Specifications S-10-0297.docx
DOCX document 78 KB Posted
- Attached to
- RECOVERY - dOMINION CREEK TUNNELL AND TRESTLE REPAIR-SANDERS COUNTY LO LO NAT. FOREST, MT
- Solicitation number
- AG-82B1-S-10-0297
About this file
Specifications
View the file
Other files
| File | Type | Posted |
|---|---|---|
| A-004 S-10-0297 Abutment alterations.tif | TIF image | |
| A-004 Amendment Attachment.docx | DOCX document | |
| A-004 - S-10-0297.pdf | ||
| A-004 S-10-0297 West Abutment Drawing.tif | TIF image | |
| A-003 S-10-0297.pdf | ||
| MT20100001 heavy construction.txt | TXT text file | |
| A002-S-10-0297.pdf | ||
| Revised Sections B-M S-10-0297.doc | DOC document | |
| A001-S-10-0297.pdf | ||
| S-10-0297 Questionnaire.docx | DOCX document | |
| pages 27 through 32.pdf | ||
| sf 1442 - s-10-0297.pdf | ||
| pages 22 through 26.pdf | ||
| General Decision NumberMT 080008 MT8.doc | DOC document | |
| vicinity map.pdf | ||
| pages 7 through 11.pdf | ||
| Map and pages 3 through 6.pdf | ||
| pages 12 through 16.pdf | ||
| pages 17 through 21.pdf | ||
| S-0297 dominion creek construction ifb.doc | DOC document | |
| pages 33 through 36.pdf |
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Table of Contents
| Table of Contents | 1 |
| Preface | 3 |
| 101 - Terms, Format, and Definitions | 4 |
| 101.01 Meaning of Terms | 4 |
| 101.03 Abbreviations. | 4 |
| 101.04 Definitions. | 4 |
| 102 - Bid, Award, and Execution of Contract | 7 |
| 102 Bid, Award, and Execution of Contract | 7 |
| 103 - Scope of Work | 8 |
| Deletions | 8 |
| 104 - Control of Work | 9 |
| Deletions | 9 |
| 104.06 Use of Roads by Contractor | 9 |
| 105 - Control of Material | 10 |
| 105.02 Material Sources. | 10 |
| 105.02(a) Government-provided sources. | 10 |
| 105.05 Use of Material Found in the Work. | 10 |
| 106 - Acceptance of Work | 11 |
| 106.07 Delete | 11 |
| 107 - Legal Relations and Responsibility to the Public | 12 |
| 107.05 Responsibility for Damage Claims. | 12 |
| 107.06 Contractor’s Responsibility for Work. | 12 |
| 107.09 Legal Relationship of the Parties. | 12 |
| 107.10 Environmental Protection. | 12 |
| 108 - Prosecution and Progress | 14 |
| 108 Delete. | 14 |
| 109 - Measurement and Payment | 15 |
| 109 Deletions | 15 |
| 109.02 Measurement Terms and Definitions. | 15 |
| 109.10 Methods of Measurement ……………………………………………………………. | 15 |
| 153 - Contractor Quality Control………………………………………………...…………… | 17 |
153.07 Project Submittals……………………………………………………………………..17
| 155 - Schedules for Construction Contracts | 18 |
| 155.02 General. | 18 |
155.03 Delete………………………………………………………………………………….18
155.04 Delete………………………………………………………………………………….18
| 155.06 Schedule Updates…………………………………………………………………….. | 18 |
| 155.08 Delete………………………………………………………………………………… | 18 |
| 155.09 modify………………………………………………………………………………... | 18 |
| 156 - Public Traffic……………………………………………………………………………… | 19 |
| 156.03 Accommodating Traffic During ork…………………………………………………. | 19 |
| 156.08 Delete………………………………………………………………………………… | 20 |
| 203 - Removal of Structures and Obstructions…………………………………………………. | 21 |
| 203.01 Modify……………………………………………………………………………….. | 21 |
| 203.03 Salvaging Material…………………………………………………………………… | 21 |
| 203.04 Removing Material………………………………………………………………….. | 21 |
| 203.05 Disposal of Material…………………………………………………………………. | 21 |
| 253 - Gabions and Revetment Matresses…………………………………………..………….. | 23 |
| 253.02 Add……………………………………………………………………….………... | 23 |
| 253.03 Modify……………………………………………………………………….…….. | 23 |
| 253.09 Acceptance……………………………………………………………………..….. | 23 |
| 308 - Minor Crushed Aggregate………………………………………………………..……… | 24 |
308.01 - 308.08……………………………………………………………………….…. 24-25
| 409 - Asphalt Surface Treatment……………………………………………………………….. | 26 |
| 409.01 Modifications……………………………………………………………………….. | 26 |
| 409.03 Composition………………………………………………………………………… | 26 |
| 409.04 Equipment. (c) Pneumatic-tire rollers………………………………………………. | 26 |
409.05 Surface Preparation…………………………………………………………………. 26
| 409.11 Single-Course Surface Treatment…………………………………………………… | 26 |
| 409.13 Acceptance………………………………………………………………………….. | 26 |
| 556 - Bridge Railing…………………………………………………………………………….. | 27 |
Preface Preface_wo_03_15_2004_m Delete all but the first paragraph and add the following:
The Forest Service, US Department of Agriculture has adopted FP-03 for construction of National Forest System Roads.
