FP03 FS Specs_Blue Sky.doc

DOC document 243 KB Posted

Attached to
RECOVERY - BRIDGE REPLACEMENT, BLUE SKY TRAIL, FORTINE RD, MONTANA
Solicitation number
AG-82B1-S-10-0026
Issued by

About this file

Specifications

View the file

Other files

File Type Posted
Best Management Practices 10-0026.docx DOCX document
A-4 10-0026.pdf PDF
A-3 S-10-0026.pdf PDF
A-3 S-10-0026.pdf PDF
A-2 S-10-0026.pdf PDF
A- 001 S-10-0026.pdf PDF
S- 10-0026 B .docx DOCX document
Wage Determination Montana.txt TXT text file
blue sky maps and drawings.pdf PDF
Blue Sky Spec Cover Page.docx DOCX document
10-0026 cover.pdf PDF
Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Table of Contents iTable of Contents

Preface iii 101 - Terms, Format, and Definitions

101.01 Meaning of Terms.

101.03 Abbreviations.

101.04 Definitions.

102 - Bid, Award, and Execution of Contract 103 - Scope of Work 104 - Control of Work

104.03 Specifications and Drawings.

104.05 Load Restrictions.

105 - Control of Material

105.02 Material Sources

106 - Acceptance of Work 106.07 107 - Legal Relations and Responsibility to the Public

107.02 Protection and Restoration of Property and Landscape.

107.05 Responsibility for Damage Claims.

107.06 Contractor’s Responsibility for Work.

107.09 Legal Relationship of the Parties.

107.10 Environmental Protection.

108 - Prosecution and Progress 109 - Measurement and Payment

109.02 Measurement Terms and Definitions.

109.06 Pricing of Adjustments.

109.07 Eliminated Work.

109.08 Progress Payments.

109.09 Final Payment.

109.10 Methods of Measurement

151 - Mobilization 155 - Schedules for Construction Contracts 156 - Public Traffic

156.03 Accommodating Traffic During Work.

156.04 Maintaining Roadways During Work.

156.08 Traffic and Safety Supervisor.

157 - Soil Erosion Control

157.02 Materials

157.03 General

157.04 Controls and Limitations on Work.

201 – Clearing and Grubbing

201.06 Disposal

201.08 203 - Removal of Structures and Obstructions

203.03 Salvaging Material.

203.05 Disposing of Material.

204 - Excavation and Embankment

204.11 Compaction.

204.13 Sloping, Shaping, and Finishing.

204.14 Disposal of Unsuitable or Excess Material.

204.16 Waste

208 - Structure Excavation and Backfill for Selected Major Structures 272 - Geocell Abutment Stabilization 308 – Minor Crushed Aggregate

308.05 Compacting and Finishing Crushed Aggregate.

553A – Precast Concrete Structures 622 - Rental Equipment

622.02 Rental Equipment

622.04 625 - Turf Establishment

625.03 General.

625.04 Preparing Seedbed.

625.05 Watering

625.06 Fertilizing.

625.07 Seeding.

625.08 Mulching.

625.09 Protecting and Caring for Seeded Areas.

625.11 Measurement

703 - Aggregate

703.06 Crushed Aggregate

Preface

Preface_wo_03_15_2004_m Delete all but the first paragraph and add the following:

The Forest Service, US Department of Agriculture has adopted FP-03 for construction of National Forest System Roads.

101 - Terms, Format, and Definitions 101.01_nat_us_02_17_2005

101.01 Meaning of Terms.

Add the following:

Delete all references in FP-03 to Transportation Acquisition Regulations (TAR).

101.03_nat_us_02_17_2005

101.03 Abbreviations.

Add the following to (a) Acronyms:

AFPA

MSHA

NIST

NESC

WCLIB

American Forest and Paper Association Mine Safety and Health Administration National Institute of Standards and Technology National Electrical Safety Code West Coast Lumber Inspection Bureau

Add the following to (b) SI Symbols:

mp
Milepost
ppm
Part Per Million

101.04_nat_us_02_22_2005

101.04 Definitions.

Delete the following definitions and substitute the following:

Bid Schedule--The Schedule of Items.

Bridge--No definition.

Contractor--The individual or legal entity contracting with the Government for performance of prescribed work. In a timber sale contract, the contractor is the “purchaser”.

Culvert--No definition.

Right-of-Way--A general term denoting (1) the privilege to pass over land in some particular line (including easement, lease, permit, or license to occupy, use, or traverse public or private lands), or (2) Real property necessary for the project, including roadway, buffer areas, access, and drainage areas.

