DONIPHAN RANGER STATION
DEFERRED MAINTENANCE ADMINISTRATIVE SITE
CIM-0905-15F-190-0905-04
Specifications-Table of Contents
Specifications-Table of Contents
Summary of Work
Applicable Codes
Abbreviations
General Provisions
OSHA Training Requirements
SIDING, TRIM, AIR/WATER BARRIERS, and WINDOW REINSTALLATION
Item No. 1A, 1B, 2A
Optional Item No. 1C
Optional Item No. 1D
REPAIR and/or REPLACEMENT OF ROOFING MATERIAL and ROOF SHEATHING
Item No. 3A
TROUBLESHOOTING OF THE EXISTING LULA ELEVATOR
Item No. 4A
REPAIRING OF THE EXISTING ELEVATOR
Optional Item No. 4B
ANALYSIS OF THE EXISTING HVAC INSTALLATION AND RECOMMENDATIONS FOR
REPAIR
Item No. 5A
REPAIR AND MODIFICATION OF THE EXISTING HVAC SYSTEM
Item No. 5B
Optional Item No. 5C:
CONVERT THE EXISTING EMERGENCY LIGHT FIXTURES TO WORK WITH THE
EXISTING SWITCHES
Item No. 6A
CONVERTING THE EXISTING FIXTURES TO OPERATE AT THREE LIGHTING LEVELS 14
Optional Item No. 6B
FURNISH AND INSTALL INSULATION IN LOWER LEVEL EXTERIOR
Item No. 7A
FURNISH, INSTALL, AND REINSTALLATION OF ATTIC INSULATION
Optional Item No. 8A
INSTALLATION OF DRAFTSTOPPING WALLS IN THE ATTIC
CIM-0905-15F-190-0905-04
Item No. 9A
MOBILIZATION
Item No. 10A
CIM-0905-15F-190-0905-04
Summary of Work
Summary of Work: The Doniphan Ranger Station Office is a 11,600 sq. ft., two story wood frame office building located 2 miles east of the town of Doniphan, Missouri. This office was constructed in 2003. This office is owned by and this contract will be administered by USDA Forest Service
(USDA FS).
This contract is to conduct maintenance and fix deficiencies on the building siding, windows, roof, mechanical systems, electrical and lighting systems, and insulation.
This contract is a construction contract. The Contractor shall furnish and install all material, furnish designs where indicated, provide all necessary equipment, provide any services, provide operation and maintenance manuals as required; and any incidentals necessary to perform the work specified below.
This contract consists of ten general items:
1. Furnish and install 5350 sq. ft. (Item No. 1A) to 6850 sq. ft. (Item No. 1A plus Optional
Item No. 1C) of siding and building wrap, and remove the existing wood siding;
2. Removal and proper reinstallation of the existing 43 wood windows and water/air barriers;
3. Troubleshoot, furnish, and repair roofing and sheathing at the front entry, of less than 200
sq. ft.
4. Troubleshooting and optional repair of the existing LULA elevator,
5. Troubleshoot, redesign, reuse, repair, balancing and commissioning of the existing HVAC system, including installing two zones in the basement; and optional replacement of the
HVAC systems
6. Modification and rewiring the lighting electrical system to allow the operation of twenty-five office fluorescent fixtures with the existing wall switches (remove the emergency operation); and an optional item to convert the existing 3 bulb fixtures to three way operation.
7. Install and design of insulation of existing 4” exterior stud walls, 1300 sq. ft.,
8. Optional reinstallation of incorrectly applied insulation in the attic, 1000 sq. ft.;
9. Installation of draftstopping material in the attic.
10. Mobilization
The above items are divided into broken up to 11 scheduled items and 6 optional scheduled items.
Award of the optional items will depend on the convenience of the government, changed scope of work, and price.
