att._2_grape_specs_(3).pdf
PDF 85 KB Posted
- Attached to
- ROAD REPAIR Federal contract opportunity
- Solicitation number
- AG-4568-S-13-0056
- Issued by
- Department of Agriculture Forest Service
About this file
STATEMENT OF WORK SPECIFICATIONS
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| att_3_experience_questionnare.doc | DOC document | |
| Contract.docx | DOCX document | |
| ATT._2_Statement_of_Work.docx | DOCX document | |
| sf-18rfq.pdf | ||
| sf30mod.pdf | ||
| DB__CHEOAH.docx | DOCX document | |
| grape_bid_schedule_(5).pdf | ||
| sf1442sol.pdf | ||
| att_2_Drawing_04_(5)n.pdf | ||
| att_2_Drawing_03_(3).pdf | ||
| ATT_2_SOW.docx | DOCX document | |
| att._2_Drawing_01_(3).pdf | ||
| att_2_Drawing_02_(3).pdf |
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Grapevine Road Stabilization
Table of Contents
Table of Contents
Preface
101 - Terms, Format, and Definitions
101.01 Meaning of Terms
101.03 Abbreviations
101.04 Definitions
102 - Bid, Award, and Execution of Contract
102 Bid, Award, and Execution of Contract
103 - Scope of Work
Deletions
104 - Control of Work
Deletions
104.06 Use of Roads by Contractor
105 - Control of Material
105.02 Material Sources
105.02(a) Government-provided sources
105.05 Use of Material Found in the Work
106 - Acceptance of Work
106.07 Delete
107 - Legal Relations and Responsibility to the Public
107.05 Responsibility for Damage Claims
107.06 Contractor’s Responsibility for Work
107.09 Legal Relationship of the Parties
107.10 Environmental Protection
108 - Prosecution and Progress
108 Delete
109 - Measurement and Payment
109 Deletions
109.02 Measurement Terms and Definitions
109.04 Receiving Procedures
151 - Mobilization
153 - Contractor Quality Control
153.02 Contractor Quality Control Plan
153.04 Records
155 - Schedules for Construction Contracts
155 Delete
157 - Soil Erosion Control
157.03 General
157.08 Water Crossings
157.11 Temporary Turf Establishment
157.12 Inspection and Reporting
157.13 Maintenance and Cleanup
201 - Clearing and Grubbing
201.02 Material:
201.01 Description
201.04 Clearing. (c)
201.06 Disposal
203 - Removal of Structures and Obstructions
203.05 Disposing of Material
713 - Roadside Improvement Material
713.04 Seed
713.05 Mulch
Preface
Preface_wo_03_15_2004_m
Delete all but the first paragraph and add the following:
The Forest Service, US Department of Agriculture has adopted FP-03 for construction of
National Forest System Roads.
101 - Terms, Format, and Definitions
101.00_nat_us_07_25_2005
101.01_nat_us_01_22_2009
101.01 Meaning of Terms
Delete all references to the TAR (Transportation Acquisition Regulations) in the specifications.
101.03_nat_us_06_16_2006
101.03 Abbreviations.
Add the following to (a) Acronyms:
AFPA
MSHA
NIST
NESC
WCLIB
American Forest and Paper Association
Mine Safety and Health Administration
National Institute of Standards and Technology
National Electrical Safety Code
West Coast Lumber Inspection Bureau
Add the following to (b) SI symbols:
mp Milepost ppm Part Per Million
101.04_nat_us_03_29_2007
101.04 Definitions.
Delete the following definitions and substitute the following:
Bid Schedule--The Schedule of Items.
Bridge--No definition.
Contractor--The individual or legal entity contracting with the Government for performance of prescribed work. In a timber sale contract, the contractor is the “purchaser”.
Culvert--No definition.
Right-of-Way--A general term denoting (1) the privilege to pass over land in some particular line (including easement, lease, permit, or license to occupy, use, or traverse public or private lands), or (2) Real property necessary for the project, including roadway, buffer areas, access, and drainage areas.
Add the following:
Adjustment in Contract Price--“Equitable adjustment,” as used in the Federal Acquisition
Regulations, or “construction cost adjustment,” as used in the Timber Sale Contract, as applicable.
Change--“Change” means “change order” as used in the Federal Acquisition Regulations, or
“design change” as used in the Timber Sale Contract.
Design Quantity--“Design quantity” is a Forest Service method of measurement from the FS-96
Forest Service Specifications for the Construction of Roads and Bridges. Under these FP specifications this term is replaced by the term “Contract Quantities”.
Forest Service--The United States of America, acting through the Forest Service, U.S.