Add the following:

Adjustment in Contract Price--“Equitable adjustment,” as used in the Federal Acquisition Regulations, or “construction cost adjustment,” as used in the Timber Sale Contract, as applicable.

Change--“Change” means “change order” as used in the Federal Acquisition Regulations, or “design change” as used in the Timber Sale Contract.

Forest Service--The United States of America, acting through the Forest Service, U.S. Department of Agriculture.

Neat Line--A line defining the proposed or specified limits of an excavation or structure.

Protected Streamcourse--A drainage shown on the plans or timber sale area map that requires designated mitigation measures.

Road Order--An order affecting and controlling traffic on roads under Forest Service jurisdiction. Road Orders are issued by a designated Forest Officer under the authorities of 36 CFR, part 260.

Schedule of Items--A schedule in the contract that contains a listing and description of construction items, quantities, units of measure, unit price, and amount.

Add Figure 101-1—Illustration of road structure terms:

Figure 101-1—Illustration of road structure terms.

102 - Bid, Award, and Execution of Contract

102.00_nat_us_02_16_2005

102 Bid, Award, and Execution of Contract

Delete Section 102 in its entirety.

103 - Scope of Work

103.01 Intent of Contract. Delete this subsection and replace with the following:

Blue Sky Trail Bridge Replacement This project is for the removal of an existing treated timber trail bridge over Grave Creek and replacing it with a new glue laminated timber trail bridge. This project is located in the Fortine Ranger District of the Kootenai National Forest in Section 12, Township 36 North, Range 25 West, in Lincoln County, Montana.

This project includes removing and disposing an existing timber trail bridge, structural excavation, parking area re-grading, backfilling, compacting, furnishing and constructing a glue laminated timber trail bridge with handrail, furnishing and constructing a timber abutment, furnishing and constructing a horse loading ramp, furnishing and setting precast concrete, riprap, and hauling and placing aggregate surfacing. The precise details of performing the work are not stipulated except as considered essential for the successful completion of the work. Furnish all labor, material, equipment, tools, transportation, and supplies necessary to complete the work according to the contract.

Delete the remaining subsections in this Section.

104 - Control of Work

104.01_nat_05_11_2004

104 Control of Work:

Delete sections 104.01, 104.02, and 104.04.

104.03_nat_05_11_2004

104.03 Specifications and Drawings.

Add the following:

(c) As-Built-Plans. Furnish one set of as built plans. The Government will provide one set of contract plans to be used exclusively for recording the as-built details of the project. Use red pencil or red ink to record the information on the as-built plans.

Note all additions or revisions to the location, character, and dimensions of the prescribed work shown on the contract plans. Line out all details shown that are not applicable to the completed work. Check off details shown that were incorporated into the completed work without change.

Retain the plans at the project site and, as work progresses, continually update them to reflect the as-built details. Upon request, make the plans available to the CO to review for compliance with these specifications.

Show the following types of changes on the as-built plans:

(1) Typical section(s)

(a) Revisions in dimensions

(b) Revisions in materials

(2) Plan and profile

· Revisions to the alignment

· Changes in the construction limits

· Revisions in location, type, and grade of road approaches

· Location and type of utilities

· Location, size, and type of underdrains

· Skew of culverts

· Channel changes

· Location of monuments and permanent references

· Elevations for all aerial and underground crossings of utilities

· Location, length, and type of fencing

· Revisions to grades, elevations, and stationing of intersection PIs

· Equations

· Culvert diameter, length, type, and stationing. On culvert extensions, indicate the length of the existing pipe and the length of the extension.

· Location, length, stationing, and type of retaining walls

· Location, length, stationing, and end treatment of guardrail

(3) Bridge

(a) Stationing of bridge ends

(b) Revisions to footing and seal elevations

(c) Pile length, size, type, and tip elevation

(d) Any changes in plan or dimensions including any major changes in reinforcing

(4) Miscellaneous

(a) Revisions to parking areas or turnouts

(b) Final location, type and length of curbs, sidewalks, etc.

Furnish the as-built working plans to the CO before the final inspection. Correct all details found during the final inspection that are not shown on the as-built plans and return to the CO within 5 days.

104.05_nat_05_17_2004

104.05 Load Restrictions.

Delete Section 104.06 and replace with the following:

The Contractor is authorized to use roads under the jurisdiction of the Forest Service for all activities necessary to complete this contract, subject to the limitations and authorizations designated in the Road Order(s) or described in the contract, when such use will not damage the roads or national forest resources, and when traffic can be accommodated safely.

