Section B - Schedule of Items.pdf
PDF 78 KB Posted
- Attached to
- RECOVERY* Water Distribution System & Restroom Bldg Replacement - Pisgah National Forest, NC
- Solicitation number
- AG-4419-S-10-0590
About this file
Section B - Schedule of Items
View the file
Other files
| File | Type | Posted |
|---|---|---|
| North Mills Sign in Sheet.pdf | ||
| SF30 - Amendment 2.pdf | ||
| SF30 Amendment 1.pdf | ||
| Exhibit 1 - Drawings.pdf | ||
| Attachment 1 - Specifications.pdf | ||
| Section B1 - SOI Supp Instructions.doc | DOC document | |
| Section A - SF 1442.pdf | ||
| Attachment 2 - Wage Determination.doc | DOC document | |
| Sections C thru M - Solicitation.doc | DOC document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BID SCHEDULE
MILLS RIVER CAMPGROUND
WASTEWATER TREATMENT PLANT
WATER DISTRIBUTION CENTER &
RESTROOM BUILDINGS REPLACEMENT PROJECT
Item No. Description
Method of Measurement Qty Unit Unit Price Total Price
1 Mobilization & Bonding LSQ 1 LS $ (Not to Exceed 5% of Bid)
2 Clearing, Grubbing and Disposal LSQ 1 LS $ (All Locations)
3 Demolition and Disposal
A. Existing Treatment Plant and Related LSQ 1 LS $
B. Existing Restroom Building LSQ 1 LS $
C. Wellhouse Selective Building LSQ 1 LS $ Demolition and Patching
D. Miscellaneous Demolition LSQ 1 LS $ (MDP, Yard Hydrants, Etc.)
4 Treatment Plant Construction
A. Access Road ABC Stone Surfacing AQ 200 TONS $ $ (Construction Equipment Compaction)
B. 12" Thk. Monolithic Slab, including DQ 103 CY $ $ turndowns and steel reinforcement
1. #57 stone fill DQ 100 TONS $ $
2. 4" Perforated PVC Drainline DQ 300 LF $ $
3. 4" Sch. 40 PVC Drain Outlet Pipe AQ 85 LF $ $
C. Installation of 15,000 gallon Dual-Train LSQ 1 LS $ Treatment Plant
D. Influent/effluent Piping
1. 3" & 4" D.I.P./PVC Influent Piping DQ 24 LF $ $
2. 6" D.I.P./PVC Effluent Piping AQ 225 LF $ $
E. Generator System `
1. Concrete Pad DQ 1.75 CY $ $
Item No. Description
Method of Measurement Qty Unit Unit Price Total Price
2. 250 gal. Aboveground Propane Tank LSQ 1 LS $
3. U.G. Piping to Generator AQ 10 LF $ $
4. 48 kW Liquid Cooled Generator LSQ 1 LS $ including Trasfer Switch
F. Electrical
1. Construction of MDP Mounting Board LSQ 1 LS $
2. Installation of Meter Base, Load Center, LSQ 1 LS $ Wireway
3. Installation of Branch Wiring in Conduit LSQ 1 LS $
4. Installation of 2-1/2" PVC U.G. Conduit AQ 230 LF $ $ from Pole Mounted Transformer to Meter Base (Common Trench w/ Effluent Piping)
G. Installation of Pump Station
1. Installation of Precast Concrete Wetwell LSQ 1 LS $
2. Installation of Duplex Grinder Pumps LSQ 1 LS $ Including J-Box & Control Panel
3. Installation of U.G. Electrical from J-Box to DQ 85 LF $ $ Control Panel @ MDP in 2" PVC Conduit
H. Installation of 6 Ft. High Security Fence AQ 386 LF $ $ with 3-strand barb wire
1. Installation of 12' Road Gate DQ 1 EA $ $