Department of Agriculture.
Neat Line--A line defining the proposed or specified limits of an excavation or structure.
Pioneer Road--Temporary construction access built along the route of the project.
Purchaser--The individual, partnership, joint venture, or corporation contracting with the
Government under the terms of a Timber Sale Contract and acting independently or through agents, employees, or subcontractors.
Protected Streamcourse--A drainage shown on the plans or timber sale area map that requires designated mitigation measures.
Road Order--An order affecting and controlling traffic on roads under Forest Service jurisdiction. Road Orders are issued by a designated Forest Officer under the authorities of 36
CFR, part 260.
Schedule of Items--A schedule in the contract that contains a listing and description of construction items, quantities, units of measure, unit price, and amount.
Utilization Standards--The minimum size and percent soundness of trees described in the specifications to determine merchantable timber.
Add Figure 101-1—Illustration of road structure terms:
Figure 101-1—Illustration of road structure terms.
102 - Bid, Award, and Execution of Contract
102.00_nat_us_02_16_2005
102 Bid, Award, and Execution of Contract
Delete Section 102 in its entirety.
103 - Scope of Work
103.00_nat_us_02_16_2005
Deletions
Delete all but subsection 103.01 Intent of Contract.
104 - Control of Work
104.00_nat_us_06_16_2006
Deletions
Delete Sections 104.01, 104.02, and 104.04.
104.06_nat_us_02_17_2005
Add the following subsection:
104.06 Use of Roads by Contractor
The Contractor is authorized to use roads under the jurisdiction of the Forest Service for all activities necessary to complete this contract, subject to the limitations and authorizations designated in the Road Order(s) or described in the contract, when such use will not damage the roads or national forest resources, and when traffic can be accommodated safely.
105 - Control of Material
105.02_nat_us_01_18_2007
105.02 Material Sources.
105.02(a) Government-provided sources.
Comply with the requirements of 30 CFR 56, subparts B and H. Use all suitable material for aggregate regardless of size unless otherwise designated. When required, re-establish vegetation in disturbed areas according to section 625.
105.05_nat_us_05_12_2004
105.05 Use of Material Found in the Work.
Delete 105.05 (a) and (b) and the last sentence of the second paragraph and substitute the following:
Materials produced or processed from Government lands in excess of the quantities required for performance of this contract are the property of the Government. The Government is not obligated to make reimbursement for the cost of producing these materials.
106 - Acceptance of Work
106.07_nat_us_05_11_2004
106.07 Delete
Delete subsection 106.07.
107 - Legal Relations and Responsibility to the Public
107.05_nat_us_05_11_2004
107.05 Responsibility for Damage Claims.
Delete the entire subsection.
107.06_nat_us_06_16_2006
107.06 Contractor’s Responsibility for Work.
Delete the following from the first paragraph.
“except as provided in Subsection 106.07”.
107.09_nat_us_06_16_2006
107.09 Legal Relationship of the Parties.
Delete the entire subsection.
107.10_nat_us_06_16_2006
107.10 Environmental Protection.
Add the following:
Design and locate equipment repair shops, stationary refueling sites, or other facilities to minimize the potential and impacts of hazardous material spills on Government land.
Before beginning any work, submit a Hazardous Spill Plan. List actions to be taken in the event of a spill. Incorporate preventive measures to be taken, such as the location of mobile refueling facilities, storage and handling of hazardous materials, and similar information. Immediately notify the CO of all hazardous material spills. Provide a written narrative report form no later than 24 hours after the initial report and include the following:
• Description of the item spilled (including identity, quantity, manifest number, and other identifying information).
• Whether amount spilled is EPA or state reportable, and if so whether it was reported, and to whom.
• Exact time and location of spill including a description of the area involved.
• Containment procedures.
• Summary of any communications the Contractor had with news media, Federal, state and local regulatory agencies and officials, or Forest Service officials.
• Description of clean-up procedures employed or to be employed at the site including final disposition and disposal location of spill residue.
When available provide copies of all spill related clean up and closure documentation and correspondence from regulatory agencies.
The Contractor is solely responsible for all spills or leaks that occur during the performance of this contract. Clean up spills or leaks to the satisfaction of the CO and in a manner that complies with Federal, state, and local laws and regulations.
108 - Prosecution and Progress
108.00_nat_us_02_16_2005
108 Delete.
Delete Section 108 in its entirety.
109 - Measurement and Payment
109.00_nat_us_02_17_2005
109 Deletions
Delete the following entire subsections:
109.06 Pricing of Adjustments.
109.07 Eliminated Work.
109.08 Progress Payments.
109.09 Final Payment.
109.02_nat_us_06_16_2006
109.02 Measurement Terms and Definitions.
(b) Contract quantity.
