AG-64R4-S-12-0023AY.Hurricane.Creek.Bidders.Copy.docx
DOCX document 165 KB Posted
- Solicitation number
- AG-64R4-S-12-0023AY
About this file
Bidder's Copy of Solicitation
View the file
Other files
| File | Type | Posted |
|---|---|---|
| AG-64R4-S-12-0023AY.Amendment.No.2.rtf | RTF text file | |
| AG-64R4-S-12-0023AY.Hurricane.Creek.Specifications.Amended.docx | DOCX document | |
| AG-64R4-S-12-0023AY.Amendment.No.1.rtf | RTF text file | |
| Hurricane.Creek.Bore.Hole.Drilling.Logs.pdf | ||
| Hurricane.Creek.Lab.Tests.pdf | ||
| Hurricane Creek DNR Permit.pdf | ||
| Hurricane.Creek.Results.pdf | ||
| AG-64R4-S-12-0023AY.Hurricane.Creek.Plans.pdf | ||
| AG-64R4-S-12-0023AY.Hurricane.Creek.USACOE.PermitNWP14.pdf | ||
| AG-64R4-S-12-0023AY.Hurricane.Creek.Specifications.docx | DOCX document | |
| AG-64R4-S-12-0023AY.Hurricane.Creek.Bid.Copy.docx | DOCX document |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOLICITATION NO. AG-64R4-S-12-0023AY – BIDDER’S COPY
HURRICANE CREEK LOW WATER CROSSING – ELEVEN POINT RANGER DISTRICT
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
AG-64R4-S-12-0023AY
2. TYPE OF SOLICITATION
|X| SEALED BID (IFB)
|_| NEGOTIATED (RFP)
3. DATE ISSUED
07/10/2012
PAGE OF PAGES
IMPORTANT - The “offer” section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
5. REQUISITION/PURCHASE REQUEST NO.
592016
6. PROJECT NO.
12-8063
| 7. ISSUED BY | CODE |
| 64R4 | |
| 8. ADDRESS OFFER TO |
Contracting Officer USDA Forest Service Mark Twain National Forest 401 Fairgrounds Road Rolla, MO 65401 USDA Forest Service Mark Twain National Forest Attn: Anita J. Young, Contracting Officer 401 Fairgrounds Road Rolla, MO 65401
| 9. FOR INFORMATION |
| CALL: |
| A. NAME (NO COLLECT CALLS) |
Anita Young, Contract Specialist, 573-341-7470 Adam Garrison, Engineer, 573-341-7438
SOLICITATION
NOTE: In sealed bid solicitations “offer” and “offeror” mean “bid” and “bidder.”
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date):
HURRICANE CREEK LOW WATER CROSSING
MARK TWAIN NATIONAL FOREST
ELEVEN POINT RANGER DISTRICT
OREGON COUNTY, MISSOURI
Price Range: The Government's estimate is between $100,000 and $250,000.
Note: If Bid is less than $150,000, no bid guarantee will be required and no performance bond will be required. However, if Bid is greater than $150,000 a bid guarantee in the amount of 20% of bid price will be required at the time of bid opening and a Performance Bond in the amount of 100% of the contract amount will be required after award by the awarded contractor.
(Note: Facsimile Bid Guarantees and Bonds are not acceptable.)
Performance and Payment Bonds shall also be required from contract awardee.
11. The Contractor shall begin performance within 10 calendar days and complete it within 120 calendar days after receiving |_| award, |X| notice to proceed. This performance period is |X| mandatory, |_| negotiable. (See Section F.)
12A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If “YES,” indicate within how many calendar days after award in Item 12B.)
| |X| YES | |_| NO **SEE NOTE ABOVE REGARDING BONDS | |
| 12B. CALENDAR DAYS |
| 13. ADDITIONAL SOLICITATION REQUIREMENTS: | |||
| A. | Sealed offers in original and 0 copies to perform the work required are due at the place specified in Item 8 by 2:00 p.m. (hour) local time August 10, 2012 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror’s name and address, the solicitation number, and the date and time offers are due. | ||
| B. | An offer guarantee | |X| is required if bid is over $150,000 | |X| is not required if bid is less than $150,000. |
| C. | All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference. | ||
| D. | Offers providing less than 60 calendar days for Government acceptance after the date offers are due will not be considered and will be rejected. |
OFFER (Must be fully completed by offeror)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)
15. TELEPHONE NO. (Include area code) & EMAIL
16. REMITTANCE ADDRESS (Include only if different than Item 14)
CODE FACILITY CODE
17. The offeror agrees to perform the work at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government within calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each
| AMENDMENT NO. |
| DATE |
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)
20B. SIGNATURE
20C. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT
23. ACCOUNTING AND APPROPRIATION DATA
| 24. SUBMIT INVOICES TO ADDRESS SHOWN IN: | (1 copy unless otherwise specified) |
| ITEM 8 |
Attn: Adam Garrison
| 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO | |
| |_| 10 U.S.C. 2304(c)( ) | |_| 41 U.S.C. 253(c)( ) |
| 26. ADMINISTERED BY |
| CODE |
| 64R4 |
| 27. PAYMENT WILL BE MADE BY |
USDA FOREST SERVICE
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
| |_| | 28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return ____ copies to issuing office.) Contractor agrees to furnish and deliver all items or perform all work, requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications or incorporated by reference in or attached to this contract. |
| |_| | 29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary. |
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31A. NAME OF CONTRACTING OFFICER (Type or print)
30B. SIGNATURE
30C. DATE
31B. UNITED STATES OF AMERICA
BY:
31C. AWARD DATE
PART I – THE SCHEDULE
SECTION B - SUPPLIES OR SERVICES AND PRICES/COSTS
The contractor shall furnish all transportation, material, labor, equipment, operators, tools, supplies, licenses, permits and other incidentals necessary to remove an existing low water crossing and replace it with a precast multiple box culvert low water crossing with wing-walls and riprap protection. This project is located on the Eleven Point Ranger District of the Mark Twain National Forest in Oregon County, Missouri. All work shall be performed in accordance with terms, conditions, specifications and drawings of this Invitation for Bids (IFB) and any resultant contract.