105 - Control of Material

105.02_nat_05_11_2004

105.02 Material Sources

Add the following before the first paragraph.

Sources have been designated for this project as follows:

Blue Sky Trail Bridge Replacement Borrow Material - Government Source - Imported Borrow material will be available at the Grave Creek Pit located approximately 10 miles downstream from the site in Section 6, T. 35 N., R. 25 W.

Riprap Source – Contractor Furnished. There is no available Government source for riprap for this project.

Crushed Aggregate Source – Contractor Furnished. There is no available Government source for Crushed Aggregate for this project.

Under (b) Contractor-located sources add the following:

Prior to any pit development or use of materials, the pit site shall be approved by the CO that the pit site is free of noxious weed as listed on the "All States Noxious Weeds List”.

106 - Acceptance of Work

106.07_nat_us_05_11_2004

106.07 Delete

Delete subsection 106.07.

107 - Legal Relations and Responsibility to the Public

107.02 Protection and Restoration of Property and Landscape.

Add the following:

Work within the wetted perimeter of streams only during low flow, estimated to be after July 15th. The Contractor will be allowed to cross the stream with equipment a maximum of four (4) crossings. No work in the stream or equipment crossings may take place from September 1 to May 15.

107.05_nat_us_05_11_2004

107.05 Responsibility for Damage Claims.

Delete the entire subsection.

107.06_nat_us_04_27_2005

107.06 Contractor’s Responsibility for Work.

Delete the following:

“except as provided in Subsection 106.07”.

107.09_nat_us_05_11_2004

107.09 Legal Relationship of the Parties.

Delete the entire subsection:

107.10_nat_us_02_23_2005

107.10 Environmental Protection.

Add the following:

Design and locate equipment repair shops, stationary refueling sites, or other facilities to minimize the potential and impacts of hazardous material spills on Government land.

Immediately notify the CO of all hazardous material spills. Provide a written narrative report form no later than 24 hours after the initial report and include the following:

· Description of the item spilled (including identity, quantity, manifest number, and other identifying information).

· Whether amount spilled is EPA or state reportable, and if so whether it was reported, and to whom.

· Exact time and location of spill including a description of the area involved.

· Containment procedures.

· Summary of any communications contractor had with news media, Federal, state and local regulatory agencies and officials, or Forest Service officials.

· Description of clean-up procedures employed or to be employed at the site including final disposition and disposal location of spill residue.

When available provide copies of all spill related clean up and closure documentation and correspondence from regulatory agencies.

The Contractor is solely responsible for all spills or leaks that occur during the performance of this contract. Clean up spills or leaks to the satisfaction of the CO and in a manner that complies with Federal, state, and local laws and regulations.

108 - Prosecution and Progress

108.00_nat_05_11_2004

108 Delete.

Delete Section 108 in its entirety.

109 - Measurement and Payment

109.02_nat_05_11_2004

109.02 Measurement Terms and Definitions.

Add the following definition:

(p) Thousand Board Feet (Mbf). 1,000 board feet based on nominal widths, thickness, and extreme usable length of each piece of lumber or timber actually incorporated in the job. For glued laminated timber, 1,000 board feet based on actual width, thickness, and length of each piece actually incorporated in the job.

109.03_nat_05_11_2004

109 Deletions

Delete the following entire subsections:

109.06 Pricing of Adjustments.

109.07 Eliminated Work.

109.08 Progress Payments.

109.09 Final Payment.

Add the following Subsection:

109.10 Methods of Measurement

One of the following methods of measurement for determining final payment is DESIGNATED IN THE SCHEDULE OF ITEMS for each PAY ITEM:

(a) Designed Quantities (DQ). These quantities denote the final number of units to be paid for under the terms of the contract. They are based upon the original design data available prior to advertising the project. Original design data include the preliminary survey information, design assumptions, calculations, drawings, and the presentation in the contract. Changes in the number of units DESIGNATED IN THE SCHEDULE OF ITEMS may be authorized under any of the following conditions:

(1) Changes in the work authorized by the CO.

(2) A determination by the CO that errors exist in the original design that cause a PAY ITEM quantity to change by 15 percent or more.

(3) A written request submitted to the CO showing evidence of errors in the original design that cause the quantity of a PAY ITEM to change by 15 percent or more. The evidence must be verifiable and consist of calculations, drawings, or other data that show how the designed quantity is in error.

