Updated specification 01 1000
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| SF_30_4.pdf | ||
| 011000_Summary_of_Work6112015.docx | DOCX document | |
| SiteElectricalScheduleofItems.pdf | ||
| Updated_Drawing_Notes.docx | DOCX document | |
| Forest_Lodge_SITE_ELEC_REVISIONS_6-02-15.pdf | ||
| SF_30_3.pdf | ||
| SF_30_2.pdf | ||
| FL_Site_Electrical_Upgrade_Pre-bid_notes.docx | DOCX document | |
| SF_30.pdf | ||
| AG-569R-S-15-0022.rtf | RTF text file | |
| SF1442.pdf | ||
| SignedCoversheet.pdf | ||
| SiteElectricalFinalSpecifications4_6_2015.pdf | ||
| Wage_Determination.docx | DOCX document | |
| Site_ElectricalFinalDrawings3312015.pdf |
Show all 15
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION 011000
SUMMARY OF WORK
PART 1 – GENERAL
CONDITIONS OF THE CONTRACT
The conditions of the contract relating to the work specified herein also apply to this section. Applicable provisions of Division 00-Procurement and Contracting Requirements, and Division 01- General Requirements shall govern work under this section.
GENERAL REQUIREMENTS
Work in all sections is subject to the provisions of the Instructions to Bidders, General Conditions, Supplementary Conditions, and all other parts of the Contract Documents.
Reference Standards: Each section of the specifications generally includes a list of reference standards. The purpose of this list is to furnish the Contractor with a list of standards normally used for outlining the quality control desired on the project. The lists are not intended to be complete or all inclusive, but serve as a general reference of standards that are regularly referred to.
Materials: Each section of the specifications may include reference to various material types and/or products which may or may not be intended for use on the respective project. Unless otherwise stated, the Contractor will be allowed to furnish only that material listed in the bid proposal documents and/or construction plans.
WORK COVERED BY THE CONTRACT
The Work covered by the Contract Documents is:
U.S. Department of Agriculture Forest Service Eastern Region, Region 9 Lake States Acquisition Team Forest Lodge Site Electrical Bayfield County, Wisconsin
DESCRIPTION OF WORK
The Work consists of furnishing all labor, materials, taxes, services, equipment, and any other incidental or collateral work or items necessary to complete the project in accordance with the design specifications.
An abbreviated description of the specified Work is as follows:
The work includes the installation of new feeder cables to each of the structures. A new main switch will be installed. In most buildings, transformers, service panels and disconnects will be installed. The NEC 2014 and erosion control Best Management Practices will be followed.
WORK SEQUENCE
Construct work in stages; assure building and adjoining roof areas remain watertight.
CONTRACTOR USE OF PREMISES
011000 - 1
Confine operations at site to areas permitted by:
Law
Ordinances
Permits
These Contract Documents
Assume full responsibility for protection and safekeeping of material and products stored on or off premises.
Move any stored material or products which interfere with operations of Owner or other Contractors.
Obtain and pay for use of additional storage or work areas needed for operation.
TIME OF COMPLETION
Work shall be totally completed by the following date: October 1, 2015 PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
- END OF SECTION -