Attachment C10_DesignReport.pdf
PDF 145 KB Posted
- Solicitation number
- AG-569R-S-11-0021
About this file
Attachment C10 - Design Report
View the file
Other files
| File | Type | Posted |
|---|---|---|
| ATB Amendment 0003.pdf | ||
| Amendment 0002.pdf | ||
| Amendment 0001.rtf | RTF text file | |
| Attachment C8-DrawingList.pdf | ||
| Attachment C7-Ely_ATB_Photos.pdf | ||
| Attachment C6-HappyCampDwgs.pdf | ||
| Attachment C1-SitePlan.pdf | ||
| AG-569R-S-11-0021.rtf | RTF text file | |
| Attachment A - Statement of Work.docx | DOCX document | |
| Attachment C5-ConceptualHelibaseOfcFloorPlan.pdf | ||
| Attachment C4-ConceptualSitePlan.pdf | ||
| Attachment E - Davis-Bacon Wage Determination.docx | DOCX document | |
| Attachment C6a-HappyCampSpecs.pdf | ||
| Attachment C3-Wetlands Report.pdf | ||
| Attachment C9-ATB_Std_Specs.pdf | ||
| Attachment C2 - Soils Data Report.pdf | ||
| Attachment C11_Small_helibase_std_dwg.pdf | ||
| Attachment D - Service Contract Act Wage Determination.docx | DOCX document |
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Page C10-1
ATTACHMENT C-10
DESIGN REPORT FORMAT AND CONTENT
The Design Report with project drawings shall capture all aspects of the project including descriptions of engineering systems, building, site and utility design; structural, mechanical, electrical, water and wastewater analyses; energy analysis; and materials analysis. The report includes but is not limited by:
Project Program (Proposed and Actual)
Special Project Analyses Alternative Building Floor Plan Renewable Energy and Energy Efficiency Analysis Government Access Road Analysis
Civil Engineering Storm Water Management (Description) and Analysis (quantity, routing, storage) Utilities Roadway and Parking Site grading Design Calculations Yard Piping Wetland Impacts Wetland Mitigation
Landscape Architecture Site design concepts and features Vegetation and Plantings
Water/Wastewater Systems Discussion of water conservation strategies Code verification Descriptions of water system and alternatives Descriptions of wastewater systems Design flow calculations Fire flow requirements Calculations for utility system sizing All other design calculations
Architecture Basis of Design as defined in the LEED 3.0 Reference Manual.
Specific LEED/green considerations Code Analysis Space Analysis Description of key interior/exterior features, image, focus for material selection, etc) Functional Analysis of Project program
Page C10-2
Structural Systems Narrative description of the structural systems Preliminary calculations Code and loading requirements Summary of the Geotech Report and significant site considerations, findings and recommendations.
Include a copy of the Geotech report as an appendix.
Foundation system Roof and floor framing systems Lateral load-resisting elements
Mechanical Systems LEED/green considerations Descriptions of the recommended HVAC System and other alternatives considered.
Description of the system controls.
Analysis and Rationale for recommended system Load analysis and equipment sizing calculations Mechanical code review, listing special code requirements Adequacy of site utilities for mechanical systems, based on actual measurements of flow and pressure available or based on information from local utility companies.
Description, design calculations of renewable energy system(s)
Electrical Systems LEED/green criteria Descriptions of electrical systems and alternatives Load summary and calculations Smart metering and panel layout for advanced metering Adequacy of site utilities for electrical systems based on information from local utility companies;
verification of phase and voltage available Electrical code review, listing special code requirements Discussion of telecommunication/data, fire, and Access control system Lighting (design levels, photometric calculations, lighting diagrams, etc)
Building Simulation Description of Software and methodology Source of data and key assumptions Baseline analysis (ASHRAE 90.1-2004 or Energy Star 50) Model runs based on current level of design Model runs used to analyze competing alternatives Comparison of design to baseline (30% reduction) Estimation of individual buildings, Site and total energy usage Estimation of individual building, site and total CO2 emissions.
Simulation of renewable energy generation based on system selected Simulation of energy generation/savings from passive system like passive solar Graphic displays of data
Fire Plan & safety Analysis A complete code assessment based on International Fire Code and Life Safety Code (NFPA 101) shall be performed and documented. Include a narrative and sketches showing egress, exits, fire rated separations, travel distances, alarm, emergency lighting and fire extinguisher locations, interior finish classes, etc.