(b) Stake Quantities (SQ). These quantities are determined from staked measurements prior to construction.

(c) Actual Quantities (AQ). These quantities are determined from measurements of completed work.

(d) Vehicle Quantities (VQ). These quantities are measured or weighed in hauling vehicles.

(e) Lump Sum Quantities (LSQ). These quantities denote one complete unit of work as required by or described in the contract, including necessary materials, equipment, and labor to complete the job.

151 - Mobilization

151.01_0105_us_02_23_2005

Delete Section 151 in its entirety and replace with the following.

Description

151.01 This work consists of moving personnel, equipment, material, and incidentals to the project and performing all work necessary before beginning work at the project site; obtaining of permits, insurance, and bonds. This work also includes washing and treating construction equipment and vehicles necessary for equipment transport to remove seeds, plants, and plant fragments before the equipment is used on Forest Service lands, according to the requirements within.

Construction Requirements

Wash the sides, tops, and undercarriages of all construction equipment. Remove all seeds, plants, plant fragments, dirt, and debris from the construction equipment. Only equipment inspected by the Forest Service will be allowed to operate within the project area. All subsequent move-ins of equipment to the project area will be treated in the same manner as the initial move-in. This requirement does not apply to cars, pickup trucks, and other vehicles that regularly travel between the construction site and areas off the National Forest.

Equipment will be considered free of soil, seed, and other such debris when a visual inspection does not disclose such material. Disassembly of equipment, components or the need for specialized inspection tools is not required.

Notify the CO in writing at least 72 hours before moving any construction equipment onto the national forest. Notification will include an agreed upon location where the equipment will be available for inspection by the Forest Service. Inspection will be required after every cleaning.

Use methods of cleaning and locations for cleaning approved by the CO.

For work at a commercial washing facility, use an approved facility.

New infestations of noxious weeds of concern to Forest Service and identified by either Contractor or Forest Service, in the Project Area or on the haul route, will be promptly reported to the other party. Contractor and Forest Service will agree on treatment methods to reduce or stop the spread of noxious weeds when new infestations are found. A current list of noxious weeds of concern to Forest Service is available at each Forest Service office.

Measurement

151.02 Clean equipment prior to moving onto this project. The initial cleaning will not be included in the measurement for payment. Payment for cleaning will only be made if subsequent cleanings are ordered by the CO. Measurement shall be on an “each” basis, meaning one complete cleaning of all equipment required for this contract. Subsequent cleanings necessitated by the Contractor’s actions but not directed by the CO will not be included in the measurement for payment.

Measure mobilization according to Subsection 109.02.

Payment

151.03 The accepted quantity, measured as provided in Subsection 109.02, will be paid at the contract price per unit of measurement for the Section 151 pay item shown in the bid schedule. Payment will be full compensation for the work prescribed in this Section. See Subsection 109.05.

Progress payments for mobilization lump sum will be paid as follows:

(a) If applicable, bond premiums will be reimbursed according to FAR Clause 52.232-5 Payments Under Fixed-Price Construction Contracts, after receipt of the evidence of payment.

(b) When 5 percent of the original contract amount is earned from other bid items, 50 percent of the mobilization item, or 5 percent of the original contract amount, whichever is less, will be paid.

(c) When 10 percent of the original contract amount is earned from other bid items, 100 percent of the mobilization item, or 10 percent of the original contract amount, whichever is less, will be paid.

(d) Any portion of the mobilization item in excess of 10 percent of the original contract amount will be paid after final acceptance.

Include all costs associated with the initial cleaning of equipment in the unit bid price for Mobilization. Cleaning for subsequent move-ins will not be paid for unless after a suspension ordered by the CO.

155 - Schedules for Construction Contracts

Delete Section 155 in its entirety.

156 - Public Traffic

156.03_nat_11_05_2004

156.03 Accommodating Traffic During Work.

Delete the first paragraph and replace with the following:

Accommodate traffic according to the requirements set forth below, MUTCD, and Section 635. Submit a traffic control plan for acceptance at least 30 days before intended use.

Delete the following from the last paragraph:

…..according to Subsection 106.07(b)

Add the following:

The contractor is allowed to close Road No. 114 to traffic in the immediate vicinity of the project site with maximum delays of two (2) hours Monday thru Thursday with no delays Friday thru Sunday and on Federal holidays.

Give the CO at least 14 days advance written notice prior to any road closure period to allow public notice of the closure by the Forest Service.

