate having different gradations shall not be intermingled.
3.8 THICKNESS REQUIREMENTS
A. The thickness of the compacted aggregate shall not vary more than 1/2 inch for aggregates with a nominal maximum particle size of 1 inch or less from the thickness shown on the drawings.
B. The compacted thickness shall not be consistently above or below the specified thickness.
3.9 TOLERANCES
A. Surface: Contractor will test finished surface of the base course with a 4-foot straightedge or other approved device. The variation between any two contacts with the surface shall not exceed one-half inch. Any areas not complying with these tolerances shall be reworked to obtain conformity.
B. Width: 48 inches minimum, plus two inches maximum.
C. Thickness: 6 inches, plus or minus one-half inch.
3.10 DISPOSAL OF SURPLUS AND WASTE MATERIALS
A. Disposal: If directed by the CO, transport surplus satisfactory soil to designated waste areas. Waste soil as directed by CO.
1. Remove waste material, including unsatisfactory soil, trash, and debris, and legally dispose of it off government’s property.
END OF SECTION 02213
02621 - 1
CURB
SECTION 02621
CURB
PART 1 - GENERAL
1.1 SUMMARY
A. This work shall consist of the construction and installation of a total of five (5) parking wheel stops.
1.2 PLACEMENT
A. Curbing shall be placed in the locations staked by the Government at Alberta Park Reservoir, Big Meadows Reservoir, Mix Lake, Road Canyon Reservoir, and Spectacle Lake.
1.3 SUBMITTALS
A. Manufacturer’s product information for the concrete blocks shall be submitted to the Contracting Officer (CO) prior to installation in order to ensure compliance with all specifications.
PART 2 – PRODUCTS
2.1 PRECAST CONCRETE CURB
A. Precast concrete curbing shall consist of precast Portland cement concrete curb units constructed to the lengths, shapes, and other details shown on the drawings. Steel reinforcement shall meet the requirements of Subsection 2.2. Concrete shall attain a minimum 28-day compressive strength of 3,000 psi.
B. Curbs shall be painted blue in accordance with MUTCD and the American Disability Act (ADA) guidelines.
2.2 REINFORCING STEEL
A. Reinforcing steel shall meet the following requirements:
1. Reinforcing rebar in wheel stop shall be #3 rebar with two installed in each curb block during fabrication to the dimensions shown on the drawings.
B. Anchoring rebar shall meet the following requirements:
1. Anchoring rebar shall be #5 rebar with two installed in each curb block to the dimensions shown on the drawings.
02621 - 2
CURB
PART 3 – EXECUTION
3.1 PRECAST CONCRETE CURBING
A. The curb shall be set so that the top surfaces of adjoining sections are true and even.
All spaces under the curbing shall be filled with material meeting the requirements of the material for bed course, and this material shall be compacted.
B. Drill or precast 5/8” diameter holes for rebar anchors and install to dimensions shown on the drawings.
END OF SECTION 02621
02722 - 1
TRAFFIC CONTROL SIGNS
SECTION 02722
TRAFFIC CONTROL SIGNS
PART 1 - GENERAL
1.1 SUMMARY
A. This work shall consist of furnishing and installing signs, sign supports, and posts.
B. Traffic control sign details, unless otherwise noted, shall meet the requirements of the Manual on Uniform Traffic Control Devices, 2009 edition (MUTCD, 2009).
1.2 MEASUREMENT
A. All signs shall conform to MUTCD dimension requirements unless otherwise noted.
B. Concrete shall be considered incidental to other pay items and additional payment will not be made.
PART 2 – PRODUCTS
2.1 SIGN PANELS
A. Sign panels shall be panels of one-piece construction made from aluminum which have the face side reflectorized.
1. Aluminum Panels: All sheets and plates shall meet the requirements of ASTM B
209, alloy 6061-T6, or 5052-H38 and shall be of the thickness shown below.
Sign Width (inches) Less than 8
Sheet Aluminum Thickness (inches) 0.022
8-12 0.040 13-19 0.063 20-30 0.080 31-48 0.100 over 48 0.125
2.2 POSTS
A. Posts shall be.
1. Steel Posts: Steel posts shall meet the requirements of ASTM A 499, galvanized in accordance with AASHTO M 111.
a. The posts shall have 7/16-inch holes drilled or punched, before galvanizing, along the centerline of the web. The punching or drilling should begin 1 inch from the top of the post, at 2-inch centers for the upper 5 feet of the post.
02722 - 2
2.3 FITTINGS
A. Lag screws, washers, clip angles, shear plates, U-bolts, clamps, bolts, nuts, and other fasteners shall be galvanized steel, cadmium-plated steel, aluminum alloy, or an acceptable alternative.
B. Galvanizing of steel hardware shall be in accordance with AASHTO M 232. High-strength steel bolts, nuts, and washers shall meet the requirements of ASTM A 325.
2.4 REFLECTIVE MATERIALS & REFLECTIVE SHEETING
A. All reflective materials (sheeting, legend, borders, and symbols) shall conform to the MUTCD reflectivity standards.
B. Colors shall be as specified in the MUTCD 2009.
C. No more than 12 months shall elapse from the date of manufacture to the date of application on the substrate.
2.5 LETTERS, NUMERALS, ARROWS, SYMBOLS, BORDER
A. Letters, numerals, arrows, symbols, border, and other features of the sign message shall be of the type, size, and series required in the MUTCD.
