View the file

Other files

File Type Posted
Amdmt 0003.rtf RTF text file
Amdmt 0002.rtf RTF text file
PREbidConfHorseshoe_8-20-09.doc DOC document
Amdmt 0001.rtf RTF text file
Att J-1_Tech Specs - Horseshoe Rec Area Paving Imprvmts.pdf PDF
Att J-2_Plans pp 1-20.pdf PDF
SF-1442.doc DOC document
Horseshoe CONSTRUCTION_IFB.doc DOC document
Att J-4_Wage Det - HWY.doc DOC document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Engineer's Estimate

COST ESTIMATE
Horseshoe Recreation Area - Paving and Site Improvements
Item No.Project SpecDescriptionMethod MeasureUnitQuantityUnit CostTotal Cost
1207001-001ExcavationDQcy265$ 90.00$ 23,850.00
2207002-000SubgradeDQcy1454$ 36.00$ 52,344.00
3207034-000Fabric for SeparationDQsy3627$ 1.50$ 5,440.50
4307001-000Aggregate Base, Class 1DQcy1252$ 30.00$ 37,560.00
5307001-000Aggregate Base, Class 10DQcy224$ 30.00$ 6,720.00
6401001-001Marshall Hot-Mix Asphalt Base Course, Class 1DQton1126$ 105.00$ 118,230.00
7401002-001Marshall Hot-Mix Asphalt Wearing CourseDQton498$ 125.00$ 62,250.00
8609001-0014" Concrete PavementDQsy9$ 200.00$ 1,800.00
9Flagstone PavingDQsy23$ 350.00$ 8,050.00
10Aggregate PavementDQsy564$ 30.00$ 16,920.00
11401002-001Pavement StripingDQlf1000$ 0.50$ 500.00
12401002-001Accessible Pavement MarkingsAQea5$ 150.00$ 750.00
Potable Water and Sanitary Sewer
136" Steel Encasement Pipe, Open TrenchDQlf534$ 200.00$ 106,800.00
144" Steel Encasement Pipe, Open TrenchDQlf38$ 175.00$ 6,650.00
153" Steel Encasement Pipe, Open TrenchDQlf47$ 150.00$ 7,050.00
General Project Items
16204001-000MobilizationLSQmile1$ 25,000.00$ 25,000.00
17639001-001Construction StakingLSQmile1$ 18,000.00$ 18,000.00
18329002Grading and SeedingLSQmile1$ 10,000.00$ 10,000.00
19Log CurbAQmile6$ 500.00$ 3,000.00
20Reserved Parking Sign AssemblyAQmile5$ 250.00$ 1,250.00
21Wheel StopAQmile7$ 85.00$ 595.00
Bid Total$ 512,759.50