Provide and install advance road closed signs, as shown below, at the junction of Road 114 and Highway 93 and the junction of Road 114 and Road 319.

156.04 Maintaining Roadways During Work.

(a) Add the following:

The construction of detour roads for this project is not allowed.

156.08 Traffic and Safety Supervisor.

Delete this section in its entirety.

157 - Soil Erosion Control

157.02_01_08_23_2004

157.02 Materials

Add the following:

Provide bales, wattles, logs and rolls from a certified noxious weed free source.

157.03_0510_11_10_2004

Construction Requirements

157.03 General

Delete the first two paragraphs and add the following:

"This work includes submitting an Erosion Control Plan detailing permanent and temporary control measures to minimize erosion and sedimentation during and after construction according to the contract specifications, contract permits, Section 107, and this Section. Contract permits amend the requirements of this Section. Do not modify the type, size, or location of any control or practice without approval. Submit the erosion control plan proposal at least 7 days before operations begin to the Contracting Officer for approval.

The erosion control plan reflects special concerns and measures necessary to protect resources and government improvements. The Erosion Control Plan shall, at a minimum:

1.

Describe the construction activities and sequence of implementation relating to specific erosion control measures.

2. Describe the location and type of permanent controls to be implemented during construction.

3.

Describe the location and type of temporary controls to be implemented during construction.

4.

For work in stream channels with flowing water include a detailed dewatering plan.

5.

Include procedures and temporary control measures to be implemented to minimize sediment delivery during re-watering of any new culvert with streambed simulation material.

6.

For work in stream channels without flowing water describe level of ground and vegetative disturbance and measures to reduce potential sediment delivery.

7. Describe what monitoring will take place.”

Add to the third paragraph:

“Upon completion of construction at the site, all temporary dewatering materials and equipment are to be removed from Government property."

157.04 Controls and Limitations on Work.

Add the following to the second paragraph:

“Temporary erosion control measures will be in place at the end of each days operation if greater than 30 percent chance of rainfall is predicated. Earthwork operations may be temporarily suspended if significant rainfall is forecasted.”

201 – Clearing and Grubbing Construction Requirements

201.06 Disposal. Delete this subsection and substitute the following:

“Dispose of construction slash by either scattering outside the clearing limits without damaging trees, or by placing on embankment slopes to reduce soil erosion. When placing slash on embankment slopes start at the toe of the fill and place as flat as practicable on the completed slope.”

Measurement

201.08. Delete this subsection and replace with the following:

“Do not measure clearing and grubbing for payment.”

203 - Removal of Structures and Obstructions

203.01_nat_05_12_2004

203.03 Salvaging Material.

Delete this subsection and add the following:

Unless shown on the plans, remove all designated material from the project area and National Forest land.

203.05 Disposing of Material.

(a) Remove from project Delete this paragraph and add the following:

All removed material may be salvaged by the Contractor unless otherwise shown on the plans. Dispose of all items not designated to be salvaged for the Government in any legal manner.

204 - Excavation and Embankment

Description

204.11 Compaction.

Delete this subsection and substitute the following:

Adjust the moisture content of the material to moisture content suitable for compaction. Operate compaction equipment over the full width of each layer until visible deformation of the layer ceases or, when a sheepsfoot roller is used, the roller “walks out” of the layer. Make at least three complete passes.

204.13 Sloping, Shaping, and Finishing.

Delete section (d) and add the following:

(d) Finishing. For crushed aggregate surfaced areas, remove all material larger than 6 inches from the top 6 inches of the roadbed. For all trails, finish the trail bed to be smooth and uniform, and shaped to conform to the typical sections. Remove unsuitable material from the trail bed and replace it with suitable material.

Ensure that the subgrade is visibly moist during shaping and dressing. Bring low sections, holes, cracks, or depressions to grade with suitable material. Maintain proper ditch drainage.

204.14_nat_05_12_2004

204.14 Disposal of Unsuitable or Excess Material.

Delete the text of the first paragraph and substitute the following:

Dispose of unsuitable or excess material at designated sites. Place unsuitable or excess material in low spots/ holes at the waste site and shape material to a uniform surface and slope to drain.

Measurement

204.16 (e) Waste. Delete this paragraph 208 - Structure Excavation and Backfill for Selected Major Structures

Description

208.01 Delete this subsection and replace with the following This work consists of excavating material for the construction of the new bridge abutments. This work includes preserving channels, shoring and bracing, constructing cofferdams, sealing foundations, dewatering, excavating, hauling and spreading excess excavated material, preparing foundations, backfilling, constructing the trail and parking area subgrade and subsequent removal of safety features and cofferdams.

