Section B - Schedule of Items.pdf

PDF 78 KB Posted

Attached to
RECOVERY* Water Distribution System & Restroom Bldg Replacement - Pisgah National Forest, NC
Solicitation number
AG-4419-S-10-0590
Issued by

About this file

Section B - Schedule of Items

View the file

Other files

File Type Posted
North Mills Sign in Sheet.pdf PDF
SF30 - Amendment 2.pdf PDF
SF30 Amendment 1.pdf PDF
Exhibit 1 - Drawings.pdf PDF
Attachment 1 - Specifications.pdf PDF
Section B1 - SOI Supp Instructions.doc DOC document
Section A - SF 1442.pdf PDF
Attachment 2 - Wage Determination.doc DOC document
Sections C thru M - Solicitation.doc DOC document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BID SCHEDULE

MILLS RIVER CAMPGROUND

WASTEWATER TREATMENT PLANT

WATER DISTRIBUTION CENTER &

RESTROOM BUILDINGS REPLACEMENT PROJECT

Item No. Description

Method of Measurement Qty Unit Unit Price Total Price

1 Mobilization & Bonding LSQ 1 LS $ (Not to Exceed 5% of Bid)

2 Clearing, Grubbing and Disposal LSQ 1 LS $ (All Locations)

3 Demolition and Disposal

A. Existing Treatment Plant and Related LSQ 1 LS $

B. Existing Restroom Building LSQ 1 LS $

C. Wellhouse Selective Building LSQ 1 LS $ Demolition and Patching

D. Miscellaneous Demolition LSQ 1 LS $ (MDP, Yard Hydrants, Etc.)

4 Treatment Plant Construction

A. Access Road ABC Stone Surfacing AQ 200 TONS $ $ (Construction Equipment Compaction)

B. 12" Thk. Monolithic Slab, including DQ 103 CY $ $ turndowns and steel reinforcement

1. #57 stone fill DQ 100 TONS $ $

2. 4" Perforated PVC Drainline DQ 300 LF $ $

3. 4" Sch. 40 PVC Drain Outlet Pipe AQ 85 LF $ $

C. Installation of 15,000 gallon Dual-Train LSQ 1 LS $ Treatment Plant

D. Influent/effluent Piping

1. 3" & 4" D.I.P./PVC Influent Piping DQ 24 LF $ $

2. 6" D.I.P./PVC Effluent Piping AQ 225 LF $ $

E. Generator System `

1. Concrete Pad DQ 1.75 CY $ $

Item No. Description

Method of Measurement Qty Unit Unit Price Total Price

2. 250 gal. Aboveground Propane Tank LSQ 1 LS $

3. U.G. Piping to Generator AQ 10 LF $ $

4. 48 kW Liquid Cooled Generator LSQ 1 LS $ including Trasfer Switch

F. Electrical

1. Construction of MDP Mounting Board LSQ 1 LS $

2. Installation of Meter Base, Load Center, LSQ 1 LS $ Wireway

3. Installation of Branch Wiring in Conduit LSQ 1 LS $

4. Installation of 2-1/2" PVC U.G. Conduit AQ 230 LF $ $ from Pole Mounted Transformer to Meter Base (Common Trench w/ Effluent Piping)

