83-2218-2013
Statement of Work
Building 9 Epoxy Wall Repair Project
1.0 Background:
The epoxy wall coating used in several of the large animal rooms in building 9 on the
USDA campus in Ames Iowa is starting to crack, separate and peel. This project will include a base bid for installing a fiberglass reinforced epoxy wall system in a small room of building nine as a trial mock up to see if it will work in other parts of the building. The base bid will also include preparation and installation of a new epoxy finish in three of the large animal rooms to reestablish an impermeable seal. If the fiberglass reinforced wall system proves to be an effective sealer, and can be cleaned easily, then the USDA will request option (A) to install the fiberglass reinforced wall coating in one of the large animal rooms. If the product does not meet the USDA’s expectations, the USDA will request option (B) to install a new epoxy wall coating without the fiberglass reinforcement to the room. There are two upcoming building shutdowns scheduled for this year. The first shut down will allow access to room 1090 between September 9th and
September 23rdin late September 2013. The second shutdown will allow access to rooms 1006, 1011, 1016 and 1021 between November 15th 2013 and January 1st
2014.from mid-November through December 2013.
2.0 Project Requirements:
The contractor shall complete the following.
1. Install a fiberglass reinforced wall coating system to the East wall of room 1090 in
Bldg. 9 as a trial mock up (approx. 204 square feet). The wall coating shall provide wear protection against abuse from large animals, prevent cracks from developing and shall be easy to clean. The wall in room 1090 is currently finished with epoxy.
and doesn’t have any adhesion issues. Abrade the wall surface before application of the new fiberglass reinforced coating system. This portion of the project shall be completed during the September shutdown. between September 9th and September
23rd.
2. Abrade the wall surfaces and remove all loose finish material in rooms 1006, 1011, and 1016 in building 9 in preparation for a new epoxy finish to be installed. It appears that the primer has remained adhered to the concrete and the separation is between the primer and the finish coat. It is not required to remove the primer coat for this project. Each room contains approximately 1848 square feet of wall area.
3. Apply two coats of epoxy to each of the walls in rooms 1006, 1011 and 1016. Both the intermediate coat and Tthe top coat shall be 14 1.5 mils DFT at a minimum.
4. Provide pricing for Option (A) to prepare and install a fiberglass reinforced epoxy coating to the walls in room 1021. Abrade the wall surface before application of the new fiberglass reinforced coating system. The fiberglass reinforcing shall consist of
5 ounce fiberglass mating at a minimum.
5. Provide pricing for option (B) to prepare and install a new epoxy finish to room 1021 to match the same specifications and surface preparation requirements for rooms
1006, 1011 and 1016.
6. Only 100% epoxy shall be used for the project.
7. Provide option (C) to install a polyurethane top coat to the new epoxy surfaces. as an option. Option (C) shall be broken down by price for each individual room.
8. All work in rooms 1006, 1011, 1016 and 1021 shall be completed between
November 15th 2013 and January 1st 2014. During the mid-November and December
2013 shutdown.
Existing Products:
Containment Walls o Epoxy Primer- Steri-Prime (Dudick), 1 coat at 200 sfpg, 3-4 mils dft o Epoxy Filler- Scratch 300 (Dudick), 1 coat, thickness as needed o Epoxy Finish- Protecto-Coat 125FR (Dudick), 1 coat at 100 sfpg, 14-16 mils dft
2.1 Warranty/Closeout:
A three year warranty shall be provided for faulty workmanship and material. The warranty shall start at the completion of the project.
The contractor shall provide technical specifications and product information along with the cost proposal.
An award will not be completed until the product has been determined to be acceptable.
3.0 General Requirements
3.1 Work Restrictions & Conditions
A. Site Security Access
1. Access to the construction site is controlled by a security fence and visitor/contractor check-in/check-out system. All contractor/subcontractor employees shall sign-in and out at the main entrance gate and wear a contractor/visitor identification badge at all times while on the site. The ID badges will be turned in at the end of the work day. A current government-issued identification with a picture ID is required for entry.
2. This project construction site is located in the limited access zone.
3. Construction vehicles will be allowed access adjacent to the work; contractor employee’s personal vehicles shall be parked in the facility parking lots.
4. The Contractor shall use only the service roads and access routes approved by the Contracting Officer’s Representative.
5. Work shall be confined to the areas identified on the Drawings. Unless accompanied by a NCAH/USDA employee, the Contractor, subcontractors, and their employees shall not enter buildings or facilities not specifically part of this project. Reasons included, but are not limited to, disease control and health requirements.
6. Additional security requirements may be imposed when the Federal Government raises the Homeland Security Alert Level. Additional directions will be provided if the situation occurs.
7. Failure to comply with access requirements shall be adequate grounds for removal of the Contractor/subcontractor employees from the site and barring further site access to individuals.
B. Work Hours: Regular work hours for the site are 7:00am to 6:00pm, Monday through Friday, excluding Government holidays.
C. Work Outside Regular Work Hours: Work scheduled outside regular work hours including late hours, Saturdays, Sundays, and Government holidays requires Contracting Officer’s Representative (COR) approval in advance. Make application to the COR at least 5 calendar days prior to such work to allow arrangements to be made by the Government for access to the work area and inspection & monitoring arrangements. Requests shall include the exact dates, hours, location, and purpose of the exception. If approved, the COR will coordinate access with the site security office.
3.2 Temporary Facilities
A. Utilities: The existing USDA utilities at the site may be used by the Contractor for completion of the contract work at no cost to the Contractor. The Contractor shall be responsible for making and removing any temporary utility connections.
B. Telephones: The Contractor shall equip all his foremen and work leaders with cell phones as necessary to coordinate the work effort. The Government will not provide any phone service to the project.
C. Construction Trailer: The Contractor may locate a job trailer to the site. Location and services shall be coordinated with the COR.
D. Toilet Facilities: The Contractor shall provide and maintain portable toilet facilities for the project workmen.
3.3 Warranty Documentation
1. Warranty List: Provide a warranty summary sheet in spreadsheet format with all the warranties listed by section, description, supplier, warranty contact, start date, end date. Provide electronic copy to the COR and place printed copy in the front of the Warranty Binder.
2. Warranty Copies in Binder: Provide the COR one signed & dated copy of all warranties for products and equipment installed on the project. An electronic
(scanned) copy of the Warranty Binder in a PDF file shall be submitted with the final close-out documentation.
END OF SECTION