208.04 General.

Add the following:

Excavate material and construct embankments for the trail and parking area according to Section 204.

208.11 Compacting. Delete this subsection and replace with the following Adjust the moisture content of the material to moisture content suitable for compaction. Operate compaction equipment over the full width of each layer until visible deformation of the layer ceases or, when a sheepsfoot roller is used, the roller “walks out” of the layer. Make at least three complete passes.

272 - Geocell Abutment Stabilization

272.01_01_08_27_2004

Description

272.01 This work consists of constructing geocell abutment stabilization at each abutment using a cellular confinement system such as Presto Geoweb Cellular Confinement System or Webtec TerraCell in accordance with the plans and manufacturers recommendations.

Materials

272.02 Requirements. Ensure that material conforms to specifications in the following subsections:

Granular Backfill Type (a)

703.03

Geotextile, Type II (A, B, C)

714.01

Geocell

Construction Requirements

272.03 General. Perform the work specified in Section 208 or 209. Use ditches, grading or similar methods to prevent surface runoff that may occur during inclement weather from ponding in the foundation excavation.

272.04 Storage and Handling of Material. During shipment and storage, wrap geotextile materials in heavy-duty protective covering. Protect the material from mud, soil, dust, debris and sunlight prior to installation.

272.05 Geotextile Installation. Place the geotextile according to Section 207. Ensure that the surface upon which the geotextile is to be placed is uniform and is reasonably smooth and free of obstructions, depressions, and debris that could damage the geotextile. Have the surface approved by the CO prior to placing geotextile.

Lay the geotextile without tension, stress, wrinkles or creases. Sew or overlap adjacent strips a minimum of 12” at joints. Insert securing pins through both strips of overlapped geotextile at minimum intervals of 3 feet, but no closer than 2 inches to each edge, to prevent the geotextile from being displaced.

Have the installed geotextile approved by the CO prior to setting the geocells.

272.06 Geocell Installation. Furnish the CO with product literature and certification as required in Section 106.03 for review and approval prior to installation. When requested by the CO, furnish a sample of the geocell from each lot for verification testing.

Place the geocell sections directly on the prepared subgrade. Expand the geocell sections into position at the grades and lines as shown on the plans. Hold the expanded geocell sections with suitable “stretcher frames”, steel stakes driven inside selected outer cell walls, or other similar methods as allowed by the manufacturer prior to filling. Ensure that the individual cells have expanded to the minimum dimensions required by the manufacturer. If necessary field cut sections as per the manufacturer’s recommendations to the lines shown on the plans.

Connect geocell panels in accordance with the manufacturer’s recommendations.

272.07 Infill Placement. Furnish the CO with the manufacturer’s specific recommendations for backfilling 2 weeks prior to placement of the geocells.

Place coarse granular backfill meeting Subsection 703.03 into the expanded cells with equipment appropriate for the site conditions such as a backhoe or a front-end loader. Do not drop infill material more than 3 feet to avoid damage or displacement of the cell walls.

Overfill the geocell cells and level to a minimum of 2 inches above the top of the cell walls. A front-end loader may be used to place the infill provided that it only traffics above geocell sections that have been filled and covered with the minimum 2 inches of additional material. Compact the infill material with a vibratory plate compacter. Operate compaction equipment over the full width of the geocell until visible deformation of the infill ceases. Make at least three complete passes. Grade the surface to be ½ inch above the top of the cells. Ensure that the cell walls are not exposed after fine grading is completed.

Use the geocell manufacturer’s specific recommendations for backfilling if they are more stringent than stated above.

272.08 Acceptance. Geotextile will be evaluated under Subsections 106.02 and 106.03 and 714.01.

Material for geocell will be evaluated under Subsections 106.2 and 106.03.

Granular backfill material will be evaluated under Section 106.02 and 106.04.

Measurement

272.08 Method. Measure the items listed in the bid schedule according to Subsection 109.02 and the following.

Measure geocell by the square yard in place, exclusive of wastage.

Payment

272.09 Basis. The accepted quantities will be paid for at the contract price per unit of measurement for the Section 272 pay items listed in the bid schedule. Payment will be full compensation for the work prescribed in this Section. See Subsection 109.05.

The cost for furnishing and placing the granular backfill required for geocell infill is incidental to this pay item and no separate payment will be made.