Add the following:
Contract quantities will be adjusted only when there are errors in the original design of 15% or more.
Change the following:
“(b) Cubic yard” to “(c) Cubic yard”.
Add the following definition:
(p) Thousand Board Feet (Mbf). 1,000 board feet based on nominal widths, thickness, and extreme usable length of each piece of lumber or timber actually incorporated in the job. For glued laminated timber, 1,000 board feet based on actual width, thickness, and length of each piece actually incorporated in the job.
109.04_0811_us_12_14_2004
109.04 Receiving Procedures.
Delete the section and add the following:
When the method of measurement requires weighing in the hauling vehicle, furnish a person to direct the spreading and distribution of material and to record the location and placement of the material on the project. During the placement, maintain a record of each delivery and document it in an acceptable manner. Include the following information:
a) Project identification
b) Truck identification
c) Drivers Name and original signature
d) Date and time weighed
e) Gross and net mass
f) Daily total for each truck
Use an approved format for the delivery record(s). Furnish the original record(s) and a written certification of the delivery of the material at the end of each week.
151 - Mobilization
151.03_nat_us_08_05_2005
151.03 Payment
Delete the entire subsection and add the following:
151.03 Payment
Mobilization is considered an indirect cost of this contract and will not be compensated as a separate work item.
153 - Contractor Quality Control
153.02_nat_us_02_17_2005
153.02 Contractor Quality Control Plan.
Add the following:
Submit written proposals for approval of alternate AASHTO or State approved test methods.
Alternate methods may be allowed based on documented equivalence to the specified method.
153.04_nat_us_10_24_2007
153.04 Records.
Delete all but the first sentence
155 - Schedules for Construction Contracts
155.00_nat_us_05_11_2004
155 Delete.
Delete Section 155 in its entirety.
157 - Soil Erosion Control
157.03_0811_us_12_14_2004
157.03 General.
Delete the first two paragraphs and add the following:
Submit an Erosion Control Plan detailing permanent and temporary control measures to minimize erosion and sedimentation during and after construction according to the contract specifications, contract permits, Section 107, and this Section. Contract permits amend the requirements of this Section. Do not modify the type, size, or location of any control or practice without approval. Submit the erosion control plan proposal at least 7 days before operations begin to the Contracting Officer for approval.
Reflect in the erosion control plan special concerns and measures necessary to protect resources and government improvements. Include:
1. The construction activities and sequence of implementation relating to specific erosion control measures.
2. The location and type of permanent controls to be implemented during construction.
3. The location and type of temporary controls to be implemented during construction.
4. For work in stream channels with equivalent 48 inch or greater culverts a detailed dewatering plan.
5. For work in stream channels without flowing water describe level of ground and vegetative disturbance and measures to reduce potential sediment delivery.
6. Describe what monitoring will take place.
Add to the third paragraph:
Upon completion of construction at the site, all temporary dewatering materials and equipment are to be removed from Government property.
157.08 Water Crossings.
Add the following:At any channel crossing designed for an equivalent 48 inch or greater culvert installation dewater by rerouting water flow around the site before and during excavation and embankment operations.
157.11 Temporary Turf Establishment
Delete the subsection including table 157-1 and replace with the following:
Apply seed, fertilizer, and mulch for soil erosion protection at the required rates. Protect and care for seeded areas, including watering, until permanent turf establishment is in place.
157.12 Inspection and Reporting
Delete the first paragraph and replace it with the following:
Inspect all erosion control facilities at least every 7 days, within 24 hours after more than ¼ inch of rain in a 24 hour period, as required by the Contractor prepared erosion control plan, and as required by contract permits.
157.13 Maintenance and Cleanup
Delete the second sentence and add the following:
Clean erosion control measures when sediment is 6 inches deep or when they are half full of sediment, which ever is less.
201 - Clearing and Grubbing
201.00_nat_us_08_05_2009
201.02 Material:
Delete Tree wound dressing material reference.
201.03 General.
Delete the last sentence.
201.04 Clearing.
Delete the last sentence of (d).
201.01_nat_us_02_18_2005
201.01 Description
Replace with the following
This work consists of clearing and grubbing within clearing limits and other designated areas.
201.04_nat_us_02_22_2005
201.04 Clearing. (c)
Delete paragraph (c) and replace with the following:
(c) In areas outside the excavation, embankment, and slope rounding limits, cut stumps to within 12 inches or one-third of the stump diameter of the ground, whichever is higher, measured on the side adjacent to the highest ground. For timber sales, stump heights will meet the requirements of the Timber Sale contract.