Applicable Codes
The proposed work shall comply with all applicable codes, including the following:
1. The International Building Code (IBC2009)
2. National Electric Code (NEC2008-NFPA 70)
3. International Fuel Gas Code (IFGC)
4. International Plumbing Code (IPC2009)
5. International Mechanical Code (IMC2009)
6. International Energy Conservation Code
7. International Fire Code
8. American Society of Heating, Refrigeration and Air-Conditioning Engineers (ASHRAE)
Standards, including 111 (Practices for Measuremnt, Testing, and Balancing of Building
HVAC…); and 62.1 (Ventilation for Acceptable Indoor Air Quality).
Abbreviations
HVAC Heating, Ventilation, Air Conditioning
AFUE Annual Fuel Utilization Efficiency
VAV Variable Air Volume
AHU Air Handling Unit
HRV Heat Recovery Ventilation
IAQ Indoor Air Quality
CO Contracting Officer
IBC International Building Code
LULA Limited Use, Limited Access
SOG Slab on grade
Sq. ft. square feet
General Provisions
The contractor shall:
1. Be responsible for location of all utilities prior to commencement of all demolition, excavation, trenching of or associated work.
2. Finish or restore all areas that are disturbed during construction.
3. Contractor shall include manufacturer installation instructions and best practices along with all product submittals prior to Contracting Officer (CO) approval and contractor installation.
4. Contractor shall install components according to industry standards, IBC, and manufacturers’ written instructions.
5. Provide manufacturer data sheets for all major components of the proposed renovation.
6. Provide as-built drawings showing types and locations of installed components.
7. Provide a minimum one year warranty on all workmanship and installed components of the system.
8. Remove of and dispose-of/recycle existing components not designated for reuse to include:
construction debris, fixtures, extraneous wiring, etc.
OSHA Training Requirements
OSHA TRAINING REQUIREMENTS
Missouri Law, 292.675 RSMO, requires the awarded contractor and its subcontractor(s) to provide a ten (10) hour Occupational Safety and Health Administration (OSHA) Construction Safety
Program (or a similar program approved by the Missouri Department of Labor and Industrial
Relations as a qualified substitute) for their on-site employees (laborers, workmen, drivers, equipment operators, and craftsmen) who have not previously completed such a program and are directly engaged in actual construction of the improvement (or working at a nearby or adjacent facility used for construction of the improvement). Information on this requirement can be found at the following website: http://www.moga.mo.gov/statutes/c200-299/2920000675.htm
SIDING, TRIM, AIR/WATER BARRIERS, and WINDOW REINSTALLATION
Item No. 1A, 1B, 2A
SIDING, TRIM, AIR/WATER BARRIERS, and WINDOW REINSTALLATION
These contract items are for furnishing and installing siding, disposal of existing siding, building wrap replacement, flashing and building wrap replacement, and window reinstallations on the
Doniphan Ranger Station. The existing windows are sound and have no significant damage, and it is the contractor's responsibility to remove the windows in a manner that they are not harmed and will be able to be reused. It is also expected that the interior casing and jambs will be able to be reused. But it is the Contractor’s responsibility to repair any damage that may occur to any windows, jambs, casing, or interior walls
Windows, siding, and any penetration shall be installed to prevent water and air penetration, and must be installed according to manufacturer’s instruction, these plans, sound construction techniques, and in a manner approved by the CO prior to construction. All building wrap seams and any penetration will be sealed with approved tape. Guides to proper installation can be found in the pamphlet "DuPont™ Tyvek® Weather Barrier Commercial Installation Guidelines" and the book
Water Management Guide by Lstiburek, Building Science Press.
Building wrap will be Tyvek® Commercial Wrap®, Tyvek®3” Tape, DuPont™ Commercial sealant, and DuPont™Flashing Systems or equal.
This contract includes properly applied paint in colors to match existing siding. Paint data and application methods will be submitted to the CO for approval prior to application.
Contractor is responsible for scheduling work and coordinating siding and window reinstallation with the CO to minimize workplace disruption. Contractor is responsible for preventing moisture penetration during construction and to provide any needed building security while windows and the wall are being worked on.