`101 - Terms, Format, and Definitions
101.01 Meaning of Terms
Delete all references to the TAR (Transportation Acquisition Regulations) in the specifications.
101.03 Abbreviations.
Add the following to (a) Acronyms:
AFPA
MSHA
NIST
NESC
WCLIB
American Forest and Paper Association Mine Safety and Health Administration National Institute of Standards and Technology National Electrical Safety Code West Coast Lumber Inspection Bureau
Add the following to (b) SI symbols:
| mp |
| Milepost |
| ppm |
| Part Per Million |
| mfbm |
| Thousand Feet Board Measure |
101.04 Definitions.
Delete the following definitions and substitute the following:
Bid Schedule--The Schedule of Items.
Bridge--No definition.
Contractor--The individual or legal entity contracting with the Government for performance of prescribed work. In a timber sale contract, the contractor is the “purchaser”.
Culvert--No definition.
Right-of-Way--A general term denoting (1) the privilege to pass over land in some particular line (including easement, lease, permit, or license to occupy, use, or traverse public or private lands), or (2) Real property necessary for the project, including roadway, buffer areas, access, and drainage areas.
Add the following:
Adjustment in Contract Price--“Equitable adjustment,” as used in the Federal Acquisition Regulations, or “construction cost adjustment,” as used in the Timber Sale Contract, as applicable.
Change--“Change” means “change order” as used in the Federal Acquisition Regulations, or “design change” as used in the Timber Sale Contract.
Design Quantity--“Design quantity” is a Forest Service method of measurement from the FS-96 Forest Service Specifications for the Construction of Roads and Bridges. Under these FP specifications this term is replaced by the term “Contract Quantities”.
Forest Service--The United States of America, acting through the Forest Service, U.S. Department of Agriculture.
Neat Line--A line defining the proposed or specified limits of an excavation or structure.
Pioneer Road--Temporary construction access built along the route of the project.
Purchaser--The individual, partnership, joint venture, or corporation contracting with the Government under the terms of a Timber Sale Contract and acting independently or through agents, employees, or subcontractors.
Protected Streamcourse--A drainage shown on the plans or timber sale area map that requires designated mitigation measures.
Road Order--An order affecting and controlling traffic on roads under Forest Service jurisdiction. Road Orders are issued by a designated Forest Officer under the authorities of 36 CFR, part 260.
Schedule of Items--A schedule in the contract that contains a listing and description of construction items, quantities, units of measure, unit price, and amount.
Utilization Standards--The minimum size and percent soundness of trees described in the specifications to determine merchantable timber.
Add Figure 101-1—Illustration of road structure terms:
Figure 101-1—Illustration of road structure terms.
102 - Bid, Award, and Execution of Contract
102 Bid, Award, and Execution of Contract
Delete Section 102 in its entirety.
103 - Scope of Work Deletions
Delete all but subsection 103.01 Intent of Contract.
Dominion Creek Tunnel - This work consists of removing existing deteriorated concrete on the wall of the tunnel and replacing with new concrete and removing approximately 4 inches of ballast.
Dominion Creek Trestle - This work consists of removing and disposing of the existing deck (concrete and ballast) and replacing with a new treated timber deck, installing a new cable handrail and concrete repair of the abutments.
Railbed from East Portal to Saltese – This work consists of repairing approximately 15 potholes, removing talus from approximately 10 small slide areas, installing 3 sections of gabion basket retaining wall, spreading ballast from the Dominion Creek Tunnel and Trestle and spreading crushed aggregate surfacing.
