Spec 7 Mob-Demob.pdf
PDF 18 KB Posted
- Solicitation number
- AG-5F48-S-09-0004
About this file
Project Specification 7 Mob/Demob
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Davis Bacon General Decision Number WI080019 08-21-2009 WI19.doc | DOC document | |
| Site Showing Minutes Laper-Westra-Gay.doc | DOC document | |
| Additional Construction Note.doc | DOC document | |
| Laper-Westra-Gay Section B 9-4-09.xls | XLS spreadsheet | |
| Additional Construction Note 9-4-09.doc | DOC document | |
| laper-westra-gay site maps.pdf | ||
| Lapers-Westra-Gay Bid Schedule Rev 8-28-09.xls | XLS spreadsheet | |
| SF-1442.pdf | ||
| Gay WRP Drawings.pdf | ||
| Westra WRP Drawings.pdf | ||
| Davis Bacon General Decision Number WI080019 08-07-09 WI19.doc | DOC document | |
| Laper WRP Drawings.pdf | ||
| Laper-Westra-Gay Wetland Restoration Project Solicitation.doc | DOC document | |
| Laper-Westra-Gay WRP Specifications.pdf |
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
USDA-NRCS-Wisconsin Section IV, Technical Guide 7-1 5/08
WISCONSIN CONSTRUCTION SPECIFICATION
7. MOBILIZATION AND DEMOBILIZATION
1. SCOPE
The work consists of the mobilization and demobilization of the Contractor's forces and equipment necessary for performing the work required.
2. EQUIPMENT AND MATERIAL
Mobilization shall include:
• All activities and associated costs for transportation of the Contractor's personnel, equipment, and operating supplies to the site;
• Establishment of offices, buildings, and other necessary general facilities for the Contractor's operations at the site
• Premiums paid for performance and payment bonds including coinsurance and reinsurance agreements as applicable
• Construction and maintenance of haul roads and equipment parking areas
• Other job related items
Demobilization shall include:
• All activities and costs for transportation of personnel, equipment, and supplies not utilized in the project from the site
• Disassembly, removal, and site cleanup of offices, buildings, and other facilities assembled on the site.
• Repair of access roads, temporary haul roads, and equipment parking areas leaving the project site in the same or better condition than at the start of the project.
• General cleanup and house keeping needed to restore a neat and orderly project site.
Access to the site, equipment parking, and staging areas are limited to that shown on the drawings or as approved by the technician.