Optional Item No. 1C:
After the lower siding has been removed, the CO and the Contractor will determine whether or not the existing cement board vertical siding on the gables will need to be replaced.
Optional Item No. 1D:
After the existing siding has been removed, the CO and the Contractor will inspect the walls for signs of deterioration. Defective walls will be replaced with similar construction as exists, including exterior sheathing, studs, insulation, interior drywall, and finish.
REPAIR and/or REPLACEMENT OF ROOFING MATERIAL and ROOF
SHEATHING
Item No. 3A
REPAIR and/or REPLACEMENT OF ROOFING MATERIAL and ROOF SHEATHING
Contractor is responsible for troubleshooting the leak in the roof at the front entrance, assessing the extent of damage, furnishing new material, and installing the repair.
Preliminary assessment shows the leak is occurring where indicated on the drawings, is likely caused by breaks in the valley flashing and the EPDM membrane, and has resulted in the rotting of about 2 sq. ft of roof sheathing. It is thought that none of the structural members or any of the existing shingles need be replaced.
The contractor is responsible for doing their own assessment of the problem and coming up with a solution. Contractor is responsible to submit their plan for the repair and the material cut sheets to the CO for approval before work starts. Repair will also include trim and ceiling replacement on the porch and any required painting of the trim and ceiling replacement to match existing. All installation will be per manufacturer’s instructions, CO approvals, and sound construction techniques.
TROUBLESHOOTING OF THE EXISTING LULA ELEVATOR
Item No. 4A
TROUBLESHOOTING OF THE EXISTING LULA ELEVATOR
This contract item is for the troubleshooting of the existing elevator which is a Limited Use, Limited Access (LULA) Flexi-Lift model by Access Industries, Inc. with a GMV Hydro Lift
System T3010EN power unit.
The LULA hasn't been functioning for several years, and a preliminary assessment shows the cause to be an oil leak due to a faulty seal and not a malfunction of the mechanical and electrical systems.
It is the responsibility of the Contractor to verify and troubleshoot what the problem is. The Forest
Service has the original installation manual and plans. A Report of the Contractor's findings on the problems, suggested repair, and costs will be given to the CO for approval.
REPAIRING OF THE EXISTING ELEVATOR
Optional Item No. 4B
REPAIRING OF THE EXISTING ELEVATOR
At the convenience of the CO, the Contractor's troubleshooting report from Item No. 4A will be the basis of this optional Item No. 4B, Repair of the Existing Elevator. If the scope of the needed repairs is significantly different from the preliminary assessment by the Forest Service or if the original bid price on Item No. 4B is significantly different from the Report from Item No. 4A, this price may be renegotiated.
The Contractor will furnish and install all required repairs and required maintenance per the Item
No. 4A, so the elevator works.
All installation must be according to manufacturer’s instruction, these plans, sound construction techniques, and in a manner approved by the CO prior to construction. All design analysis, cut sheets, shop drawings, and product data will be submitted for approval by the CO. Contractor is responsible for scheduling work with the CO to minimize workplace disruption.
The repair will be done by a properly licensed elevator technician. Submit qualifications to the CO for approval.
This repair will also include the annual required safety inspection and certification.
Contractor is responsible for proper disposal of any replaced material and for clean-up, including oil spills.
ANALYSIS OF THE EXISTING HVAC INSTALLATION AND
RECOMMENDATIONS FOR REPAIR
Item No. 5A
ANALYSIS OF THE EXISTING HVAC INSTALLATION AND RECOMMENDATIONS FOR
REPAIR
This contract item is for the redesign, analysis, and troubleshooting of the HVAC (heating, ventilation, and air conditioning) system. Preliminary assessment of the system shows the original plans were not followed; there are no as built plans; the system wasn't commissioned, there are no operation manuals; the lower level single zoned system is causing excessive temperature variations;
there are no balancing dampers in any ducts, the building's existing HVAC has never been balanced; the HRVs (hear recovery ventilation)have never worked; and outside air exchange only works when the main AHUs are running.
