grape_bid_schedule_(5).pdf

PDF 16 KB Posted

Attached to
ROAD REPAIR Federal contract opportunity
Solicitation number
AG-4568-S-13-0056
Issued by
Department of Agriculture Forest Service

About this file

BID SCHEDULE COST BREAKDOWN - GRAPEVINE ROAD REPAIR

View the file

Other files for this federal contract opportunity

Other files attached to ROAD REPAIR, newest first.
File Type Posted
att_3_experience_questionnare.doc DOC document
Contract.docx DOCX document
ATT._2_Statement_of_Work.docx DOCX document
sf-18rfq.pdf PDF
sf30mod.pdf PDF
DB__CHEOAH.docx DOCX document
sf1442sol.pdf PDF
att_2_Drawing_04_(5)n.pdf PDF
att_2_Drawing_03_(3).pdf PDF
ATT_2_SOW.docx DOCX document
att._2_Drawing_01_(3).pdf PDF
att._2_grape_specs_(3).pdf PDF
att_2_Drawing_02_(3).pdf PDF
Show all 13

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

8/6/2013

Contract 2606

Road Name 1.83

ITEM NO. DESCRIPTION UNIT QUANTITY UNIT PRICE TOTALS

15702 36"x18"x14" Hay Bales with Stakes Installed on Slides EA 345.0

20101 Clearing and Grubbing, Disposal Method E Mile 1.8

62506 Seeding, fertilizing, and mulching, hydraulic method Acre 0.7

2606 -$

AQ

CQ

CQ

SCHEDULE OF ITEMS

(PUBLIC WORKS)

Length (Miles)NFSR 2606 - Grapevine

SUB-TOTAL FOR ROAD:

Road No.

As stated in FP-03, Subsection 109.05, payment for all contract work is provided, either directly or indirectly, under the pay items shown in the bid schedule. Work for which direct payment is not provided is a subsidary obligation of the Contractor. Payment for such work is indirectly included under other pay items shown in the bid schedule. All quantities are Actual Quantities unless specifically designated as a Contract

Quantity by "CQ"

METHOD OF

MEASURE

File details come from the government source that posted it. Updated .