PAY
ITEM
DESCRIPTION
PAY
UNIT
QUANTITY
TOTAL
Mobilization* Lump Sum
| Demolition of existing low water crossing structure |
| Lump |
Sum
Construction of west approach. Includes earthwork, slab, riprap armoring, curbs, wing-walls, signage, testing, dewatering and incidentals
Lump Sum
Construction of east approach. Includes, earthwork, slab, rock blanket armoring, curbs, wing-walls, signage, testing, dewatering and incidentals
Construction of precast box culvert low water crossing. Includes earthwork, precast culverts, curbs, rock blanket aprons, testing, dewatering and incidentals
TOTAL FOR ALL ITEMS:
NOTE: All work necessary for the construction of the low water crossing as shown on the plans and specifications not specified in the schedule of items shall be considered incidental to the contract.
*Payment for bond premiums in accordance with Clause 52.232-5, Payments under Fixed-Price Construction Contracts, shall not be in addition to the contract price. Include bond payments under 101 Mobilization.
Payment will be made on actual work performed as described in FP-03 109.01 unless otherwise noted.
PRE-BID MEETING: A pre-bid meeting will be held at the project site on July 20, 2012. Interested bidders should plan to meet at the project site at 1:00 p.m.
DIRECTIONS TO PROJECT SITE: From Alton, MO travel North on State Highway 19 approximately 11 miles. Turn right on Forest Road 3152 and drive 4.5 miles to the project site.
IMPORTANT NOTICE TO BIDDERS
CENTRAL CONTRACTOR REGISTRATION: In order to be eligible for an award, potential contractors must comply with all requirements of FAR Clause 52.204-7, Central Contractor Registration. All bidders must submit the following information:
PHONE NO.___________________________ CELL PHONE NO._______________________________
E-MAIL ADDRESS:____________________________________________________________________
DATA UNIVERSAL NUMBERING SYSTEM (DUNS) NUMBER: _____________________________
FEDERAL TAX IDENTIFICATION NUMBER: _____________________________________________
ARE YOU REGISTERED IN THE CENTRAL CONTRACTOR REGISTRY? [ ] YES [ ] NO
ARE YOU REGISTERED IN THE ONLINE REPRESENTATIONS AND CERTIFICATIONS (ORCA) DATABASE? [ ] YES [ ] NO
SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
Scope of Contract: The contractor shall furnish all transportation, material, labor, equipment, operators, tools, supplies, licenses, permits and other incidentals necessary to remove an existing low water crossing and replace it with a precast multiple box culvert low water crossing with wing-walls and riprap protection. All work shall be performed in accordance with terms, conditions, specifications and drawings of this Invitation for Bids (IFB) and any resultant contract.
Project Location: This project is located on the Eleven Point Ranger District of the Mark Twain National Forest in Oregon County, Missouri.
Directions to Project Site: From Alton, MO travel North on State Highway 19 approximately 11 miles. Turn right on Forest Road 3152 and drive 4.5 miles to the project site.
Price Range: The Government's estimate is between $100,000 and $250,000.
AGAR 452.211-72 Statement of Work/Specifications (FEB 1988)
The Contractor shall furnish the necessary personnel, material, equipment, services and facilities (except as otherwise specified), to perform the Statement of Work/Specifications referenced in Section J.
AGAR 452.211-73 Attachments to Statement of Work/Specifications (FEB 1988)
The attachments to the Statement of Work/Specifications listed in Section J are hereby made part of this solicitation and any resultant contract.