There appears to be sufficient capacity of the A/C and heating systems and the two zoned upper level give acceptable comfort; but the problem is the lack of zoning in the lower level, lack of ability of the entire system to be balanced, and lack of outside air exchange.
The Contractor is responsible for the full assessment of the system's condition and problems, and to work with the CO to assure all HVAC problems are fully addressed.
The analysis of the existing system will include an complete HVAC analysis according to all applicable ASHRAE and ICBO Standards and , including but not limited to total heating and cooling capacity, air flow requirements for each room, duct sizes, fire dampers, ability to balance the system, indoor air quality, and outdoor air rates. This analysis will include actual measurements of the existing system. This item will include recommendations for repair and modifications of the existing system. Such recommendations will include, but not be limited to recommendations of making two zones in the lower level with VAVs, balancing dampers, proper functioning of the HRV and IAQ systems, CO2 sensors, and energy conservation. A Report will be given to the CO for approval which includes the analysis, recommendations, sketches, proposed product data, and cut sheets.
REPAIR AND MODIFICATION OF THE EXISTING HVAC SYSTEM
Item No. 5B
REPAIR AND MODIFICATION OF THE EXISTING HVAC SYSTEM
At the convenience of the CO, the Contractor's Report from Item No. 5A will be the basis of Item
No. 5B. If the scope of the needed repairs is significantly different from the preliminary assessment by the Forest Service or if the original bid price on Item No. 5B is significantly different from the
Report from Item No. 5A, this price may be renegotiated.
Repair and modification of the existing system will be the furnishing and installation of all required material; balancing of the system, documentation by measurement of compliance with ASHRAE
62.1; providing of required documentation in ASHRAE 62.1, Sec. 7.2 including balancing, operating and maintenance manual, HVAC control sequences, diagrams, design criteria, and as built drawings of the system.
All installation must be according to manufacturer’s instruction, sound construction techniques, and in a manner approved by the CO prior to construction. All design analysis, cut sheets, shop drawings, and product data will be submitted for approval by the CO prior to construction.
Contractor is responsible for notification and approval by the CO of the proposed schedule and any limitation that repair of the HVAC will impose on the ability of the building to be used.
Optional Item No. 5C:
REPLACEMENT OF THE EXISTING FURNANCES AND AIR HANDLING UNITS.
The contractor will provide itemized prices for total replacement of the existing furnaces, IAQ and other HVAC systems. This option will include a cost benefit analysis of the proposed replacements.
Replacement furnaces will have a minimum AFUE of 90%, CO2 controls for IAQ, other HVAC, and other energy saving equipment.
All design analysis, cut sheets, sketches, and product data will be submitted for approval by the CO.
At the convenience of the CO, this Repair and Modification of the existing HVAC system may be negotiated as a substitute for Items No. 5B.
CONVERT THE EXISTING EMERGENCY LIGHT FIXTURES TO WORK
WITH THE EXISTING SWITCHES
Item No. 6A
CONVERT THE EXISTING EMERGENCY LIGHT FIXTURES TO WORK WITH THE
EXISTING SWITCHES
This contract item is for the conversion of the existing emergency lights fixtures to work as the rest of the fixtures and to be able to turn them off with the existing switches. Fixtures in the stair well
(Rm. 15) will have added three-way switches if currently lacking.
It is expected that the existing light fixtures and bulbs can be reused. Included are the furnishing, layout, and installation of any required wiring, switches removal, wall and finish repair, and disposal of the emergency ballasts and batteries.
Work will be performed by a licensed electrician in compliance with NEC and all applicable codes, following manufacture’s recommendations, and submitted of and approval of a plan and schedule by the CO.
