Exhibit1C_General Decision Number_AZ080008_HEAVY_Apache_Feb132009.doc
DOC document 35 KB Posted
- Attached to
- APACHE-SITGREAVES FOREST ROADS IDIQ Federal contract opportunity
- Solicitation number
- AG-8173-S-09-0007
About this file
WAGES
View the file
Other files for this federal contract opportunity
Show all 20
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
General Decision Number: AZ080008 02/13/2009 AZ8
Superseded General Decision Number: AZ20070010
State: Arizona
Construction Type: Heavy
Counties: Apache and Navajo Counties in Arizona.
HEAVY CONSTRUCTION PROJECTS (excluding dam construction)
Modification Number Publication Date
0 02/08/2008
1 04/04/2008
2 05/23/2008
3 08/08/2008
4 08/22/2008
5 02/13/2009
ASBE0073-002 08/01/2007
Rates Fringes
Asbestos Workers/Insulator
(Includes the application of all insulating materials, protective coverings, coatings, and finishes to all types of mechanical systems).....$ 33.26 9.32
ASBE0073-004 02/16/2001
Rates Fringes
Asbestos Removal worker/hazardous material handler (Includes preparation, wetting, stripping, removal, scrapping, vacuuming, bagging and disposing of all insulation materials from mechanical systems, whether they contain asbestos or not)....$ 20.18 5.87
* BOIL0627-002 10/01/2008
Rates Fringes
BOILERMAKER (Including
Containment Lining)..............$ 31.37 19.16
CARP0408-002 09/01/2007
Rates Fringes
CARPENTER (Including Form
Work)............................$ 22.50 5.97
CARP1914-001 09/01/2007
Rates Fringes
MILLWRIGHT
Zone 1......................$ 23.29 12.34
Zone 2......................$ 24.67 12.34
Zone 3......................$ 27.79 12.34
ZONE DEFINITIONS FOR MILLWRIGHTS: Mileage shall be calculated from the construction site to the City Hall in Phoenix or Tucson, or to the workmen's residence, whichever is less:
Zone 1: 0-30 miles
Zone 2: 31-49 miles
Zone 3: 50 miles and over
ENGI0428-006 06/15/2008
Rates Fringes
Power Equipment Operator
Group 1.....................$ 19.89 8.84
Group 2.....................$ 23.16 8.84
Group 3.....................$ 24.24 8.84
Group 4.....................$ 25.27 8.84
POWER EQUIPMENT OPERATORS CLASSIFICATIONS
GROUP 1: Gin Truck; and Loader, 3.5 cu yd and under
GROUP 2: Backhoe, under 1 cu yd; Bulldozer; Caisson Drill;
Crane, under 15 tons; Blade/Grader; Field Equipment Service man; Loader, over 3.5 cu yd but less than 6 cu yd; Oiler; and Scraper
GROUP 3: Backhoe, up to 10 cu yd; Crane, over 15 tons but less than 100 tons; Loader, 6 cu yd but less than 10 cu yd; and Mechanic
GROUP 4: Backhoe, 10 cu yd and over; Crane, 100 tons and over; Loader, 10 cu yd and over
IRON0075-005 08/01/2008
Rates Fringes
IRONWORKER, STRUCTURAL
Zone 1:.....................$ 25.52 16.39
Zone 1: 0 to 50 miles from City Hall in Phoenix or Tucson
Zone 2: 050 to 100 miles - Add $4.00
Zone 3: 100 to 150 miles - Add $5.00
Zone 4: 150 miles & over - Add $6.50
SUAZ1994-003 02/01/1994
Rates Fringes
LABORER
General.....................$ 10.37 2.77
Pipelayer...................$ 15.15
WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.
Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).
In the listing above, the "SU" designation means that rates listed under the identifier do not reflect collectively bargained wage and fringe benefit rates. Other designations indicate unions whose rates have been determined to be prevailing.
WAGE DETERMINATION APPEALS PROCESS
1.) Has there been an initial decision in the matter? This can be:
* an existing published wage determination
* a survey underlying a wage determination
* a Wage and Hour Division letter setting forth a position on a wage determination matter
* a conformance (additional classification and rate) ruling
On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.) and 3.) should be followed.
With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:
Branch of Construction Wage Determinations
Wage and Hour Division
U.S. Department of Labor
200 Constitution Avenue, N.W.
Washington, DC 20210
2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator
(See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:
Wage and Hour Administrator
The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.
3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:
Administrative Review Board
4.) All decisions by the Administrative Review Board are final.
END OF GENERAL DECISION
File details come from the government source that posted it. Updated .