SECTION D - PACKAGING AND MARKING
{For this Solicitation, there are NO clauses in this Section}
SECTION E - INSPECTION AND ACCEPTANCE
FAR 52.252-2 Clauses Incorporated by Reference. (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):
www.acquisition.gov/far/index.html www.arnet.gov/far/
FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES
52.246-1 Contractor Inspection Requirements. (APR 1984)
FAR 52.246-12 Inspection of Construction. (APR 1996)
(a) Definition. "Work" includes, but is not limited to, materials, workmanship, and manufacture and fabrication of components.
(b) The Contractor shall maintain an adequate inspection system and perform such inspections as will ensure that the work performed under the contract conforms to contract requirements. The Contractor shall maintain complete inspection records and make them available to the Government. All work shall be conducted under the general direction of the Contracting Officer and is subject to Government inspection and test at all places and at all reasonable times before acceptance to ensure strict compliance with the terms of the contract.
(c) Government inspections and tests are for the sole benefit of the Government and do not -
(1) Relieve the Contractor of responsibility for providing adequate quality control measures;
(2) Relieve the Contractor of responsibility for damage to or loss of the material before acceptance;
(3) Constitute or imply acceptance; or
(4) Affect the continuing rights of the Government after acceptance of the completed work under paragraph (i) of this section.
(d) The presence or absence of a Government inspector does not relieve the Contractor from any contract requirement, nor is the inspector authorized to change any term or condition of the specification without the Contracting Officer's written authorization.
(e) The Contractor shall promptly furnish, at no increase in contract price, all facilities, labor, and material reasonably needed for performing such safe and convenient inspections and tests as may be required by the Contracting Officer. The Government may charge to the Contractor any additional cost of inspection or test when work is not ready at the time specified by the Contractor for inspection or test, or when prior rejection makes reinspection or retest necessary. The Government shall perform all inspections and tests in a manner that will not unnecessarily delay the work. Special, full size, and performance tests shall be performed as described in the contract.
(f) The Contractor shall, without charge, replace or correct work found by the Government not to conform to contract requirements, unless in the public interest the Government consents to accept the work with an appropriate adjustment in contract price. The Contractor shall promptly segregate and remove rejected material from the premises.
(g) If the Contractor does not promptly replace or correct rejected work, the Government may -
(1) By contract or otherwise, replace or correct the work and charge the cost to the Contractor; or
(2) Terminate for default the Contractor's right to proceed.
(h) If, before acceptance of the entire work, the Government decides to examine already completed work by removing it or tearing it out, the Contractor, on request, shall promptly furnish all necessary facilities, labor, and material. If the work is found to be defective or nonconforming in any material respect due to the fault of the Contractor or its subcontractors, the Contractor shall defray the expenses of the examination and of satisfactory reconstruction. However, if the work is found to meet contract requirements, the Contracting Officer shall make an equitable adjustment for the additional services involved in the examination and reconstruction, including, if completion of the work was thereby delayed, an extension of time.
(i) Unless otherwise specified in the contract, the Government shall accept, as promptly as practicable after completion and inspection, all work required by the contract or that portion of the work the Contracting Officer determines can be accepted separately. Acceptance shall be final and conclusive except for latent defects, fraud, gross mistakes amounting to fraud, or the Government's rights under any warranty or guarantee.
SECTION F - DELIVERIES OR PERFORMANCE
FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): www.arnet.gov/far/
FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES
52.242-14 Suspension of Work (APR 1984)
FAR 52.211-10 Commencement, Prosecution, and Completion of Work (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 120 calendar days. The time stated for completion shall include final cleanup of the premises.
SECTION G - CONTRACT ADMINISTRATION DATA
AGAR 452.215-73 Post Award Conference (NOV 1996)
A post award conference with the successful contractor is required. It will be scheduled and held within 10 days after the date of contract award. Location of the conference will be determined after award, however it is anticipated that the post award conference will be held at the project site.
DESIGNATION OF CONTRACTING OFFICER’S REPRESENTATIVE
The Contracting Officer will designate a Contracting Officer’s Representative (COR) at the time of award.
The COR is responsible for administering the performance of work under this contract. In no event, however, will any understanding, agreement, modification, change order, or other matter deviating from the terms of this contract be effective or binding upon the Government unless formalized by proper contractual documents executed by the Contracting Officer prior to completion of the contract.
On all matters that pertain to the contract terms the contractor must communicate with the Contracting Officer. Whenever, in the opinion of the Contractor, the COR requests effort outside the scope of the scope of the contract, the Contractor should so advise the COR. If the COR persists and there still exists a disagreement as to proper contractual coverage, the contracting officer should be notified immediately, preferably in writing if time permits. Proceeding with work without proper contractual coverage could result in nonpayment or necessitate submittal for a contract claim.
SECTION H - SPECIAL CONTRACT REQUIREMENTS
FAR 52.236-4 Physical Data (APR 1984)
Data and information furnished or referred to below is for the Contractor’s information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.