5 WellHouse Upgrading
A. Storage Room Addition
1. Concrete Foundation DQ 3.5 CY $ $
2. Block Walls DQ 200 SF $ $
3. Metal Doors and Hardware LSQ 1 LS $
4. Roof Framing LSQ 1 LS $
B. New Roofing, Entire Structure LSQ 1 LS $ (40 Year Shingles)
C. New Plumbing LSQ 1 LS $
D. New Electrical LSQ 1 LS $
E. Rock Veneer (Addition Only) DQ 200 SF $ $ (Match Existing)
Method of Measurement Qty Unit Unit Price Total Price
6 Water System Construction
A. Installation of Waterlines
1. 3" SDR-21 PVC AQ 225 LF $ $
2. 3" SCh. 80 PVC (Insulated) AQ 70 LF $ $
3. 2" SDR-21 PVC AQ 930 LF $ $
4. 1-1/2" SDR-9 HDPE AQ 1300 LF $ $
5. 3/4" SDR-9 HDPE AQ 945 LF $ $
6. Shop Fabricated Waterline Hangers AQ 13 EA $ $
B. Installation of Valves, including Valve Boxes
1. 3" size Gate Valve AQ 1 EA $ $
2. 2" size Gate Valve AQ 6 EA $ $
3. 1-1/2" size Curb Stop AQ 5 EA $ $
4. 3/4" size Curb Stop AQ 9 EA $ $
C. Hydrants
1. Host Site Hydrant AQ 3 EA $ $
2. Accessible Yard Hydrant AQ 2 EA $ $
3. Non-Accessible Yard Hydrant AQ 3 EA $ $
4. Treatment Plant Hydrant AQ 1 EA $ $ Including Double-Check Valve
7 8-Unit Bath-House Construction
A. Bath-House Building, complete including LSQ 1 LS $ Perimeter Sidewalks
B. Construction of 6' wide Access Sidewalk DQ 290 SF $ $
C. Installation of 6" Sch. 40 PVC Sewerline AQ 230 LF $ $
D. Installation of 4" Sch. 40 PVC Sewerline AQ 50 LF $ $
E. Installation of Sewer Cleanouts and AQ 3 EA $ $ Host Site Hook Up
Method of Measurement Qty Unit Unit Price Total Price
8 Site Electrical Modifications
A. Installation of Managers Site Meter Base LSQ 1 LS $
B. Installation of new MDP for New LSQ 1 LS $ Bath-House & Host Site, complete including Meter Base, Disconnects and Wireway
C. Installation of U.G service to New AQ 300 LF $ $ Bath-House in 2-1/2" Sch. 40 PVC Conduit
D. Installation of Host Site RV-Pedestals AQ 2 EA $ $ (Managers Site and Site #23)
E. Underground Wiring to RV-Pedestals
1. (2) #2, (1) #4 N., and (1) #6 G. AQ 260 LF $ $
2. (3) #6, (1) #8 G. in 1-1/2" PVC AQ 40 LF $ $ (Managers Site)
9 Sedimentation and Erosion Control
A. Installation of Silt Fences AQ 1420 LF $ $
B. Installation of Hay Bales AQ 50 EA $ $
C. Seeding & Mulching All Disturbed Areas LSQ 1 LS $
TOTAL BASE BID PRICE $
ALTERNATE BID ITEMS
Item No. Description Method of
Measurement Qty Unit A. Construction of Roof Shelter
1. Structural Steel LSQ 1 LS $
2. Prefabricated Roof LSQ 1 LS $ Trusses, Sheating and Facias
3. 40 Year Shingles DQ 21.3 SQ $ $
B. Installation of RV-Electrical Pedestal AQ 1 EA $ $ Camping Site #14
1. Installation of (3) #6 & (1) #8 G. in AQ 175 LF $ $ 1-1/2" PVC Conduit (Site # 14)
TOTAL ALTERNATE BID PRICE $
GRAND TOTAL $
* Any other item of work shown on the drawings or required by the specifications shall be considered incidental to the bid items shown, and no additional payment will be made.