CONVERTING THE EXISTING FIXTURES TO OPERATE AT THREE
LIGHTING LEVELS
Optional Item No. 6B
CONVERTING THE EXISTING FIXTURES TO OPERATE AT THREE LIGHTING LEVELS
At the convenience of the CO this optional bid will be awarded.
The Contractor will submit prices to convert the existing 3 bulb, 2x4 fluorescent light fixtures in
Rooms 5, 6, 11, 17, 18, 19, 20, 32, 33, 36, 37, 39, 40, 45, 46, and 47 to be able to operate with one, two, or three bulbs by replacing the current single switches with two single throw switches and by splitting ballasts and rewiring. All the 2 bulb 2x2 fixtures in the corridors will have alternate fixtures connected to separate switches to allow only half the fixtures to be operated when desired.
Work will be performed by a licensed electrician in compliance with NEC and all applicable codes, following manufactures’ recommendations, and approval by the CO of submitted product data, shop drawings, cut sheets and a plan and schedule.
FURNISH AND INSTALL INSULATION IN LOWER LEVEL EXTERIOR
Item No. 7A
FURNISH AND INSTALL INSULATION IN LOWER LEVEL EXTERIOR WALLS
This contract item is for the furnishing and installation of insulation in the indicated walls.
The existing walls to have insulation installed are all 2x4 stud walls with finished 5/8" drywall.
Preliminary assessment by the Forest Service indicates that the best method to insulate these walls would be with blown or spray insulation through small holes drilled in the drywall.
The Contractor will submit, for approval, a work plan indicating the exact material and method used. Included will be recommendations, product data, shop drawings, cut sheets, and a plan and schedule. Contractor is responsible for working with the CO to schedule work and coordinating with the building occupants to minimize workplace disruption.
These submittals will be approved by the CO before construction.
FURNISH, INSTALL, AND REINSTALLATION OF ATTIC INSULATION
Optional Item No. 8A
FURNISH, INSTALL, AND/OR REINSTALLATION OF ATTIC INSULATION
This optional contract item is for the furnishing, installation, and reinstallation of the ceiling insulation.
The building was designed for R40 ceiling insulation throughout. 12" of fiberglass batting was installed in most areas. Due to incomplete installation in the original construction contract in 2003, an estimated 1000 sq. ft. of this insulation was improperly installed or was not installed at all. Some of the improperly installed insulation may be reused and properly placed, and other insulation must be furnished. All installed insulation will be 12" of fiberglass batt unless insulation is proposed and approved by the CO. Installed insulation will envelop the entire area, and will be cut and fit tightly around obstructions, trusses, and ductwork throughout the ceiling area.
Access to the attic is through a 2'x3' hatch in Rm. 05.
Work will follow manufactures’ recommendations, and the CO will approve submitted product data, shop drawings, cut sheets, and a plan and schedule before construction.
CIM-0905-15F-190-0905-04
INSTALLATION OF DRAFTSTOPPING WALLS IN THE ATTIC
Item No. 9A
INSTALLATION OF DRAFTSTOPPING WALLS IN THE ATTIC
This contract item is for the furnishing and installation of proper draftstops in the attic to comply with fire rated construction requirement in attics.
Material, installation, and locations will follow IBC 717.4 with a maximum horizontal area of 3000
sq. ft. Suitable material will be ½” drywall or 3/8” OSB on one side of the roof trusses with added studs where needed. The required doors will be a minimum of 30” x 48” OSB with spring hinges.
Access for material access will require removal of ceiling drywall or removal of gable panel, and replacement and matching finishing of any removed material.
Work will follow manufactures’ recommendations, and the CO will approve submitted product data, shop drawings, cut sheets, and a plan and schedule before construction.
CIM-0905-15F-190-0905-04
MOBILIZATION
Item No. 10A
MOBILIZATION
This work consists of moving personnel, equipment, material, and incidentals to the project and performing all work necessary before beginning work at the project site. Mobilization includes the obtaining of permits, insurance, and bonds.