(a) The indications of physical conditions on the drawings and in the specifications are the resut of site investigations by (insert a description of investigational methods used, such as surveys, auger borings, core borings, test pits, probings, test tunnels).
(b) Weather conditions
(c) Transportation facilities
(d) Other pertinent information – In stream work can only be performed during the periods of June 15 to September 30 or December 1 to March 15.
AGAR 452.236-72 Use of Premises (NOV 1996)
(a) Before any camp, quarry, borrow pit, storage, detour, or bypass site, other than shown on the drawings, is opened or operated on USDA land or lands administered by the USDA, the Contractor shall obtain written permission from the Contracting Officer. A camp is interpreted to include a campsite or trailer parking area of any employee working on the project for the Contractor.
(b) Unless excepted elsewhere in the contract, the Contractor shall (i) provide and maintain sanitation facilities for the work force at the site and (ii) dispose of solid waste in accordance with applicable Federal, State and local regulations.
AGAR 452.236-77 Emergency Response (NOV 1996)
(a) Contractor’s Responsibility for Fire Fighting.
(1) The Contractor, under the provisions of FAR clause 52.236-9, PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND IMPROVEMENTS, shall immediately extinguish all fires on the work site other than those fires in use as a part of the work.
(2) The contractor may be held liable for all damages and for all costs incurred by the Government for labor, subsistence, equipment, supplies and transportation deemed necessary to control or suppress a fire set or caused by the Contractor or the Contractor’s agents or employees.
(b) Contractor’s Responsibility for Notification in Case of Fire. The Contractor shall immediately notify the Government of any fires sighted or in the vicinity of the work site.
(c) Contractor’s Responsibility for Responding to Emergencies. When directed by the Contracting Officer, the Contractor shall allow the Government to temporarily use employees and equipment from the work site for emergency work (anticipated to be restricted to firefighting). An equitable adjustment for the temporary use of employees and equipment will be made under the CHANGES clause, FAR 52.243-4.
PART II - CONTRACT CLAUSES
SECTION I - CONTRACT CLAUSES
52.252-2 Clauses Incorporated by Reference. (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):
www.acquisition.gov/far/index.html www.arnet.gov/far/
FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES
52.202-1 Definitions. (JAN 2012) 52.203-3 Gratuities. (APR 1984) 52.203-5 Covenant Against Contingent Fees. (APR 1984) 52.203-6 Restrictions on Subcontractor Sales to the Government. (SEP 2006) 52.203-7 Anti-Kickback Procedures. (OCT 2010) 52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity. (JAN 1997) 52.203-10 Price or Fee Adjustment for Illegal or Improper Activity. (JAN 1997) 52.203-12 Limitation on Payments to Influence Certain Federal Transactions. (OCT 2010) 52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber Content Paper. (May 2011) 52.209-6 Protecting the Government's Interest When Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment. (DEC 2010) 52.211-18 Variation in Estimated Quantity. (APR 1984) 52.219-6 Notice of Total Small Business Set-Aside. (NOV 2011) 52.219-8 Utilization of Small Business Concerns. (JAN 2011) 52.219-14 Limitations on Subcontracting. (NOV 2011) 52.222-3 Convict Labor. (JUN 2003) 52.222-4 Contract Work Hours and Safety Standards Act - Overtime Compensation. (JUL 2005) 52.222-6 Davis-Bacon Act. (JUL 2005) 52.222-7 Withholding of Funds. (FEB 1988) 52.222-8 Payrolls and Basic Records. (JUN 2010) 52.222-9 Apprentices and Trainees. (JUL 2005) 52.222-10 Compliance with Copeland Act Requirements. (FEB 1988) 52.222-11 Subcontracts (Labor Standards). (JUL 2005) 52.222-12 Contract Termination - Debarment. (FEB 1988) 52.222-13 Compliance with Davis-Bacon and Related Act Regulations. (FEB 1988) 52.222-14 Disputes Concerning Labor Standards. (FEB 1988) 52.222-15 Certification of Eligibility. (FEB 1988) 52.222-21 Prohibition of Segregated Facilities. (FEB 1999) 52.222-26 Equal Opportunity. (MAR 2007) 52.222-27 Affirmative Action Compliance Requirements for Construction. (FEB 1999) 52.222-35 Equal Opportunity for Veterans. (SEP 2010) 52.222-36 Affirmative Action for Workers with Disabilities. (OCT 2010) 52.222-37 Employment Reports on Veterans. (SEP 2010) 52.222-50 Combating Trafficking in Persons. (FEB 2009) 52.223-5 Pollution Prevention and Right-to-Know Information. (MAY 2011) 52.223-6 Drug-Free Workplace. (MAY 2001) 