View the file

Other files

File Type Posted
Amend_4_Questions_and_AnswersAugust_30.docx DOCX document
Amend_3_Questions_and_AnswersAugust_27.docx DOCX document
Amendment001SOOPageChange.pdf PDF
SOO_Attachment_K_-_FSM_6600_Systems_Management_6680_Security_of_Info-InfoSystemsandInfoTechnology.doc DOC document
Amendment001RFPPageChanges.pdf PDF
SOO_Attachment_L_-_USDA_Web_Standards_and_Style_Guide.pdf PDF
Amendment_000002.pdf PDF
Amendment_001.pdf PDF
QuestionsPosted7Aug2013_(2).docx DOCX document
USDA_Web_Standards_and_Style_Guide_v1_1.pdf PDF
USDA_Incident_Mgmt_Policy.doc DOC document
FS_OSOH_WC_PreproposalConference_v01_20130802_PMO.pptx PPTX presentation
SOO_Attachment_G_FS_WC_OSOH_VendorDemoScenarios-27Jul13-POSTED.docx DOCX document
SOO_Attachment_F_Commonly_Used_Forms-27Jul13-POSTED.zip ZIP file
RFP_Attachment_6_Pricing_Tables_31Jul13-POSTED.xls XLS spreadsheet
SOO_Attachment_E_Current_Database_Field_Descriptions-27Jul13-POSTED.docx DOCX document
SOO_Attachment_D_SSO_API_specification-27Jul13-POSTED.docx DOCX document
SOO_Attachment_J_USDA_DemographicsbyMission_Area_Agency_31Jul13-POSTED.docx DOCX document
RFP_Attachment_3_Past_Performance_Questionnaire-27Jul-POSTED.docx DOCX document
SOO_Attachment_I_OSOH_DepartmentRegulation(DR)4410-004_OHRM_DR30Jul13-POSTED.pdf PDF
RFP_Attachment_1_FS_WC_OSOH_SOO-31Jul13-POSTED.docx DOCX document
RFP_Attachment_2_QASP-30Jul13-POSTED.docx DOCX document
RFP_AG-7604-S-13-0033_SaaS_Reporting_Incidents-1August2013-POSTED.docx DOCX document
SOO_Attachment_H_WC_DepartmentRegulation(DR)4430-003_OPPM_DR30Jul13-POSTED.pdf PDF
RFP_Attachment_5_VPAT_Checklist-27Jul13-POSTED.doc DOC document
SOO_Attachment_B_FS_OSOH_WC_Business_Process_Standardization-27Jul13-POSTED.docx DOCX document
SOO_Attachment_C_FS_OSOH_WC_IntegratedProjectRequirements-31Jul13-POSTED.xlsx XLSX spreadsheet
RFP_Attachment_4_Client__Authorization_Letter_for_Past_Performance_Questionnaires-27Jul13-POSTED.doc DOC document
SOO_Attachment_A_Acronymns_used_in_Document-27Jul13-POSTED.docx DOCX document
Show all 29

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers, 15 August 2013

1. Question: Page 17 - concerning the Organization Table: Management Ballet - Do you want our structure, our plan or our resumes?

Answer: Please include the structure of your organization that would be in place to implement this contract if selected. You may include a structure for implementation that would be different from ongoing services.

2. Question: Since the solution requires hosting in GDC’s data center in St. Louis with a fail-over in Omaha Nebraska, will Forest Service (FS) provide detailed architectural drawings of the network infrastructure and the hosting platform (Network focus: Token rings, Ethernet, T1, etc.)?

Answer: FS will provide additional detail to the selected vendor after award.

3. Question: Does GDC’s hosting platform include the Oracle database plus necessary tools to replicate the solution between St Louis and Omaha (Database focus)?

Answer: Vendors should assume that the hosting environment can perform the necessary actions to replicate to the Disaster Recovery site. Vendors should propose a solution that includes all necessary application and database elements in order to run their solution.

4. Question: Please describe the technical architecture of GDC’s hosting platform (Equipment/Software focus: servers, operating systems, software, database, firewall, monitoring tools, VPN, etc.?)

Answer: The selected vendor will have the opportunity to coordinate with the hosting vendor during the transition phase. Vendors should include in their transition approach any particular hosting requirements they may have.

5. Question: Will FS/GDC provide a list of the inherited and hybrid security controls associated with GDC’s Certification and Accreditation?

Answer: In general, the selected vendor will need to assure application security and testing for Certification and Accreditation (C&A) compliance.

6. Question: We were recently informed that Oracle no longer provides concurrent user licenses. They now offer Enterprise or Core Processor Licenses. Therefore, to effectively cost this out, we will need the number of core processors contained within GDC’s targeted hosting platform for this solution.

Answer: Vendors should assume licensing necessary to implement their solution based on the data provided. Details of core processors required for the solution should be included in the vendor’s approach.

7. What is the proposed GoLive plan for the new solution?

Answer: It is up to the vendor to propose what they believe to be the most effective GoLive plan as part of their strategy. That being said, however, the Government anticipates having resources available to thoroughly test the solution in User Acceptance Testing (UAT) prior to GoLive and to use existing media (email, HR bulletins, web pages) to announce GoLive information to the field.