104 - Control of Work
Deletions
Delete Sections 104.01, 104.02, and 104.04.
Add the following subsection:
104.06 Use of Roads by Contractor
The Contractor is authorized to use roads under the jurisdiction of the Forest Service for all activities necessary to complete this contract, subject to the limitations and authorizations designated in the Road Order(s) or described in the contract, when such use will not damage the roads or national forest resources, and when traffic can be accommodated safely.
105 - Control of Material
105.02 Material Sources.
105.02(a) Government-provided sources.
Add the following:
Comply with the requirements of 30 CFR 56, subparts B and H. Use all suitable material for aggregate regardless of size unless otherwise designated. When required, re-establish vegetation in disturbed areas according to section 625.
105.05 Use of Material Found in the Work.
Delete 105.05 (a) and (b) and the last sentence of the second paragraph and substitute the following:
Materials produced or processed from Government lands in excess of the quantities required for performance of this contract are the property of the Government. The Government is not obligated to make reimbursement for the cost of producing these materials.
106 - Acceptance of Work
106.07 Delete
Delete subsection 106.07.
107 - Legal Relations and Responsibility to the Public
107.02 Protection and Restoration of Property and Landscape
Add the following paragraph:
The Contractor is responsible for repairing any damage to the East Portal parking lot or the access road to the parking lot, which may result from the Contractor’s hauling or construction equipment. The Contracting Officer will inspect the parking lot surface prior to the Hiawatha Bicycle Trail opening in May and at completion of the work on this contract to determine what level of regrading is required. The Contractor will be responsible for any regrading which is necessary.
107.05 Responsibility for Damage Claims.
Delete the entire subsection.
107.06 Contractor’s Responsibility for Work.
Delete the following from the first paragraph.
“except as provided in Subsection 106.07”.
107.08 Sanitation, Health and Safety.
Add the following:
30 days before beginning any work, furnish the Contracting Officer with a Safety Plan detailing safety measures, equipment, etc. which will be implemented and used to ensure Contractor and Public safety.
107.09 Legal Relationship of the Parties.
Delete the entire subsection.
107.10 Environmental Protection.
Add the following:
Design and locate equipment repair shops, stationary refueling sites, or other facilities to minimize the potential and impacts of hazardous material spills on Government land.
Before beginning any work, submit a Hazardous Spill Plan. List actions to be taken in the event of a spill. Incorporate preventive measures to be taken, such as the location of mobile refueling facilities, storage and handling of hazardous materials, and similar information. Immediately notify the CO of all hazardous material spills. Provide a written narrative report form no later than 24 hours after the initial report and include the following:
· Description of the item spilled (including identity, quantity, manifest number, and other identifying information).
· Whether amount spilled is EPA or state reportable, and if so whether it was reported, and to whom.
· Exact time and location of spill including a description of the area involved.
· Containment procedures.
· Summary of any communications the Contractor had with news media, Federal, state and local regulatory agencies and officials, or Forest Service officials.
· Description of clean-up procedures employed or to be employed at the site including final disposition and disposal location of spill residue.
When available provide copies of all spill related clean up and closure documentation and correspondence from regulatory agencies.
The Contractor is solely responsible for all spills or leaks that occur during the performance of this contract. Clean up spills or leaks to the satisfaction of the CO and in a manner that complies with Federal, state, and local laws and regulations.
108 - Prosecution and Progress
108 Delete.
Delete Section 108 in its entirety.
109 - Measurement and Payment 109.00_nat_us_02_17_2005 109 Deletions Delete the following entire subsections:
109.06 Pricing of Adjustments.
109.07 Eliminated Work.
109.08 Progress Payments.
109.09 Final Payment.
109.02_nat_us_06_16_2006
109.02 Measurement Terms and Definitions.
(b) Contract quantity.
Add the following:
Contract quantities will be adjusted only when there are errors in the original design of 15% or more.
Change the following:
“(b) Cubic yard” to “(c) Cubic yard”.
Add the following definition:
(p) Thousand Board Feet (Mbf). 1,000 board feet based on nominal widths, thickness, and extreme usable length of each piece of lumber or timber actually incorporated in the job. For glued laminated timber, 1,000 board feet based on actual width, thickness, and length of each piece actually incorporated in the job.