52.225-13 Restrictions on Certain Foreign Purchases. (JUN 2008) 52.227-1 Authorization and Consent. (DEC 2007) 52.227-2 Notice and Assistance Regarding Patent and Copyright Infringement. (DEC 2007) 52.228-2 Additional Bond Security. (OCT 1997) 52.228-11 Pledges of Assets. (JAN 2012) 52.228-12 Prospective Subcontractor Requests for Bonds. (OCT 1995) 52.228-14 Irrevocable Letter of Credit. (DEC 1999) 52.228-15 Performance and Payment Bonds - Construction. (OCT 2010) 52.229-3 Federal, State, and Local Taxes. (APR 2003) 52.232-5 Payments under Fixed-Price Construction Contracts. (SEP 2002) 52.232-17 Interest. (OCT 2010) 52.232-23 Assignment of Claims. (JAN 1986) 52.232-27 Prompt Payment For Construction Contracts. (OCT 2008) 52.232-33 Payment by Electronic Funds Transfer - Central Contractor Registration. (OCT 2003) 52.233-1 Disputes. (JUL 2002) 52.233-3 Protest after Award. (AUG 1996) 52.233-4 Applicable Law for Breach of Contract Claim. (OCT 2004) 52.236-2 Differing Site Conditions. (APR 1984) 52.236-3 Site Investigation and Conditions Affecting the Work. (APR 1984) 52.236-5 Material and Workmanship. (APR 1984) 52.236-6 Superintendence by the Contractor. (APR 1984) 52.236-7 Permits and Responsibilities. (NOV 1991) 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements. (APR 1984) 52.236-10 Operations and Storage Areas. (APR 1984) 52.236-11 Use and Possession Prior to Completion. (APR 1984) 52.236-12 Cleaning Up. (APR 1984) 52.236-13 Accident Prevention. (NOV 1991) 52.236-14 Availability and Use of Utility Services. (APR 1984) 52.236-15 Schedules for Construction Contracts. (APR 1984) 52.236-17 Layout of Work. (APR 1984) 52.236-21 Specifications and Drawings for Construction. (FEB 1997) 52.236-26 Preconstruction Conference. (FEB 1995) 52.242-13 Bankruptcy. (JUL 1995) 52.243-4 Changes. (JUN 2007) 52.244-6 Subcontracts for Commercial Items. (DEC 2010) 52.245-1 Government Property. (APR 2012) 52.246-21 Warranty of Construction. (MAR 1994) 52.249-2 Termination for Convenience of the Government (Fixed-Price). (APR 2012) 52.249-10 Default (Fixed-Price Construction). (APR 1984) 452.232-70 Reimbursement for Bond Premiums - Fixed-Price Construction Contracts. (NOV 1996) 452.236-71 Prohibition Against the Use of Lead-Based Paint. (NOV 1996) 452.236-72 Use of Premises. (NOV 1996) 452.236-73 Archaeological or Historic Sites. (FEB 1988) 452.236-74 Control of Erosion, Sedimentation, and Pollution. (NOV 1996) 452.236-76 Samples and Certificates. (FEB 1988)
FAR 52.204-7 Central Contractor Registration. (FEB 2012)
(a) Definitions. As used in this clause--
"Central Contractor Registration (CCR) database" means the primary Government repository for Contractor information required for the conduct of business with the Government.
"Data Universal Numbering System (DUNS) number" means the 9-digit number assigned by Dun and Bradstreet, Inc. (D&B) to identify unique business entities.
"Data Universal Numbering System +4 (DUNS+4) number" means the DUNS number assigned by D&B plus a 4-character suffix that may be assigned by a business concern. (D&B has no affiliation with this 4-character suffix.) This 4-character suffix may be assigned at the discretion of the business concern to establish additional CCR records for identifying alternative Electronic Funds Transfer (EFT) accounts (see the FAR at Subpart 32.11) for the same concern.
"Registered in the CCR database" means that--
(1) The Contractor has entered all mandatory information, including the DUNS number or the DUNS+4 number, into the CCR database; and
(2) The Government has validated all mandatory data fields, to include validation of the Taxpayer Identification Number (TIN) with the Internal Revenue Service (IRS), and has marked the record "Active". The Contractor will be required to provide consent for TIN validation to the Government as a part of the CCR registration process.
(b)(1) By submission of an offer, the offeror acknowledges the requirement that a prospective awardee shall be registered in the CCR database prior to award, during performance, and through final payment of any contract, basic agreement, basic ordering agreement, or blanket purchasing agreement resulting from this solicitation.
(2) The offeror shall enter, in the block with its name and address on the cover page of its offer, the annotation "DUNS" or "DUNS +4" followed by the DUNS or DUNS +4 number that identifies the offeror's name and address exactly as stated in the offer. The DUNS number will be used by the Contracting Officer to verify that the offeror is registered in the CCR database.
(c) If the offeror does not have a DUNS number, it should contact Dun and Bradstreet directly to obtain one.