G. Installation of Pump Station

1. Installation of Precast Concrete Wetwell LSQ 1 LS $

2. Installation of Duplex Grinder Pumps LSQ 1 LS $ Including J-Box & Control Panel

3. Installation of U.G. Electrical from J-Box to DQ 85 LF $ $ Control Panel @ MDP in 2" PVC Conduit

H. Installation of 6 Ft. High Security Fence AQ 386 LF $ $ with 3-strand barb wire

1. Installation of 12' Road Gate DQ 1 EA $ $

5 WellHouse Upgrading

A. Storage Room Addition

1. Concrete Foundation DQ 3.5 CY $ $

2. Block Walls DQ 200 SF $ $

3. Metal Doors and Hardware LSQ 1 LS $

4. Roof Framing LSQ 1 LS $

B. New Roofing, Entire Structure LSQ 1 LS $ (40 Year Shingles)

C. New Plumbing LSQ 1 LS $

D. New Electrical LSQ 1 LS $

E. Rock Veneer (Addition Only) DQ 200 SF $ $ (Match Existing)

Method of Measurement Qty Unit Unit Price Total Price

6 Water System Construction

A. Installation of Waterlines

1. 3" SDR-21 PVC AQ 225 LF $ $

2. 3" SCh. 80 PVC (Insulated) AQ 70 LF $ $

3. 2" SDR-21 PVC AQ 930 LF $ $

4. 1-1/2" SDR-9 HDPE AQ 1300 LF $ $

5. 3/4" SDR-9 HDPE AQ 945 LF $ $

6. Shop Fabricated Waterline Hangers AQ 13 EA $ $

B. Installation of Valves, including Valve Boxes

1. 3" size Gate Valve AQ 1 EA $ $

2. 2" size Gate Valve AQ 6 EA $ $

3. 1-1/2" size Curb Stop AQ 5 EA $ $

4. 3/4" size Curb Stop AQ 9 EA $ $

C. Hydrants

1. Host Site Hydrant AQ 3 EA $ $

2. Accessible Yard Hydrant AQ 2 EA $ $

3. Non-Accessible Yard Hydrant AQ 3 EA $ $

4. Treatment Plant Hydrant AQ 1 EA $ $ Including Double-Check Valve

7 8-Unit Bath-House Construction

A. Bath-House Building, complete including LSQ 1 LS $ Perimeter Sidewalks

B. Construction of 6' wide Access Sidewalk DQ 290 SF $ $

C. Installation of 6" Sch. 40 PVC Sewerline AQ 230 LF $ $

D. Installation of 4" Sch. 40 PVC Sewerline AQ 50 LF $ $

E. Installation of Sewer Cleanouts and AQ 3 EA $ $ Host Site Hook Up

Method of Measurement Qty Unit Unit Price Total Price

8 Site Electrical Modifications

A. Installation of Managers Site Meter Base LSQ 1 LS $

B. Installation of new MDP for New LSQ 1 LS $ Bath-House & Host Site, complete including Meter Base, Disconnects and Wireway

C. Installation of U.G service to New AQ 300 LF $ $ Bath-House in 2-1/2" Sch. 40 PVC Conduit

D. Installation of Host Site RV-Pedestals AQ 2 EA $ $ (Managers Site and Site #23)

E. Underground Wiring to RV-Pedestals

1. (2) #2, (1) #4 N., and (1) #6 G. AQ 260 LF $ $

2. (3) #6, (1) #8 G. in 1-1/2" PVC AQ 40 LF $ $ (Managers Site)

9 Sedimentation and Erosion Control

A. Installation of Silt Fences AQ 1420 LF $ $

B. Installation of Hay Bales AQ 50 EA $ $

C. Seeding & Mulching All Disturbed Areas LSQ 1 LS $

TOTAL BASE BID PRICE $

ALTERNATE BID ITEMS

Item No. Description Method of

Measurement Qty Unit A. Construction of Roof Shelter

1. Structural Steel LSQ 1 LS $

2. Prefabricated Roof LSQ 1 LS $ Trusses, Sheating and Facias

3. 40 Year Shingles DQ 21.3 SQ $ $

B. Installation of RV-Electrical Pedestal AQ 1 EA $ $ Camping Site #14

1. Installation of (3) #6 & (1) #8 G. in AQ 175 LF $ $ 1-1/2" PVC Conduit (Site # 14)

TOTAL ALTERNATE BID PRICE $

GRAND TOTAL $

* Any other item of work shown on the drawings or required by the specifications shall be considered incidental to the bid items shown, and no additional payment will be made.

Sheet1

File details come from the government source that posted it. Updated .