Add the following Subsection:
109.10 Methods of Measurement
One of the following methods of measurement for determining final payment is DESIGNATED IN THE SCHEDULE OF ITEMS for each PAY ITEM:
(a) Designed Quantities (DQ). These quantities denote the final number of units to be paid for under the terms of the contract. They are based upon the original design data available prior to advertising the project. Original design data include the preliminary survey information, design assumptions, calculations, drawings, and the presentation in the contract. Changes in the number of units DESIGNATED IN THE SCHEDULE OF ITEMS may be authorized under any of the following conditions:
(1) Changes in the work authorized by the CO.
(2) A determination by the CO that errors exist in the original design that cause a PAY ITEM quantity to change by 15 percent or more.
(3) A written request submitted to the CO showing evidence of errors in the original design that cause the quantity of a PAY ITEM to change by 15 percent or more. The evidence must be verifiable and consist of calculations, drawings, or other data that show how the designed quantity is in error.
(b) Stake Quantities (SQ). These quantities are determined from staked measurements prior to construction.
(c) Actual Quantities (AQ). These quantities are determined from measurements of completed work.
(d) Vehicle Quantities (VQ). These quantities are measured or weighed in hauling vehicles.
(e) Lump Sum Quantities (LSQ). These quantities denote one complete unit of work as required by or described in the contract, including necessary materials, equipment, and labor to complete the job.
153 – Contractor Quality Control
Add the following:
153.07 Project Submittals.
At a minimum the Contractor shall provide project submittals as shown on the Submittal Log below. Complete submittal requirements are listed in the Standard Specifications, Forest Service Special Specifications and on the Plans.
Submittal Log
| Log No. |
| Incidental to |
Pay Item(s)
| Description of Submittal |
| Type of Submittal |
| Requirement found in Specification No. |
/Drawings Additional Specification References
| 1 |
| 151 |
| Health & Safety Plan |
| Plan |
| FSSS 105.02(b) |
| 2 |
| 151 |
| Hazardous Spill Plan |
| Plan |
| FSSS 107.10 |
| 3 |
| 151 |
| Contractor Quality Control Plan |
| Plan |
| 153.02 |
| 552.09 |
| 4 |
| 151 |
| Traffic Control Plan |
| Plan |
| FSSS 156.03 |
| 5 |
| 151 |
| Construction Schedule |
| Plan |
| 155.02 |
| 6 |
| 151 |
| Soil Erosion and Pollution Control Plan |
| Plan |
| FSSS 157.03 |
| 7 |
| 308 |
| Aggregate Gradation & Quality Properties |
| Material |
Certification
| FSSS 308306 |
| 703.06, Drawings |
| 8 |
| 409 |
| Aggregat gradation |
| Certification |
| 409.13 |
| 703.10 |
| 9 |
| 409 |
| Emulsified Asphalt |
| Certification |
| 409.13 |
| 702.03 |
| 10 |
| 552 |
| Structural Concrete: Mix Design |
| Mix Design |
| 552.03 |
| 553, 53A, |
| 11 |
| 552 |
| Structural Concrete: Testing |
| Test Results |
| 552.19 |
| 106, Drawings |
| 12 |
| 552 |
| Falsework and Forming |
| Drawing |
| 552.19 |
| 562.04 |
| 13 |
| 555 |
| Steel Structures: AISC Steel Certification |
| Fabrication Certification |
| 555.03 |
| FSSS 555.03 |
| 14 |
| 555 |
| Steel Structures: Materials |
| Material |
Certification
| 555.21 |
| 106 |
| 15 |
| 557 |
| Timber Structures |
| Shop Drawing |
| 104.03 |
| 557, Drawings |
| 16 |
| 557 |
| Timber Structures: Materials |
| Material |
Certification
| 557.19 |
| 106, 716, Drawings |
| 17 |
| 557 |
| Treatment Certification |
| Certification |
| 557.02 |
| 716.03 |
Drawings
155 - Schedules for Construction Contracts Construction Requirements
155.02 General.
Delete the portion of this section beginning with “Use the Bar Chart Method………….
155.03 Bar Chart Method (BCM).
Delete this Section.
155.04 Critical Path Method (CPM).
Delete this Sctions.
155.06 Schedule Updates.
Delete Subsection (b) in the second paragraph.
Measurement 155.08
Delete this Section.
Payment
155.09
Replace this Section with the following:
No separate payment will be made for “Schedules for Construction Contracts.”
156 – Public Traffic
156.03 Accommodating Traffic During Work.
Delete the first paragraph and replace with the following:
Accommodate traffic according to the requirements set forth below and in the MUTCD and Section 635. Submit a traffic control plan for acceptance at least 30 days before intended use.