(1) An offeror may obtain a DUNS number--
(i) Via the Internet at http://fedgov.dnb.com/webform or if the offeror does not have internet access, it may call Dun and Bradstreet at 1-866-705-5711 if located within the United States; or
(ii) If located outside the United States, by contacting the local Dun and Bradstreet office. The offeror should indicate that it is an offeror for a U.S. Government contract when contacting the local Dun and Bradstreet office.
(2) The offeror should be prepared to provide the following information:
(i) Company legal business.
(ii) Tradestyle, doing business, or other name by which your entity is commonly recognized.
(iii) Company Physical Street Address, City, State, and Zip Code.
(iv) Company Mailing Address, City, State and Zip Code (if separate from physical).
(v) Company Telephone Number.
(vi) Date the company was started.
(vii) Number of employees at your location.
(viii) Chief executive officer/key manager.
(ix) Line of business (industry).
(x) Company Headquarters name and address (reporting relationship within your entity).
(d) If the Offeror does not become registered in the CCR database in the time prescribed by the Contracting Officer, the Contracting Officer will proceed to award to the next otherwise successful registered Offeror.
(e) Processing time, which normally takes 48 hours, should be taken into consideration when registering. Offerors who are not registered should consider applying for registration immediately upon receipt of this solicitation.
(f) The Contractor is responsible for the accuracy and completeness of the data within the CCR database, and for any liability resulting from the Government's reliance on inaccurate or incomplete data. To remain registered in the CCR database after the initial registration, the Contractor is required to review and update on an annual basis from the date of initial registration or subsequent updates its information in the CCR database to ensure it is current, accurate and complete. Updating information in the CCR does not alter the terms and conditions of this contract and is not a substitute for a properly executed contractual document.
(g)(1)(i) If a Contractor has legally changed its business name, "doing business as" name, or division name (whichever is shown on the contract), or has transferred the assets used in performing the contract, but has not completed the necessary requirements regarding novation and change-of-name agreements in Subpart 42.12, the Contractor shall provide the responsible Contracting Officer a minimum of one business day's written notification of its intention to (A) change the name in the CCR database; (B) comply with the requirements of Subpart 42.12 of the FAR; and (C) agree in writing to the timeline and procedures specified by the responsible Contracting Officer. The Contractor must provide with the notification sufficient documentation to support the legally changed name.
(ii) If the Contractor fails to comply with the requirements of paragraph (g)(1)(i) of this clause, or fails to perform the agreement at paragraph (g)(1)(i)(C) of this clause, and, in the absence of a properly executed novation or change-of-name agreement, the CCR information that shows the Contractor to be other than the Contractor indicated in the contract will be considered to be incorrect information within the meaning of the "Suspension of Payment" paragraph of the electronic funds transfer (EFT) clause of this contract.
(2) The Contractor shall not change the name or address for EFT payments or manual payments, as appropriate, in the CCR record to reflect an assignee for the purpose of assignment of claims (see FAR Subpart 32.8, Assignment of Claims). Assignees shall be separately registered in the CCR database. Information provided to the Contractor's CCR record that indicates payments, including those made by EFT, to an ultimate recipient other than that Contractor will be considered to be incorrect information within the meaning of the "Suspension of payment" paragraph of the EFT clause of this contract.
(h) Offerors and Contractors may obtain information on registration and annual confirmation requirements via CCR accessed through https://www.acquisition.gov or by calling 1-888-227-2423, or 269-961-5757.
FAR 52.214-29 Order of Precedence - Sealed Bidding. (JAN 1986)
Any inconsistency in this solicitation or contract shall be resolved by giving precedence in the following order:
(a) The Schedule (excluding the specifications);
(b) Representations and other instructions;
(c) Contract clauses;
(d) Other documents, exhibits, and attachments; and
(e) The specifications.
FAR 52.222-5 Davis-Bacon Act--Secondary Site of the Work. (JUL 2005)
(a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Davis-Bacon Act, of this solicitation.
(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.
(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.
(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.
FAR 52.222-54 Employment Eligibility Verification. (JAN 2009)
(a) Definitions. As used in this clause--
"Commercially available off-the-shelf (COTS) item" --
(1) Means any item of supply that is --
(i) A commercial item (as defined in paragraph (1) of the definition at 2.101);
(ii) Sold in substantial quantities in the commercial marketplace; and
(iii) Offered to the Government, without modification, in the same form in which it is sold in the commercial marketplace; and
(2) Does not include bulk cargo, as defined in section 3 of the Shipping Act of 1984 (46 U.S.C. App. 1702), such as agricultural products and petroleum products. Per 46 CFR 525.1(c)(2), "bulk cargo" means cargo that is loaded and carried in bulk onboard ship without mark or count, in a loose unpackaged form, having homogenous characteristics. Bulk cargo loaded into intermodal equipment, except LASH or Seabee barges, is subject to mark and count and, therefore, ceases to be bulk cargo.
"Employee assigned to the contract" means an employee who was hired after November 6, 1986, who is directly performing work, in the United States, under a contract that is required to include the clause prescribed at 22.1803. An employee is not considered to be directly performing work under a contract if the employee--
(1) Normally performs support work, such as indirect or overhead functions; and
(2) Does not perform any substantial duties applicable to the contract.