B. Colors shall be as specified in MUTCD. Completed letters, numerals, and other units shall be formed to provide continuous stroke width with smooth edges and shall present a flat surface free of warp, blisters, wrinkles, burrs, and splinters.
PART 3 – EXECUTION
3.1 FABRICATION OF SIGN PANELS
A. Fabrication of all parts shall be accomplished in a uniform manner. All panel fabrication, including cutting, punching, and drilling of holes, shall be completed prior to final surface preparation and application of reflective sheeting, except where required for the fabrication of die-cut or sawed letters on processed and mounted signs. Metal panels shall be cut to size and shape and shall be free of buckles, warp, dents, cockles, burrs, and defects resulting from fabrication. The surface of all sign panels shall be flat.
B. Field drilling of holes in any part of the structural assembly will not be permitted without the approval of the Contracting Officer (CO).
1. Aluminum Panels: Aluminum sign panels shall be fabricated from standard widths of aluminum sheet. The thickness shall be in accordance with Subsection 2.1.1.2.
02722 - 3
3.2 SIGN ERECTION
A. Sign supports shall be erected plumb and in accordance with the details shown on the drawings
B. The sign panels shall be securely fastened to the posts as shown on the drawings.
C. To reduce specular glare, sign panel face shall be erected in accordance with MUTCD.
PART 4 – SIGN SCHEDULE
4.1 EXTERIOR SIGN SCHEDULE
A. All signs shall comply with MUTCD 2009 standards, with the noted text exceptions below.
1. All signs with text differing from MUTCD 2009 standards shall comply with all
MUTCD color, font size, symbol, and border requirements.
B. MUTCD Sign Designations, Sizes, Texts, Quantities, and Installation Locations:
1. Handicap Accessible Parking:
a. Sign Designation: R7-8
b. Size: 12” x 18”
c. Text: Reserved Parking
d. Quantity: 5
e. Locations: Alberta Park Reservoir, Big Meadows Reservoir, Mix Lake, Road
Canyon Reservoir, and Spectacle Lake
2. No Parking:
a. Sign Designation: R7-6
b. Size: 12” x 18”
c. Text: No Parking, Accessible Loading Zone
d. Quantity: 1
e. Location: Shaw Reservoir
END OF SECTION 02722
02900 - 1
LANDSCAPING
SECTION 02900
LANDSCAPING
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this Section.
1.2 SUMMARY
A. This Section includes the following:
1. Seed.
2. Seed Source.
3. Topsoil.
1.3 SUBMITTALS
A. General: Submit each item in this Article according to the Conditions of the Contract and Division 1 Specification Sections.
B. Certification of grass seed from seed vendor for each grass-seed mixture stating the botanical and common name and percentage by weight of each species and variety, and percentage of purity, germination, and weed seed. Include the year of production and date of packaging.
1. Certification of each seed mixture for sod, identifying sod source, including name and telephone number of supplier.
1.4 DELIVERY, STORAGE, AND HANDLING
A. Packaged Materials: Deliver packaged materials in containers showing weight, analysis, and name of manufacturer. Protect materials from deterioration during delivery and while stored at site.
B. Seed: Deliver seed in original sealed, labeled, and undamaged containers.
02900 - 2
1.5 PROJECT CONDITIONS
A. Excavation: When conditions detrimental to plant growth are encountered, such as rubble fill, adverse drainage conditions, or obstructions, notify Architect before planting.
B. Do not install plants when the ambient temperature may drop to below 35° F or the wind velocity exceeds 30 mph.
1.6 COORDINATION AND SCHEDULING
A. Coordinate installation of planting materials during normal planting seasons for each type of plant material required.
B. Unless otherwise approved by the CO, all seeding and planting shall be accomplished during the period from:
1. May 1 through September 30.
PART 2 – PRODUCTS
2.1 SEED
A. All seed shall be new crop seed labeled in accordance with U.S. Department of Agriculture Rules and Regulations under the Federal Seed Act. Seed shall meet the requirements of Federal Specification JJJ-S-181. Seed which has become wet, moldy, or otherwise damaged will not be acceptable.
B. Seed shall be furnished separately or in mixture in standard containers with: Seed name; lot number; net weight; percentages of purity and of germination (in case of legumes, percentage of germination to include hard seed); and percentage of maximum weed seed content clearly marked for each kind of seed.
C. The contractor shall furnish the CO duplicate signed copies of a statement by the vendor, certifying that each lot of seed has been tested by a recognized laboratory for seed testing within 6 months of date of delivery. This statement shall include: Name and address of laboratory; date of test; lot number for each kind of seed; and results of tests as to name, percentages of purity and of germination, and percentage of weed content for each kind of seed furnished, and in case of a mixture, the proportions of each kind of seed. Legume seed shall be inoculated with approved cultures in accordance with the instructions of the manufacturer.
02900 - 3
D. Seed Substitution: Before any species substitution of a grass or wildflower seed will be considered, the contractor shall make inquiries of all sources at his disposal.
Written statements concerning the…