Add the following project specific requirements.
Two Forest Service contracts will be active concurrently with this project: Dominion Creek Culvert Replacement and East Portal Trailhead Parking Lot Expansion.
The Dominion Creek Culvert project replaces 2 culverts on Dominion Creek Road No. 810 and will be active between July 15 and September 1, 2010. Dominion Trestle crosses NFSR 810 between the 2 culverts. Realizing that the road will need to be closed during some periods of work to minimize hazards, the Forest Service will coordinate road closures as necessary.
The East Portal Trailhead parking lot will be under reconstruction at some point during this contract. It is anticipated most work will occur between October 2010 and june 1011. Access through the parking lot during construction will be coordinated by the Forest Service to accommodate both contracts.
The Contractor will be allowed to close National Forest System Road (NFSR) 810 at the Dominion Creek Trestle as needed in accordance with the approved safety plan. The Forest Service must notify the public 7 days prior to any closure. Place advance warning signs at road intersections above and below the work site as approved by the Contracting Officer.
The Contractor will be allowed to close NFSR 300.1 between the East Portal parking lot and the Dominion Creek Tunnel to all traffic as needed in accordance with the approved safety plan. The Forest Service must notify the public 7 days prior to any closure.
Access to the Milwaukee Railroad grade is at the East Portal Trailhead parking lot. Construction equipment will only be allowed access through the parking lot on weekdays before 10 am and after 4 pm due to heavy public use of the parking lot. Employee passenger vehicles can pass through the parking lot at any time. The access restrictions through the parking lot are lifted between October 2, 2010 and May 15, 2011.
Equipment and material staging will be allowed at wide areas along the railroad grade between Dominion Creek and the East Portal Trailhead (there are at least 5 suitable areas). Additional staging will be allowed on National Forest System land only with CO approval.
Physical road closure devices, and signing, will be installed prior to winter shutdown to prevent access by the public during the winter season.
It is the responsibility of the Contractor to schedule delivery of materials, equipment and all necessary supplies to the site. To ensure that the construction can be completed within the specified contract time. The Contractor is required to provide, install, maintain and remove warning signs and barricades for road closure periods in accordance with the MUTCD and as submitted and approved in the traffic control plan.
Delete the following from the last sentence of the last paragraph:
according to Subsection 106.07(b)
156.08 Traffic and Safety Supervisor.
Delete this subsection in its entirety.
203 – REMOVAL OF STRUCTURES AND OBSTRUCTIONS
Description
203.01 Replace this section with the following:
This work consists of removing and disposing of the 168 existing concrete deck ballast boxes (including steel brackets and timber posts) on the Dominion Creek Trestle. This work includes removal of treated timber shoring under the east abutment.
The work also consists of removing and spreading waste ballast from the tunnel and trestle.
Construction requirements
203.03 Salvaging Material.
Add the following:
Do not remove or damage the existing overhead timber towers and cross members.
03.04 Removing Materials.
Add the following:
Concrete removal in the Dominion Creek Tunnel and on the Dominion Creek Trestle abutments is a subsidiary to the respective 552 Structural Concrete repair and patching pay items.
Either remove this concrete from National Forest System (NFS) lands or reduce in size to 6 inches or less and scatter. Any steel or timber which is encountered must be removed from NFS lands. Tunnel concrete must be scattered before ballast is removed and removed with the waste ballast.
Spread waste ballast from the tunnel and trestle at Waste Area 1 or 2 as directed by the CO. Place ballast material by end dumping to the depths directed by the CO. Adjust the moisture content of the material to obtain a mass that will not visibly deflect under the load of the hauling and spreading equipment. Operate compaction equipment over the full width of the cross section until there is no visible evidence of further consolidation. Make at least three complete passes. After leveling and compacting, cover the waste ballast with crushed aggregate surfacing as shown on the drawings and specified in Section 308.
203.05 Disposing of Material.
Add the following to Section (a):
The concrete deck sections can be temporarily stored at several staging areas between the Dominion Creek Tunnel and the East Portal parking lot. The Contracting Officer will designate these areas.
Delete the following sections:
(b) Burn and
(c) Bury
Section 253 – GABIONS AND REVETMENT MATRESSES
Material
253.02
Add the following:
Talus rock removed as Pay Item 20435 may be used as gabion rock provided it meets the requirements of Section 70501(c)(1). . If needed, the Contacting Officer will designate additional gabion rock source sites on the project.