"Subcontract" means any contract, as defined in 2.101, entered into by a subcontractor to furnish supplies or services for performance of a prime contract or a subcontract. It includes but is not limited to purchase orders, and changes and modifications to purchase orders.
"Subcontractor" means any supplier, distributor, vendor, or firm that furnishes supplies or services to or for a prime Contractor or another subcontractor.
"United States," as defined in 8 U.S.C. 1101(a)(38), means the 50 States, the District of Columbia, Puerto Rico, Guam, and the U.S. Virgin Islands.
(b) Enrollment and verification requirements. (1) If the Contractor is not enrolled as a Federal Contractor in E-Verify at time of contract award, the Contractor shall--
(i) Enroll. Enroll as a Federal Contractor in the E-Verify program within 30 calendar days of contract award;
(ii) Verify all new employees. Within 90 calendar days of enrollment in the E-Verify program, begin to use E-Verify to initiate verification of employment eligibility of all new hires of the Contractor, who are working in the United States, whether or not assigned to the contract, within 3 business days after the date of hire (but see paragraph (b)(3) of this section); and
(iii) Verify employees assigned to the contract. For each employee assigned to the contract, initiate verification within 90 calendar days after date of enrollment or within 30 calendar days of the employee's assignment to the contract, whichever date is later (but see paragraph (b)(4) of this section).
(2) If the Contractor is enrolled as a Federal Contractor in E-Verify at time of contract award, the Contractor shall use E-Verify to initiate verification of employment eligibility of--
(i) All new employees.
(A) Enrolled 90 calendar days or more. The Contractor shall initiate verification of all new hires of the Contractor, who are working in the United States, whether or not assigned to the contract, within 3 business days after the date of hire (but see paragraph (b)(3) of this section); or
(B) Enrolled less than 90 calendar days. Within 90 calendar days after enrollment as a Federal Contractor in E-Verify, the Contractor shall initiate verification of all new hires of the Contractor, who are working in the United States, whether or not assigned to the contract, within 3 business days after the date of hire (but see paragraph (b)(3) of this section); or
(ii) Employees assigned to the contract. For each employee assigned to the contract, the Contractor shall initiate verification within 90 calendar days after date of contract award or within 30 days after assignment to the contract, whichever date is later (but see paragraph (b)(4) of this section).
(3) If the Contractor is an institution of higher education (as defined at 20 U.S.C. 1001(a)); a State or local government or the government of a Federally recognized Indian tribe; or a surety performing under a takeover agreement entered into with a Federal agency pursuant to a performance bond, the Contractor may choose to verify only employees assigned to the contract, whether existing employees or new hires. The Contractor shall follow the applicable verification requirements at (b)(1) or (b)(2), respectively, except that any requirement for verification of new employees applies only to new employees assigned to the contract.
(4) Option to verify employment eligibility of all employees. The Contractor may elect to verify all existing employees hired after November 6, 1986, rather than just those employees assigned to the contract. The Contractor shall initiate verification for each existing employee working in the United States who was hired after November 6, 1986, within 180 calendar days of--
(i) Enrollment in the E-Verify program; or
(ii) Notification to E-Verify Operations of the Contractor's decision to exercise this option, using the contact information provided in the E-Verify program Memorandum of Understanding (MOU).
(5) The Contractor shall comply, for the period of performance of this contract, with the requirements of the E-Verify program MOU.
(i) The Department of Homeland Security (DHS) or the Social Security Administration (SSA) may terminate the Contractor's MOU and deny access to the E-Verify system in accordance with the terms of the MOU. In such case, the Contractor will be referred to a suspension or debarment official.
(ii) During the period between termination of the MOU and a decision by the suspension or debarment official whether to suspend or debar, the Contractor is excused from its obligations under paragraph (b) of this clause. If the suspension or debarment official determines not to suspend or debar the Contractor, then the Contractor must reenroll in E-Verify.
(c) Web site. Information on registration for and use of the E-Verify program can be obtained via the Internet at the Department of Homeland Security Web site: http://www.dhs.gov/E-Verify.
(d) Individuals previously verified. The Contractor is not required by this clause to perform additional employment verification using E-Verify for any employee--
(1) Whose employment eligibility was previously verified by the Contractor through the E-Verify program;
(2) Who has been granted and holds an active U.S. Government security clearance for access to confidential, secret, or top secret information in accordance with the National Industrial Security Program Operating Manual; or
(3) Who has undergone a completed background investigation and been issued credentials pursuant to Homeland Security Presidential Directive (HSPD)-12, Policy for a Common Identification Standard for Federal Employees and Contractors.