The cost for furnishing and placing geotextile for the geocell installation is incidental to this pay item and no separate payment will be made.

308 – Minor Crushed Aggregate

Construction Requirements

308.05 Compacting and Finishing Crushed Aggregate.

(a) Roadway aggregate. Delete this subsection and replace with the following:

Use compression-type or vibratory rollers. Adjust the moisture content of the material to a level suitable for compaction. Operate compaction equipment over the full width of each layer until visible deformation of the layer ceases. Make at least three complete roller passes.

Blade the surface of each layer during the compaction operations to remove irregularities and produce a smooth, even surface.

Ensure that the thickness and width of the compacted aggregate conform to the dimensions SHOWN ON THE DRAWINGS, and that measurements on the compacted aggregate meet the following criteria:

(a) The maximum variation from the compacted specified thickness is ½ inch.

(b) The compacted thickness is not consistently above or below the specified thickness and the average thickness of 4 random measurements for any ½ mile of road segment is within + ¼ inch of the specified thickness.

(c) The maximum variation from the specified width will not exceed +12 inches at any point.

(d) The compacted width is not consistently above the specified width and the average of any four random measurements along any ½ mile of road segment is within +4 inches of the specified width.

553A – Precast Concrete Structures

Description

553A.01 Work. Construct precast concrete members. In addition, manufacture, test materials for, transport, store, and install all precast concrete portions except piling, and perform all necessary grouting, welding, or other connections. Furnish precast concrete members complete and in place, including all concrete reinforcing steel and incidentals connected therewith.

Materials

553A.02 Requirements. Provide materials that meet the requirements specified in the following subsections:

Elastomeric Bearing Pads …………………………………….. 717.10

High-Strength Nonshrink Grout ……………………………… 725.40

Low-Strength Grout …………………………………………... 725.22(f)

Mortar ………………………………………………………… 725.40

Reinforcing Steel ……………………………………………… 709.01

Sealants, Fillers, Seals, & Sleeves …………………………….. 712.01

Structural Concrete ……………………………………………. 552

Structural Steel ………………………………………………… 717.01

Provide precast concrete members of the size, shape, strength, air content, and finish that are SHOWN ON THE DRAWINGS. Precast concrete members must be manufactured by a plant certified by the Prestressed Concrete Institute (PCI). Submit a copy of the transmittal letter of the latest PCI inspection with the shop drawings.

Perform all sampling, testing, and inspection necessary to ensure quality control of the component materials and the concrete. Sample and test for quality control and acceptance testing in accordance with the AASHTO or ASTM test methods prescribed in Section 552.

Maintain adequate records of all inspections and tests. Keep records that indicate the nature and number of observations made, the number and type of deficiencies found, the quantities approved and rejected, and the nature of any corrective action taken.

Sample and test every batch (100 percent sampling and testing) for air content and slump at the start of concrete production. Random sampling and testing for air content and slump at the rate of one for every five successive batches may be substituted for 100 percent sampling and testing if the test results for three successive batches are within the specification limitations for air content or slump; but reinstate 100 percent sampling and testing if a test result for any random sample is outside the specification limitations for either air content or slump.

Make compression tests to determine the minimum strength requirements on cylinders. Make a minimum of four cylinders from each day’s production, and cure them in the same manner as the precast units. Use testing methods in accordance with AASHTO T 22.

Furnish, or have the supplier furnish, a Certificate of Compliance to the CO Certifying that the above materials comply with the applicable specifications. In addition, furnish to the CO a copy of all test results performed by the Contractor or supplier that are necessary to ensure compliance.

Construction

553A.03 Performance. Construct precast concrete structural members in accordance with the following sections and subsections, as applicable:

Erecting and Placement of Multibeam Members ………………...553.08

Reinforcing Steel ………………………………………………... 554

Storing, Transporting, & Erecting ………………………………. 553.08

Structural Concrete ……………………………………………… 552

Submit four sets of shop drawings to the CO for approval, including the concrete mix design for each class of concrete proposed for use, a minimum of 21 days before fabrication of the precast member(s).

553A.04 Casting Yard. The precasting of concrete structural members may only be done at a casting yard of a PCI Certified plant.

553A.05 Handling, Transporting, & Erecting. Provide additional reinforcement, as needed, to meet the requirements of handling, transporting, and erecting precast members.