&R&"Times New Roman,Bold"By:_________ Date:________

Approved:________________

Schedule

ABSTRACT OF OFFERS—CONSTRUCTION
Solicitation No. AG-51KN-S-09-0034Opened: 9/1/2009Solicitation No. AG-51KN-S-09-0034Opened: 9/1/2009
ProjectProject
Title:Camp Horseshoe Recreation Area Paving and Site ImprovementsTitle:Camp Horseshoe Recreation Area Paving and Site Improvements
Monongahela National ForestMonongahela National Forest
Page 1 of 2Page 2 of 2
Number of Addenda Issued: 3Number of Offers:
I certify that I have opened, read, and recorded on this abstract
all offers received in response to this solicitation.
/s/ Debra Huron
Contracting Officer9/1/09
Date
Offeror #1Offeror #2Offeror #3Offeror #4Offeror #5
ContractorGreen River Group LLCMeadows Stone & Paving IncContractorJF Allen CompanyLaurita Excavating, Inc.West Virginia Paving Inc.
City, StateMorgantown, WV 26508Gassaway, WV 26624City, StateBuckhannon, WV 26201Morgantown, WV 26501Dunbar, WV 25064
AddendaAcknowledgedYes XX/ NoYes xx/ NoAddendaAcknowledgedYes xx/ NoYes xx/ NoYes xx/ No
BondingYes XX/ NoYes xx/ NoBondingYes xx/ NoYes xx/ NoYes xx/ No
SCHEDULE OF ITEMS
Horseshoe Recreation Area - Paving and Site Improvements
Item No.Project SpecDescriptionMethod MeasureUnitQuantityUnitTotalUnitTotalItem No.UnitTotalUnitTotalUnitTotal
PriceAmountPriceAmountPriceAmountPriceAmountPriceAmount
1207001-001ExcavationDQcy265$28.00$7,420.00$86.00$22,790.001$40.95$10,851.75$98.89$26,205.85$150.00$39,750.00
2207002-000SubgradeDQcy1454$47.00$68,338.00$40.40$58,741.602$24.20$35,186.80$67.67$98,392.18$45.00$65,430.00
3207034-000Fabric for SeparationDQsy3627$2.00$7,254.00$2.00$7,254.003$1.50$5,440.50$1.04$3,772.08$2.00$7,254.00
4307001-000Aggregate Base, Class 1DQcy1252$48.00$60,096.00$55.00$68,860.004$48.40$60,596.80$67.67$84,722.84$46.00$57,592.00
5307001-000Aggregate Base, Class 10DQcy224$54.00$12,096.00$56.75$12,712.005$59.15$13,249.60$61.90$13,865.60$66.00$14,784.00
6401001-001Marshall Hot-Mix Asphalt Base Course, Class 1DQton1126$90.00$101,340.00$88.00$99,088.006$77.25$86,983.50$93.43$105,202.18$95.00$106,970.00
7401002-001Marshall Hot-Mix Asphalt Wearing CourseDQton498$105.00$52,290.00$95.00$47,310.007$87.80$43,724.40$116.13$57,832.74$110.00$54,780.00
8609001-0014" Concrete PavementDQsy9$300.00$2,700.00$300.00$2,700.008$219.70$1,977.30$363.60$3,272.40$403.00$3,627.00
9Flagstone PavingDQsy23$400.00$9,200.00$540.00$12,420.009$318.00$7,314.00$493.29$11,345.67$185.00$4,255.00
10Aggregate PavementDQsy564$17.00$9,588.00$20.00$11,280.0010$29.20$16,468.80$9.20$5,188.80$35.00$19,740.00
11401002-001Pavement StripingDQlf1000$1.00$1,000.00$1.00$1,000.0011$1.25$1,250.00$3.38$3,380.00$2.00$2,000.00
12401002-001Accessible Pavement MarkingsAQea5$150.00$750.00$175.00$875.0012$400.00$2,000.00$281.37$1,406.85$100.00$500.00
Potable Water and Sanitary Sewer
136" Steel Encasement Pipe, Open TrenchDQlf534$30.00$16,020.00$49.00$26,166.0013$49.00$26,166.00$42.10$22,481.40$70.00$37,380.00
144" Steel Encasement Pipe, Open TrenchDQlf38$25.00$950.00$40.00$1,520.0014$49.00$1,862.00$38.38$1,458.44$80.00$3,040.00
153" Steel Encasement Pipe, Open TrenchDQlf47$23.00$1,081.00$38.00$1,786.0015$49.00$2,303.00$37.98$1,785.06$70.00$3,290.00
General Project Items
16204001-000MobilizationLSQmile1$16,000.00$16,000.00$15,000.00$15,000.0016$22,000.00$22,000.00$22,509.44$22,509.44$4,000.00$4,000.00
17639001-001Construction StakingLSQmile1$4,500.00$4,500.00$8,000.00$8,000.0017$26,826.80$26,826.80$11,254.73$11,254.73$6,500.00$6,500.00
18329002Grading and SeedingLSQmile1$6,000.00$6,000.00$4,000.00$4,000.0018$24,323.20$24,323.20$5,796.18$5,796.18$8,000.00$8,000.00
19Log CurbAQea6$500.00$3,000.00$275.00$1,650.0019$522.50$3,135.00$488.64$2,931.84$625.00$3,750.00
20Reserved Parking Sign AssemblyAQmile5$500.00$2,500.00$125.00$625.0020$200.00$1,000.00$116.19$580.95$254.00$1,270.00
21Wheel StopAQmile7$200.00$1,400.00$125.00$875.0021$200.00$1,400.00$115.92$811.44$170.00$1,190.00
TOTAL: Items 1-21Apparent Low:$383,523.00Should Be$404,652.60TOTAL: Items 1-21$394,059.45$484,196.67$445,102.00
contractor bid:$404,472.60

File details come from the government source that posted it. Updated .