Construction Requirements 253.03 Replace this section with the following:
Construct gabions as shown on the drawings and at stationing locations to be determined by the Contracting Officer.
263.09 Acceptance.
Delete the fourth paragraph.
308 - Minor Crushed Aggregate
Delete section 308 in its entirety and replace with the following:
Description
308.01 This work consists of placing Government furnished aggregate or furnishing and placing crushed aggregate for bedding, backfill and roadway aggregate course.
Material
308.02 Conform to the following Subsections:
| Crushed aggregate | 703.06 | |
| Water | 725.01 |
Construction Requirements
308.03 Preparing Surface. Prepare the roadway surface on which aggregate course is placed as shown on the plans.
308.04 Placing Crushed Aggregate.
(a) Roadway aggregate. Mix the aggregate and adjust the moisture content to obtain a uniform mixture with moisture content suitable for compaction. Spread and shape the mixture on the prepared surface in a uniform layer.
Do not place the mixture in a layer exceeding 6 inches in compacted thickness. When more than one layer is necessary, compact each layer according to Subsection 308.05(a) before placing the next layer.
(b) Bedding and backfill aggregate. Place and shape the mixture in layers that, when compacted, do not exceed 6 inches in depth.
308.05 Compacting and Finishing Crushed Aggregate.
(a) Roadway aggregate. Compact as follows:
Compact the aggregate by operating compaction equipment over the total width until visible deformation ceases. A minimum of three complete roller passes shall be made at moisture content suitable for compaction.
(b) Bedding and backfill aggregate. Compact in 6 inch lifts by using a Forest Service approved mechanical compactor until no visible deformation is observed over the entire area of aggregate.
308.06 Acceptance. Crushed aggregate will be evaluated under Subsections 106.02 and 106.03. Furnish a production certification including gradation and quality properties for each source.
Construction of roadway aggregate courses will be evaluated under Subsections 106.02 and 106.04. Method 2 compaction will be evaluated under Section 106.04.
Placement of bedding and backfill aggregate will be evaluated under Subsection 106.02 and Section 209.
Preparation of the surfaces on which crushed aggregate is placed will be evaluated under Section 303 and 209 as applicable.
Measurement
308.07 Measure the Section 308 items listed in the bid schedule according to Subsection 109.02 and the following as applicable.
Measure crushed aggregate by the cubic yard in-place on the road.
Measure width horizontally to include the top of aggregate width including designed widening. Measure the length horizontally along the centerline of the roadway.
Payment
308.08 The accepted quantities will be paid at the contract price per unit of measurement for the Section 308 pay item listed in the bid schedule. Payment will be full compensation for the work prescribed in this Section. See Subsection 109.05.
Section 409 – ASPHALT SURFACE TREATMENT
409.01.
Replace the first paragraph with the following:
This work consists of constructing a single asphalt surface treatment with aggregate across the treated timber deck of the Dominion Creek Trestle.
Construction Requirements
409.03 Composition.
Delete Sections (a) and (c).
409.04 Equipment. (c) Pneumatic-tire rollers.
Replace the first sentence of this Subsection with the following:
Furnish a minimum of one pneumatic tire roller with the following capacities:
409.05 Surface Preparation.
Delete this section and replace with the following:
Ensure that the timber surface is dry and free of loose dirt and other objectionable material.
409.11 Single-Coarse Surface Treatment.
Delete the second and third sentences of the first paragraph and replace with the following:
Apply the emulsified asphalt at an estimated rate of .16 to .20 gallons per square yard. Apply the aggregate at an estimated rate of 20 to 22 pounds per square yard. Apply according to Subsections 409.08 and 409.09.
Delete the second paragraph.
Delete the third paragraph and replace with the following:
Maintain the surface by distributing blotter according to Section 411 to absorb any free asphalt and by repairing areas deficient in aggregate. Spread by hand any areas with excess aggregate. Do not sweep off excess aggregate.
409.13 Acceptance.
Delete the first paragraph and replace with the following:
Sampling and testing is not required for this item, however, the Contractor shall submit certification that the aggregate and asphalt materials meet the requirements of the these specifications..
Section 556 – Bridge Railing
556.01 Delete this section and replace with the following:
This work consists of furnishing, fabricating and erecting a 7 strand cable handrail on the Dominion Creek Trestle and a single cable underdeck lifeline for the timber inspection walkway.
Material 556.02 Add the following:\ Wire Rope or Wire Cable 709.02 image1.png