201.04 Clearing.
Delete subsection (d) and replace with the following:
(d) Do not cut vegetation less than 3 feet tall and less than 3 inches in diameter, that is within the clearing limits but beyond the roadway and not in a decking area, and that does not interfere with sight distance along the road.
Add the following:
(e) Trim branches of remaining trees or shrubs to give a clear height of 14 feet above the roadbed unless otherwise indicated. Trim tree limbs as near flush with the trunk as practicable.
(f) Remove brush from log decks. Deck logs so that logs are piled parallel to one another; can be removed by standard log loading equipment; will not damage standing trees; will not interfere with drainage, and will not roll. Keep logs in log decks free of brush and soil.
201.06_nat_us_02_23_2005
201.06 Disposal.
Delete the first sentence of this subsection and substitute the following:
All merchantable timber within the clearing limits on either private or Government land remains the property of the landowners. Deck according to 201.04(f) on each owner's property adjacent to the road in approved locations.
203 - Removal of Structures and Obstructions
203.05_nat_us_02_18_2005
203.05 Disposing of Material.
Add the following:
(e) Windrowing Construction Slash. Place construction slash outside the roadway in neat, compacted windrows approximately parallel to and along the toeline of embankment slopes. Do not permit the top of the windrows to extend above subgrade. Use construction equipment to matt down all material in a windrow to form a compact and uniform pile. Construct breaks of at least 15 feet at least every 200 feet in a windrow. Do not place windrows against trees. Obtain approval for pioneer roads. A pioneer road may be constructed to provide an area for placement of windrows, provided the excavated material is kept within the clearing limits and does not adversely affect the road construction.
(f) Scattering. Scatter construction slash outside the clearing limits without damaging trees.
Limb all logs. Place logs and stumps away from trees, positioned so they will not roll, and are not on top of one another. Limb and scatter other construction slash to reduce slash concentrations.
(g) Chipping or Grinding. Use an approved chipping machine to grind slash and stumps greater than 3 inches in diameter and longer than 3 feet. Deposit chips or ground woody material on embankment slopes or outside the roadway to a loose depth less than 6 inches. Minor amounts of chips or ground woody material may be permitted within the roadway if they are thoroughly mixed with soil and do not form a layer.
(h) Debris Mat. Use tree limbs, tops, cull logs, split stumps, wood chunks, and other debris to form a mat upon which construction equipment is operated. Place stumps upside down and blend stumps into the mat.
(i) Decking Firewood Material. Remove brush from decks. Limb and deck logs that do not meet Utilization Standards according to Subsection 201.04 as directed by the CO. Cut logs to lengths less than 30 feet. Ensure that logs stacks are stable and free of brush and soil.
(j) Removal to designated locations. Remove construction slash to designated locations.
(k) Piling. Pile construction slash in designated areas. Place and construct piles so that if the piles are burned, the burning will not damage remaining trees. Keep piles free of dirt from stumps. Cut unmerchantable logs into lengths of less than 20 feet.
(l) Placing Slash on Embankment Slopes. Place construction slash on completed embankment slopes to reduce soil erosion. Place construction slash as flat as practicable on the completed slope. Do not place slash closer than 2 feet below subgrade. Priority for use of available slash is for: (1) through fills; (2) insides of curves; and (3) ditch relief outlets.
(m) Hydrological Sensitive Placement. Where required use this method in combination with other designated methods to dispose of material to reduce erosion and to aid in re-vegetation:
1. Place windrow segments on contours, wrap in type I geotextile.
2. Place logs as log erosion barriers on contours. Place logs so that 80% of their length is on the ground surface.
3. Scatter slash on bare or disturbed areas within or outside the clearing limits as directed.
4. Scatter chips or ground woody material on bare or disturbed areas within or outside the clearing limits as directed.
Place stumps in swales or on sites to form planting pockets. Place windrow segments on contours, wrap in type I geotextile.
713 - Roadside Improvement Material
713.04_0811_us_05_04_2007
713.04 Seed
Add the following:
Furnish a product certification for each kind or type of seed, certifying that the seed was tested by a recognized laboratory within 6 months of the date of delivery. Include the following:
(1) Name and address of testing laboratory
(2) Date of test
(3) Seed identification
(4) Test results showing the percentages of purity, germination, and weed content
(5) Certified weed-free seed.
713.05_nat_us_03_02_2005
713.05 Mulch.
Assure that mulch used on the project is certified noxious weed free by the appropriate authority in the jurisdiction of use.