(e) Subcontracts. The Contractor shall include the requirements of this clause, including this paragraph (e) (appropriately modified for identification of the parties), in each subcontract that--
(1) Is for--
(i) Commercial or noncommercial services (except for commercial services that are part of the purchase of a COTS item (or an item that would be a COTS item, but for minor modifications), performed by the COTS provider, and are normally provided for that COTS item); or
(ii) Construction;
(2) Has a value of more than $3,000; and
(3) Includes work performed in the United States.
FAR 52.225-9 Buy American Act - Construction Materials. (SEP 2010)
(a) Definitions. As used in this clause -
"Commercially available off-the-shelf (COTS) item"--
(1) Means any item of supply (including construction material) that is--
(i) A commercial item (as defined in paragraph (1) of the definition at FAR 2.101);
(ii) Sold in substantial quantities in the commercial marketplace; and
(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and
(2) Does not include bulk cargo, as defined in section 3 of the Shipping Act of 1984 (46 U.S.C. App. 1702), such as agricultural products and petroleum products.
"Component" means an article, material, or supply incorporated directly into a construction material.
"Construction material" means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.
"Cost of components" means -
(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or
(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.
"Domestic construction material" means--
(1) An unmanufactured construction material mined or produced in the United States;
(2) A construction material manufactured in the United States, if--
(i) The cost of its components mined, produced, or manufactured in the United States exceeds 50 percent of the cost of all its components. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic; or
(ii) The construction material is a COTS item.
"Foreign construction material" means a construction material other than a domestic construction material.
"United States" means the 50 States, the District of Columbia, and outlying areas.
(b) Domestic preference.
(1) This clause implements the Buy American Act (41 U.S.C. 10a-10d) by providing a preference for domestic construction material. In accordance with 41 U.S.C. 431, the component test of the Buy American Act is waived for construction material that is a COTS item (See FAR 12.505(a)(2)). The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.
(2) This requirement does not apply to information technology that is a commercial item or to the construction materials or components listed by the Government as follows:
None
(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that -
(i) The cost of domestic construction material would be unreasonable. The cost of a particular domestic construction material subject to the requirements of the Buy American Act is unreasonable when the cost of such material exceeds the cost of foreign material by more than 6 percent;
(ii) The application of the restriction of the Buy American Act to a particular construction material would be impracticable or inconsistent with the public interest; or
(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.
(c) Request for determination of inapplicability of the Buy American Act.
(1)
(i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(3) of this clause shall include adequate information for Government evaluation of the request, including -
(A) A description of the foreign and domestic construction materials;
(B) Unit of measure;
(C) Quantity;
(D) Price;
(E) Time of delivery or availability;
(F) Location of the construction project;
(G) Name and address of the proposed supplier; and
(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.
(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.
(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).
(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.
(2) If the Government determines after contract award that an exception to the Buy American Act applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material. However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(3)(i) of this clause.
(3) Unless the Government determines that an exception to the Buy American Act applies, use of foreign construction material is noncompliant with the Buy American Act or Balance of Payments Program.
(d) Data. To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the Contractor shall include the following information and any applicable supporting data based on the survey of suppliers:
Foreign and Domestic Construction Materials Price Comparison
Construction Material Description Unit of Measure Quantity Price (Dollars)* Item 1:
Foreign construction material _______ _______ _______
Domestic construction material _______ _______ _______
| Item 2: | _______ | _______ | _______ | |
| Foreign construction material | _______ | _______ | _______ |
Domestic construction material
List name, address, telephone number, and contact for suppliers surveyed. Attach copy of response; if oral, attach summary.
Include other applicable supporting information.
* Include all delivery costs to the construction site and any applicable duty (whether or not a duty-free entry certificate is issued).
FAR 52.228-1 Bid Guarantee. (SEP 1996)
(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.
(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds -
(1) To unsuccessful bidders as soon as practicable after the opening of bids; and
(2) To the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.
(c) The amount of the bid guarantee shall be 20 percent of the bid price.
(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.
(d) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.
(End of Clause)
NOTE: A bid guarantee is not required if total bid amount is less than $150,000.
FAR 52.236-3 Site Investigation and Conditions Affecting the Work. (APR 1984)
(a) The Contractor acknowledges that it has taken steps reasonably necessary to ascertain the nature and location of the work, and that it has investigated and satisfied itself as to the general and local conditions which can affect the work or its cost, including but not limited to (1) conditions bearing upon transportation, disposal, handling, and storage of materials; (2) the availability of labor, water, electric power, and roads; (3) uncertainties of weather, river stages, tides, or similar physical conditions at the site; (4) the conformation and conditions of the ground; and (5) the character of equipment and facilities needed preliminary to and during work performance. The Contractor also acknowledges that it has satisfied itself as to the character, quality, and quantity of surface and subsurface materials or obstacles to be encountered insofar as this information is reasonably ascertainable from an inspection of the site, including all exploratory work done by the Government, as well as from the drawings and specifications made a part of this contract.
This is the start of the file's text. The full file is on GovTribe.