553A.06 Acceptance. Reinforcing steel, anchor devices, elastomeric bearings, and material for concrete and grout will be evaluated under Subsection 106.03. Furnish production certifications for hydraulic cement, and reinforcing steel.

Concrete for precast concrete members will be evaluated under Subsections 106.02, 106.03, and 106.04.

Construction of precast concrete members will be evaluated under Subsections 106.02 and 106.04.

Reinforcing steel will be evaluated under Section 554.

Falsework and forms will be evaluated under Section 562.

Measurement

553A.07 Measure the Section 553A items listed in the bid schedule according to Subsection 109.02 and the following as applicable.

Do not measure reinforcing steel, concrete, anchorages, plates, nuts, and other material contained within or attached to the unit for precast concrete structural members.

Payment

553A.08 The accepted quantities will be paid at the contract price per unit of measurement for the Section 553A pay items listed in the bid schedule. Payment will be full compensation for the work prescribed in this Section. See Subsection 109.05.

622 - Rental Equipment

622.02_01_08_20_2004 Construction Requirements

622.02 Rental Equipment

Delete the first two sentences of the first paragraph and add the following:

Hydraulic Excavator. Provide a track mounted hydraulic excavator in acceptable operating condition as determined by the CO. Bucket must be equipped with an hydraulic "thumb". It is anticipated that an excavator of a size capable of performing the excavation needs for the project, i.e. structure excavation, riprap construction, etc., will be of an adequate size to be acceptable for any work that the Contractor may be directed to perform under this section.

Large Dump Truck. Provide a large dump truck with a minimum capacity of 12 cubic yards in acceptable operating condition as determined by the CO.

Measurement

622.04 Add the following:

The Government reserves the right to reduce or eliminate entirely the work under this item with no adjustment in contract unit price.

625 - Turf Establishment

625.00_0114_us_07_12_2007

625.03 General.

Delete the first sentence and add the following:

Apply turf establishment to portions of slopes, ditches, waste areas, and other disturbed areas within 14 days after being constructed to template lines unless otherwise specified in writing by the C.O..

625.04 Preparing Seedbed.

Delete the second sentence of the first paragraph.

Delete the third paragraph.

625.05 Watering

Delete the entire paragraph.

625.06 Fertilizing.

Delete the entire subsection and add the following.

Apply fertilizer having a chemical analysis as listed in (c) below by the following methods. Apply seed and fertilizer in one application.

(a) Dry Method. Apply the fertilizer with approved power driven seeders, drills, fertilizer spreaders or other mechanical equipment. Hand operated methods are satisfactory on areas inaccessible to mechanical equipment.

(b) Hydraulic method. Use hydraulic-type equipment capable of providing a uniform application using water as the carrying agent. Add fertilizer to the slurry and mix before adding seed.

(c) Chemical analysis. Apply fertilizer at the rate of 240 pounds per acre. Apply fertilizer having the following chemical analysis.

Nutrient Percent

Nitrogen, N

Phosphorus, P2O5

Potassium, K

Fertilizer having a different chemical analysis may be used if approved in advance by the CO.

625.07 Seeding.

Delete the first sentence and add the following.

Apply seed mix shown in (c) below by the following methods.

(a) Dry method.

Delete the third sentence.

Add the following after subsection (b).

(c) Seed Mix. In terms of pure live seed, furnish and apply the following kinds and amounts of seed. Obtain the pounds of seed to furnish per acre by dividing the pounds of pure live seed required per acre by the product of the percent purity and percent germination.

Example:

5 lbs Pure Live Seed/Acre = 6.55 lbs Commercial Seed/Acre

0.90 X 0.85 (Purity = 90% and Germination = 85%)

Kind of Seed Quantity of Pure Live Seed

(Lbs/Acre)

1. Annual Rye

2. Hard Fescue

3. Orchard Grass

Total

625.08 Mulching.

(b) Hydraulic method.

Delete the first sentence and add the following.

Apply mulch in a separate application from the seed or in a single application with the seed using hydraulic-type equipment according to Subsection 625.07(b).

625.09 Protecting and Caring for Seeded Areas.

Delete the first sentence and add the following.

Protect and care for seeded areas until final acceptance.

625.11 Measurement

Delete the second paragraph and add the following.

Measure seeding, fertilizing, and mulching by the acre on the ground surface or by lump sum.

703 - Aggregate

703.06 Crushed Aggregate.

Delete the second sentence and add the following:

Furnish crushed aggregate with a maximum size of 3/4 inch as determined by AASHTO T 27 and T 11.

PAGE

ii